To install the stationary slide rails on the front of a
tapped hole equipment rack:
Locate the
following components:
2 x stationary slide rail sections
4 x 10-32 x 5/8” screws
2 x mounting spacers
Line up the
stationary slide rail end with three mounting slots with an appropriate mount
point on the front of the equipment rack.
Stationary Slide Rail Lined Up With Front Mount
Point
Place 2 x 10-32
screws through the mounting spacer and through the stationary slide rail ear.
Screw in and secure
the stationary slide rail to the equipment rack as shown in the following
exploded view. Do not completely torque the screws; leave a small amount of
play at this point.
Screwing In and Securing the Stationary Slide Rail
Repeat Steps 3 and
4 for the other mounting point.
Installed Stationary Slide Rail
Repeat this
procedure for the other stationary slide. Your rack should resemble the
following image.