Infolets Related to Work Execution

The Operations infolet and the Operations Scheduled Versus Actual infolet shows key metrics at either the plant level or the work area or work center level that you have selected using the View By icon.

Operations Infolet

The Operations infolet is a text-layout-based infolet that displays the count of operations which are Past Due, Ready and Reject, belonging to the selected work area or work center.

The infolet shows three key metrics:

Past Due: Displays the count of operations having the following:

  • Operation type is specified as in-house.

  • In Ready or Reject status.

  • Scheduled completion date of the operation is past due the current date.

  • Operation type is specified as in-house.

Reject: Displays the count of operations having the following:

  • Operation type is specified as in-house.

  • In Reject status.

Ready: Displays the count of operations having the following:

  • Operation type is specified as in-house.

  • In Ready status.

Each count drills down to the Review Dispatch List page with the appropriate query criteria filtered. You can search for your required operation here and track its progress.

Note: The Operations infolet can't be flipped or expanded.

Operations Scheduled Versus Actual Infolet

The Operation Scheduled Versus Actual infolet is a ring-chart-based infolet.

It shows the following two kinds of metrics:

Scheduled Quantity: Displays the total quantity scheduled for production in the current shift. This is the sum of all work order quantities against operations which have the following:

  • Scheduled completion date of the operation is within the current shift of the plant calendar.

  • Operation type is specified as in-house.

Operation Quantity by Dispatch Status: The ring segments are color-coded to represent operation quantities in their corresponding dispatch status such as Ready, Complete, Reject and Scrap.

The Not Ready metric calculation is derived as the total of Ready, Scrapped, Rejected, and Completed quantity deducted from the Scheduled total quantity. If Not Ready is calculated as negative in any of the operations, it's displayed as zero.

You can view more details regarding the operations in your work center and the progress of each work center based on the shift you select by clicking the Expand icon on the infolet.

The expanded view of this infolet is a list of records which displays the operation quantities and their completion progress by work center. This list is sorted in the ascending order of the least performing work centers. The Progress percentage is calculated as Completed Quantity divided by Total quantity.

Each metric on the infolet in either the front view or expanded view directs you to the Review Dispatch List page with the appropriate query criteria filtered. You can search for your required operation here and track its progress.