Inspect Appliance

When the rack is in its allocated space, but prior to applying power, visually inspect the appliance.

  1. Check for rack damage.

  2. Check the rack for loose or missing screws.

  3. Check your appliance for the ordered configuration. Refer to the Customer Information Sheet (CIS) on the side of the packaging. Ensure that the correct connectors have been supplied for the data center facility power source.

  4. Check that all cable connections are secure and firmly in place.

  5. Check the site location tile arrangement for cable access and airflow.

  6. Check the data center airflow that leads in to the front of the system. (See Verify Installation Requirements.)