Changeover Rules
Use changeover rules to specify the time it will take to prepare a resource for the production of an item. Preparation activities are cleanups or setups that must be done when the item being produced on a resource changes. To manage changeover rules, open the actions menu for an organization and click the Changeover Rules option.
Define a Changeover Rule
-
On the Manage Changeover Rules page, click Add.
-
Specify a sequence number to indicate when the changeover occurs. You can use decimal values.
-
Select either the resource group or the work center and resource. You can edit all fields using the REST service.
-
Select the attribute on which the changeover will occur. If you leave the Attribute field blank, the rule applies to all attributes.
-
Select the current and changed attribute values. If you leave the From and/or To fields empty, the rule applies to all from and/or all to attribute values.
-
Specify the duration of the changeover and the duration unit of measure.
-
Specify the cost of the changeover. It's considered when the user-defined attribute sequence is set to Reverse.
During schedule calculation, if multiple changeover rules are applicable between two work order operations, then the rules with a lower sequence number are applied. Hence the more specific rules with respect to resources, attributes, and attribute values should be assigned lower sequence number and the more general catch-all type rules should be assigned higher sequence number.
Changeover rules can also be defined using the Supply Chain Planning/Production Scheduling Organizations/Changeover Rules REST service. To know more, refer to the REST API for Oracle Fusion Cloud SCM guide.