Create a Production Campaign
Define a campaign’s production rate, size, and attributes, then assign matching work orders to it.
- In the campaigns table, select a Resource.
- Select the Add icon (+).
- In the drawer, enter the Campaign Name and Campaign Sequence number.
- If needed, specify an Earliest Start Date.
- In the Production rate section, enter the Units and Hours. The Unit of Measure comes from the campaign resource setup.
- In the Campaign basis section, select one of these options:
- Quantity: Enter the quantity you want to produce.
- Required usage: Enter the resource usage hours.
- In the Campaign attributes section, select the attribute values. You can assign only work orders with matching values to the campaign.
- Select the Color for attribute value combination to use in the Gantt chart. Campaigns with the same attribute value combination use the same color.
- Select Create.