Resequence Flow Schedules

You can resequence a flow schedule on any day to cater to a situation where a rush order needs to be fulfilled.

To resequence a flow schedule for flow manufacturing:

  1. Navigate to the Work Execution Overview work area.
  2. From the Actions menu, select Manage Flow Schedules.

    The Production Lines page opens.

  3. Select a production line and click View Flow Schedules Summary.

    The Production Schedule Summary page opens.

  4. Select a flow schedule for a specific day and click the date link.

    The Flow Schedules page opens.

  5. Click Resequence.

    The dialog appears on the right-pane.

  6. Drag and drop a flow schedule sequence.

    For example, let’s resequence the flow schedule ending with 26 and manually drag it to prioritize and change the build sequence.

  7. Click Save.

    The flow schedule ending with 26 has been resequenced.