Exceptions in a Constrained Supply Plan
You can evaluate a plan and prioritize the manual changes to perform based on the exceptions generated from a plan. Oracle Supply Planning provides several exception messages for constraint-based supply planning.
You can drill down on an exception to obtain more detailed information about the exception. These are the four types of exceptions for a constrained supply plan.
-
Demands at Risk Exceptions
-
Late Supply Exceptions
-
Overloaded Capacities Exceptions
-
Usage of Alternates and Substitutes Exceptions
Demands at Risk Exceptions
This table shows the demands at risk exceptions for unconstrained and constrained supply plans.
Exception |
Exception is generated for the following conditions: |
---|---|
Demand at Risk Due to Insufficient Lead Time |
Note:
All three conditions must be met before the planning process generates the exception. |
Demand at Risk Due to a Resource Capacity Shortage |
Resource availability is less than the resource requirements for the resource capacity measures of any resource used in making any supply that's end-pegged to the demand. |
Demand at Risk Due to a Supplier Capacity Shortage |
Supplier capacity availability is less than the supplier capacity required for the supplier capacity measures of any item that's end pegged to the demand. |
Late Supply Exceptions
This table shows the late supply exceptions for unconstrained and constrained supply plans.
Exception |
Exception is generated for the following conditions: |
---|---|
Late Supply Pegged to Forecast |
Days late is greater than 0 for the Days Late demand order attribute. This condition means that the demand could be at risk due to the late supply. |
Late Supply Pegged to Sales Order |
Days late is greater than 0 for the Days Late demand order attribute. This condition means that the demand could be at risk due to the late supply. |
Orders with Insufficient Lead Time |
Note:
All three conditions must be met before the planning process generates the exception |
Orders To Be Canceled |
The planning process detects a supply order that's not firm for which you don't need to satisfy demand or safety stock requirements. The planning process:
|
Orders To Be Rescheduled In |
The planning process detects a supply order that's not firm with an original due date that's later than the suggested due date. The planning process:
|
Orders To Be Rescheduled Out |
The planning process detects a supply order that's not firm with an original due date that's earlier than the suggested due date. The planning process:
|
Overload Capacities Exceptions
This table shows the overload capacity exceptions for unconstrained and constrained supply plans.
Exception |
Exception is generated for the following conditions: |
---|---|
Resource Overloaded |
Resource utilization percentage is greater than 100. |
Supplier Capacity Overloaded |
Supplier capacity utilization percentage is greater than 100. |
Use of Alternates and Substitutes Exceptions
This table shows the use of alternates and substitutes exceptions for only constrained supply plans.
Exception |
Exception is generated for the following conditions: |
---|---|
Order Sourced from Alternate Facility |
Alternate Facility Used attribute is set to True. The order is sourced from an alternate facility due to the material, resource, or lead time constraints. |
Order Sourced from Alternate Supplier |
Alternate Supplier Used attribute is set to True. The order is sourced from an alternate supplier (Rank 2 supplier and higher) due to the supplier capacity constraints. |
Planned Order Uses Alternate Work Definition |
Alternate Work Definition Used attribute is set to True. The planned order has used an alternate work definition due to the material, resource, or lead time constraints. |
Planned Order Uses Alternate Resources |
Alternate Resource Used attribute is set to True. The planned order has used an alternate resource due to the capacity constraints. |
Planned Order Uses Substitute Component |
Substitute Component Used attribute is set to True. The order has used a substitute component. The scenarios where this exception is generated are:
|