You can enable multithreading for measure data disaggregation for all demand, demand
and supply, replenishment, sales and operations, or supply plans.
Before you start
You may need to work with someone who has administration
privileges to make these profile-related changes.
Here's what to do
-
In the Demand Management, Demand and Supply Planning, Plan Inputs, Planning
Central, Replenishment Planning, Sales and Operations Planning, or Supply
Planning work area, on the Tasks panel tab, under Configuration, select
Manage Planning Profile Options.
The Manage Planning Profile Options page opens.
-
Search for the SCP_PARAMETER_OVERRIDES profile option code.
-
If the SCP_PARAMETER_OVERRIDES profile option code exists, then click the
New icon.
A new row appears for the profile value.
-
Add the profile value as follows:
-
Click Save and Close.
-
If the SCP_PARAMETER_OVERRIDES profile option code doesn't exist, then follow
these steps:
-
In the Setup and Maintenance work area, go to the Manage
Profile Options task.
The Manage Profile Options page opens.
-
Click New.
The Create Profile Option page opens.
-
Create the profile option as follows:
- Profile Option Code: SCP_PARAMETER_OVERRIDES
- Profile Display Name: SCP_PARAMETER_OVERRIDES
- Application: Planning Common
- Module: Planning Common
- Start Date: Current date
Leave the remaining fields blank.
-
Click Save and Close.
-
For the profile option levels for the profile option, select the check boxes
under the Enabled and Updatable
columns for both the Site and User levels.
-
Click Save and Close.
-
In your work area, open the Manage Planning Profile Options page.
-
Search for the SCP_PARAMETER_OVERRIDES profile option code.
-
Set the profile level and value as previously explained.
-
Click Save and Close.