How can I set a performance goal as completed?
You can set a performance goal as completed in the Update your progress panel.
Open the performance goal that you want to set as completed. In the Update your progress panel, do these actions:
- If your administrator has enabled the Status list of values, select the status as Completed.
- If your administrator has enabled the Completion Percentage field, set the percentage to the maximum value.
- Select the actual completion date.
- Optionally, add a progress note.
- Select Update Progress.