Report Quantities

After starting a work order operation at a workstation, you can report completed and rejected quantities.

For serial-tracked operations, you can scan or enter the serial number and work on the operation. Once finished, you can report completion or rejection.

For operations that are not serial tracked, you can enter completion and rejection quantities under Quantity Reporting. The Production Summary section shows the completed, rejected, and target quantities. The real-time target is the quantity a user should have produced based on the elapsed execution time and the cycle time of the operation.

If the operation uses a quality inspection plan, then you are required to enter the inspection results for automatic completion or rejection of quantities.