Best Practices for Setting Up Replenishment Plans

You can configure replenishment plans in various ways to meet your business requirements.

This table explains the various configurations that you can use for your replenishment plans:

Plan Type

Plan Purpose

Planning Horizon

Planning Time Level

Frequency of Plan Runs

Selected Check Boxes

Release from Plan?

Strategic replenishment plan

To estimate how well your policies meet anticipated demands

6 months to 1 year

Week or period

Weekly or monthly

Generate forecast, Calculate policy parameters, and Calculate replenishments check boxes

No

Integrated replenishment plan

To monitor and execute policies according to the generated forecast

Optionally, you can use a weekly demand plan, a weekly replenishment plan, or an external forecast schedule for the forecast.

Optionally, you can use a policy comparison or policy calculation plan for the policy parameters.

Optionally, you can use the integrated replenishment plan to also rebalance the inventory by selecting the Rebalance inventory check box. However, this use case isn't common.

100 days or less

Day

Daily

Generate forecast, Calculate policy parameters, and Calculate replenishments check boxes

Yes

Automated execution plan

To incrementally calculate replenishments according to a schedule and actual demands (sales orders, transfer orders, and inventory position)

You must use another replenishment plan for the policy parameters.

You can't select another replenishment plan, a demand plan, or an external forecast schedule for the demand forecast.

15 days or less

Day

Daily or intraday

Enable for incremental planning and Calculate replenishments check boxes

Yes

Policy comparison plan or policy calculation plan

To compare or calculate policies

You must feed the calculated policies to an integrated replenishment plan or automated execution plan.

6 months

Week

Monthly

Generate forecast and Calculate policy parameters check boxes

No

Inventory rebalancing plan

To rebalance inventory among the item-location combinations in the clusters of a replenishment plan

You must use another replenishment plan with a planning time level of week, month, or period to calculate the policy parameters.

You must use another replenishment plan, a demand plan, or an external forecast schedule for the demand forecast. The planning time level of the other plan can be week, month, or period.

100 days or less

Day

Daily

Calculate replenishments and Rebalance inventory check boxes

Yes

Optionally, if you've selected the Calculate replenishments check box, you can also configure the replenishment plan for end item substitution and supersession.