Gantt Chart

Use the Gantt Chart to view orders and resource requirement durations on a timeline along with the calculated attributes. You can also interactively modify the planned dates of a supply or resource requirement from the Gantt Chart.

You can only open the Gantt Chart in context by drilling to it from another table. Also, the Gantt chart always opens in a different pane than the pane from which you drilled from. For example, if you're using a single pane layout and open the Gantt Chart from the Supplies and Demands table, the page layout switches to a double pane (top and bottom) layout. In this situation, the Gantt chart opens in the bottom pane.

How You Drill to the Gantt Chart

You can only open the Gantt Chart in context by drilling to it from another table. Here are the tables from which you can drill to the Gantt Chart.

Drill to Context

What is Displayed in the Gantt Chart

Supplies and Demands

Supply orders

Resource Requirements

Resource requirements

Cells corresponding to these measures in the Material Plan, Build Plan, or a user-defined table:

  • Total Supply

  • Planned Orders

  • Scheduled Receipts

  • Purchase Orders

  • Purchase Requisitions

  • Transfer Orders

  • Work Orders

  • Dependent Demands

Supply orders

Cells corresponding to the Resource Requirements measure in the Resource Plan, Build Plan, or a user-defined table.

Resource requirements

Drill From the Gantt Chart to Other Tables

From the Gantt Chart, here are the tables that you can drill to and what the tables display.

Drill From

Drill to Table

What the Table Displays

Supply bar

Supplies and Demands

Supply order details

Supply bar

Material Plan

Material plan for the item-organization

Supply bar

Items

Item corresponding to the supply

Supply bar

Item Structure

Item structure corresponding to the item of supply

Supply bar

Routings

Routing of the item of the supply

Supply bar

Suppliers

Suppliers for the item corresponding to the supply

Resource Requirement bar

Resources

Resource corresponding to the resource requirement

Resource Requirement bar

Resource Availability

Resource availability of the resource

Resource Requirement bar

Resource Plan

Resource plan for the resource corresponding to the resource requirement

Resource Requirement bar

Resource Requirements

Resource requirement details

List of Order Attributes You Can Display

You can display these order attributes in the left pane of your Gantt Chart:

Order Attribute

Automatically Displayed

Item

Yes

Organization

Yes

Order Number

Yes

Order Quantity

Yes

Order Type

Yes

Supplier

No

Supplier Site

No

Source Organization

No

Ship Method

No

Work Definition

No

Item Structure

No

Supply Bar and Resource Requirements Bar

Let's discuss the characteristics of the supply bar and the resource requirement bar in your Gantt Chart.

  • Supply bars span from the suggested start date to the suggested due date of the supply. If the suggested start and suggest due dates are the same, the supply bar appears as a thin line.

  • Resource requirement bars span from the bucket start date of the planning time bucket that contains the start date of the resource requirements to the bucket end date of the planning time bucket that contains the end date of the resource requirement.

Show Diagnostics

You can select from the Show Diagnostics drop-down list which diagnostic attributes to display for orders and resource requirements. These are the diagnostic attributes that you can display in your Gantt Chart:

  • Contributes to Demand Lateness

  • Contributes to Overload

  • Consumption Start Date

  • Need-by Date

  • Material Available Date

  • Earliest Start Date

  • Firm

Gantt Chart Actions

When you work in the Gantt Chart, there are some useful tool for you to use.

Action you can take from the Actions menu or the Gantt Chart toolbar

Result of the action

Move In

Moves the selected bar in by one planning time bucket.

Note: You can't move a bar from a less granular time bucket, such as week, to a more granular time bucket, such as day.

Move Out

Moves the selected bar out by one planning time bucket.

Zoom In

Zooms in the time line display. You can't zoom in below the planning time bucket level.

Zoom Out

Zooms out the time line display.

Refresh

Refreshes the content in the Gantt Chart.

Moving the Bars in the Gantt Chart

Here are some pointers about moving the bars in the Gantt Chart.

  • You can use the Move In and Move Out options in the toolbar or use the drag and drop action. However, you can't move a bar to another row.

  • The end date of the supply bar always snaps to the last working day of the planning time bucket that you move the bar to.

  • If you move a bar to a non-working day within the daily bucket portion of the plan horizon, you will be asked if you want to move it to the previous working day.

  • The time durations of the bars remain the same as you move them across planning time buckets. A replan or recalculate action can change the durations.