Overview of Schedule Actions
You can begin scheduling after your schedule has been set up.
Refresh and Solve a Schedule
Open the actions menu of a schedule to refresh or to refresh and solve a schedule.
-
Click Refresh to update schedule data.
-
Click Refresh and Solve to update schedule data and generate a new schedule.
You can review a schedule after either action, by clicking Open in the action menu. You can also solve the schedule using the Solve button in the schedule view.
You must refresh a schedule after its last release, or else changes to the schedule for some work orders made after that release may not get released in the next one.
Analyze and Adjust a Schedule
In the actions menu for a schedule, click Open to enter the schedule view. Here's how you analyze and adjust a schedule:
-
Review schedule analytics.
-
Adjust the schedule using the interactive features of the Gantt chart and the focused data views.
-
Click Repair to implement your adjustments. It's best that you repair the schedule after every adjustment.
If you need to undo all your manual adjustments and repairs since the last solve process, click Solve.
Release a Schedule
Use release actions to review the number of work orders slated for release, and to release the schedule to your manufacturing application.
-
Click the Release Schedule button in the schedule view.
-
Review work order metrics.
-
Click Release.
Duplicate a Schedule
- In the actions menu for a schedule, click Duplicate to open the Duplicate a Schedule dialog box.
- Enter an unique name and description of the duplicated schedule.
- To copy only the schedule options of the original schedule, select the Copy schedule options only check box.
- Click Duplicate.
Production Campaigns
Production Scheduling automatically considers campaign resources within the schedule scope, which is defined by the schedule horizon, item catalog, and item categories. No additional schedule options are required.
The Solve action respects the campaign sequence, work order assignments to campaigns, and work order sequences within campaigns. Use the Production Campaigns workbench to change these assignments and sequences.
Capacity for Partially Assigned Campaigns
Campaigns are scheduled based on their sizes, regardless of how many work orders are assigned. For a campaign that isn’t fully assigned, the Solve action reserves the unassigned resource hours by leaving a time gap after the last assigned work order. This preserves the campaign duration calculated in the Production Campaigns workbench. Work orders in subsequent campaigns start after this gap, according to the campaign sequence.
- Occur before the schedule horizon start.
- Are already in progress.
- Are firm.
Work orders that use a campaign resource but aren’t assigned to a campaign are scheduled after all work orders assigned to campaigns.
Upstream and Downstream Resource Constraints
Upstream and downstream resource constraints can affect scheduling on the campaign resource. For example, an upstream constraint might delay a work order within a campaign.
As a best practice, constrain campaign resources and relax upstream and downstream resources. This allows campaign resources, which are typically manufacturing bottlenecks, to drive the production schedule.
Manual Schedule AdjustmentsYou can manually move work orders before or after their campaigns in Production Scheduling. These adjustments don’t change the work order assignments to campaigns or their sequences within campaigns, and Production Scheduling doesn’t publish changes to these assignments or sequences to Work Execution.
Any resulting date inconsistencies are corrected during the next campaign plan calculation, which reapplies the work order assignments and sequences defined in the Production Campaigns workbench.