Enable Display of Use-Up Date

When you remove or replace a component, you can view and select a use-up date specified in a supply plan as the effective date for the affected object.

To make the relevant use-up dates available for selection on selecting the Calculate Use-Up Date action (on the Affected Objects tab of the change in the Product Development work area), you must do the following:

  • Ensure that the Supply Chain offering is enabled and in Implemented status.
    1. In the Setup and Maintenance work area, select the Supply Chain Planning offering.
    2. Click Actions > Edit Implementation Status. Make sure the implementation status is set to Implemented.
  • Indicate which supply plan is to be referenced.
    1. In Supply Chain Planning, go to the Supply Planning work area.
    2. Use the Manage Plans task to find and open the plan you want to reference.
    3. On the Edit Plan Options page, select the Use as a reference plan for fulfillment systems checkbox.
    4. Save your changes.