Setting Milestones

View an issue and then set milestones.

Use Milestones to track events. You can assign one or more milestones to an event.

To set milestones:

  1. View the issue:

    1. Navigate to Team Development.

    2. Click the issue title.

      The Issue Details page appears.

      Description of the illustration issue_details_action_menu.png

  2. From the Actions menu, select Set Milestones.

    You can also click the Set Milestones icon on far right side of the page.

  3. In the Milestones dialog:

    1. Select milestones to add to the issue.

    2. Optionally select Show Closed Milestones.

    3. Click Apply Changes.

    A new event is added to the Event Timeline and the new milestones display under Milestones in the far right region. The color of the milestone indicates the following:

    • Red - The milestones date is in the past.

    • Yellow - The milestones date is within two weeks.

    • Green - The milestones date is more than two weeks 2 weeks in the future.

For more information, see: