Example of Safety Stock Planning with Lead Time Constraints

This example shows how the supply planning process plans safety stock in a constrained supply plan with a lead time constraint.

Safety Stock Planning with Lead Time Constraint

For this example, let's use these parameters:

  • Nonworking days: Days 6, 7, 13, and 14

  • Purchasing lead time: 3 days

  • Enforce Purchasing Lead Time item attribute: Yes

Safety Stock Planning with Lead Time Constraint

In this scenario,

  • The constrained supply plan enforced the purchase lead time of Item C.

  • The planning process created supply on Day 4, which is the plan start date plus the lead time.

  • Safety stock from Day 1 to Day 3 wasn't met because the purchasing lead time was enforced by the plan for Item C.