Create a Production Campaign

Define a campaign’s production rate, size, and attributes, then assign matching work orders to it.

  1. In the campaigns table, select a Resource.
  2. Select the Add icon (+).
  3. In the drawer, enter the Campaign Name and Campaign Sequence number.
  4. If needed, specify an Earliest Start Date.
  5. In the Production rate section, enter the Units and Hours. The Unit of Measure comes from the campaign resource setup.
  6. In the Campaign basis section, select one of these options:
    • Quantity: Enter the quantity you want to produce.
    • Required usage: Enter the resource usage hours.
  7. In the Campaign attributes section, select the attribute values. You can assign only work orders with matching values to the campaign.
  8. Select the Color for attribute value combination to use in the Gantt chart. Campaigns with the same attribute value combination use the same color.
  9. Select Create.