Schedule View Settings

Schedule view settings determine the data that's to be displayed in the Gantt chart in the schedule view UI.

Configure View Settings

  1. Select a default resource group for display in the Gantt chart. You can switch to another resource group later from the Gantt chart toolbar.

    Note: Limiting the number of resources to be displayed might improve application performance.
    Note: The selection of a default resource group can be done only after refreshing the schedule.
  2. Specify the default display horizon in terms of days. This allows to set the number of days the Gantt chart considers to display data when you open the schedule view.

  3. Specify how the labels for work order operations in the Gantt chart will be displayed. These are different combinations of item, work order, and operation that can be used as display label.
    • Work order and operation
    • Work order and item
    • Item and work order
    • Item and operation
  4. Specify how the resource labels will be displayed in the Gantt chart, Dispatch List, and Resource Utilization. Select any of these options that will be used as a resource label.
    • Resource code
    • Resource name
  5. Specify the time in the field Flow Schedule Aggregation in Hours. Individual flow schedules that end within the specified number of hours are merged in the Gantt chart and displayed as an aggregate taskbar. Only the last operation in a flow work definition is included in the aggregation. The aggregation logic gets applied from schedule horizon start. The underlying, individual flow schedules are still visible in the tabular display.