Edit a Flow Schedule

To edit a flow schedule for flow manufacturing:

  1. Navigate to the Work Execution Overview work area.
  2. From the Actions menu, select Manage Flow Schedules.

    The Production Lines page opens.

  3. Select a production line and click View Flow Schedules Summary to review the flow schedule summary of a production line.

    The Production Schedule Summary page opens.

  4. Select a flow schedule for a specific day and click the date link.

    The Flow Schedules page opens for you to review and edit the details of the flow schedule.

    The dialog appears on the right-pane.

  5. Select and click the flow schedule link.
  6. (Optional) Edit the completion date or the description flexfields values.