Data Center Room Checklist
Complete the following checklist to ensure that the data center room requirements are met. For information about the data center requirements, see Flooring Requirements.
| Data Center Room Considerations | Yes | No | N/A | Comment |
|---|---|---|---|---|
|
Has the Oracle Private Cloud Appliance location been allocated? |
||||
|
Is there a vacant location for the new equipment? |
||||
|
Does the floor layout meet the equipment maintenance access requirements? |
||||
|
Is there adequate space available for maintenance? |
||||
|
Will the equipment be positioned so that the exhaust air of one rack does not enter the air inlet of another rack? |
||||
|
Have cabinet stabilization measures been considered? |
||||
|
Does the raised floor satisfy the weight requirements for the new hardware? |
||||
|
Can floor tiles be removed without permission to accommodate service? |
||||
|
Are there cable routing channels or cutouts? |
||||
|
Are you providing any additional hardware? |
||||
|
Is the hardware you are providing fully compatible with the Oracle Private Cloud Appliance? |
||||
|
Will the new hardware location require any non-standard cable lengths? |
||||
|
Is the floor to ceiling height a minimum of 3214 mm or 3.2 m (10.5 feet)? |
||||
|
Is the depth of the raised floor a minimum of 46 cm (18 inches)? |