Quick Complete
You can report completion of a flow schedule using a single user action when no additional information must be entered.
To report flow schedule completion using quick complete action:
- Navigate to the Work Execution Overview work area.
- From the Actions menu, select Flow Schedules
Execution.
The Production Lines page opens displaying the production lines that have been identified for the organization.
- Select a production line and click View Flow Schedules to
review the flow schedule summary of a production line.
The Flow Schedules page displays the schedules that are sequenced for execution on a production line. The flow schedules are displayed in the order of the build sequence.
- Select a flow schedule and click Quick Complete.
The flow scheduled is completed and the material and resource usages for the flow schedule are automatically reported based on the associated flow manufacturing work definition. The next schedule in sequence is automatically moved up for report completion.