Calendars Used to Calculate Dates
In the Supplies and Demands view, there are different calendars used to calculate the various dates. This topic discusses the different calendars and the calendar selection hierarchy used by the planning process to calculate dates.
For each calendar hierarchy listed in this topic, the planning process searches for an associated calendar. When an associated calendar is found, the planning process stops and the other levels in the hierarchy aren't checked.
For example, to calculate the start date of purchase supplies, the planning process first looks for the Supplier Site Capacity Calendar in the Approved Supplier List (ASL). If the planning process doesn't find a Supplier Site Capacity Calendar, then the process defaults to a 24 hour, 7 days a week calendar to calculate the start date of purchase supplies.
The following lists the calendars and the calendar hierarchy the planning process uses to calculate dates. In cases where the calendar association appears in the Review Planning Calendar Associations UI, the applicable calendar type and assignment type is listed.
-
Supplier Capacity Calendar (SCC): Calendar used to calculate the start date of purchase supplies.
Hierarchy of Calendar Selection
Calendar Type
Assignment Type
1. SSC = Supplier Site Capacity Calendar in the ASL
N/A
N/A
2. 24 Hours, 7 Days a Week
N/A
N/A
View the Supplier Capacity Calendar in the Suppliers UI. When copying supplier item records into the plan and the Supplier Capacity Calendar isn't found, the Supplier Site Calendar from the Supply Network Model is copied into the Supplier Capacity Calendar.
-
Supplier Shipping Calendar (SSC) : Calendar used to calculate the shipment date of purchase supplies.
Hierarchy of Calendar Selection
Calendar Type
Assignment Type
1. SSC = Carrier/Supplier/Supplier Site Calendar
Carrier
10 - Carrier and Supplier Site
2. Supplier/Supplier Site Shipping Calendar
Shipping
5 - Supplier Site
3. Carrier/Supplier Calendar
Carrier
7 - Carrier and Supplier
4. Supplier Shipping Calendar
Shipping
1 - Supplier
5. 24 Hours, 7 Days a Week
N/A
N/A
-
Organization Receiving Calendar (ORC): Calendar used to calculate the dock date at destination and receiving organization.
Hierarchy of Calendar Selection
Calendar Type
Assignment Type
1. ORC = Carrier/Organization Calendar
Carrier
9 - Carrier and Organization
2. Organization Receiving Calendar
Receiving
3 - Organization
3. Organization Manufacturing Calendar (OMC)
N/A
N/A
5. 24 Hours, 7 Days a Week
N/A
N/A
-
Organization Manufacturing Calendar (OMC): Calendar used to calculate the order date and due date of purchase supplies. This calendar is used to calculate all dates of make supplies. You can view the Organization Manufacturing Calendar in the Supply Network Model UI.
Hierarchy of Calendar Selection
Calendar Type
Assignment Type
1. OMC = Organization Manufacturing Calendar
N/A
N/A
2. 24 Hours, 7 Days a Week
N/A
N/A
-
Organization Shipping Calendar (OSC): Calendar used to calculate the ship date at the source and shipping organization for transfer orders.
Hierarchy of Calendar Selection
Calendar Type
Assignment Type
1. OSC = Carrier/Organization Calendar
Carrier
9 - Carrier and Organization
2. Organization Shipping Calendar
Shipping
3 - Organization
3. Organization Manufacturing Calendar (OMC)
N/A
N/A
5. 24 Hours, 7 Days a Week
N/A
N/A
-
Customer Receiving Calendar (CRC): Calendar used to calculate the arrival date on end demands (sales orders).
Hierarchy of Calendar Selection
Calendar Type
Assignment Type
1. CRC = Carrier/Customer/Customer Site Calendar
Carrier
11 - Carrier and Customer Site
2. Customer/Customer Site Receiving Calendar
Receiving
6 - Customer Site
3. Carrier/Customer Calendar
Carrier
8 - Carrier and Customer
4. Customer Receiving Calendar
Receiving
2 - Customer
5. 24 Hours, 7 Days a Week
N/A
N/A
-
Valid Transit Calendar (VTC): Calendar used to calculate transit days on demands and supplies.
Hierarchy of Calendar Selection
Calendar Type
Assignment Type
1. VTC = Carrier Transit Calendar
Carrier
4 - Carrier
2. 24 Hours, 7 Days a Week
N/A
N/A