Overview of Schedule Options

Use the Schedule Options page to set up your production schedule and to configure how it gets solved.

While creating a new schedule, you first define schedule options. To edit schedule options for an existing schedule, open the action menu for that schedule and click Schedule Options.

Set Up and Configure a Schedule

  1. On the Manage Schedule Options page, specify a schedule name and a description.

  2. Define the schedule scope. This includes the schedule horizon, the organization you want to schedule production for, and item catalogs and categories. Specify if you want to consider planned orders from supply planning while creating production schedules.

  3. Configure schedule parameter values by defining scheduling horizons and fixed time fence settings.

  4. Configure advanced schedule options by defining parameters such as resource allocation priorities and scheduling bucket specifications that drive algorithmic decisions during schedule generation.

  5. Configure the schedule display by specifying which resources are displayed by default in the Gantt Chart.

Note: All dates and times in a schedule are displayed in the time zone of the scheduling organization.

Guidelines for Working with Planned Orders from Oracle Supply Planning

  • You can reference a supply plan with a Fusion source in a production schedule and reference one production schedule per organization in a supply plan.
  • The unreleased planned make orders from a supply plan are included in a schedule only if they satisfy the schedule scope criteria.
  • Work orders from SCM Execution and unreleased planned orders from a supply plan or an integrated demand and supply plan are scheduled together in the same production schedule.
  • In the subsequent supply plan runs, the planned make orders scheduled by Oracle Production Scheduling are considered firm.

Campaign Planning

Use the Production Campaigns workbench to define and manage production campaigns and establish longer-term plans for campaign resources, which are typically bottleneck resources.

The workbench schedules activities only at the campaign resource level. It doesn’t consider upstream and downstream operations defined in work definitions and work orders. Production Scheduling aligns these operations with the scheduled activities on campaign resources.

Create and manage production schedules separately from campaign plans. The scope of each production schedule is determined by the specified item catalog, item categories, and schedule horizon.