4.3 Backout Phases

The following table shows the backout process by procedure and estimated time. Actual times may vary with typing speed and system configuration. Complete the phases in the order shown.

Table 4-6 Backout Procedure Overview

Phase Elapsed Time (Hours or Minutes) Activity Impact Procedure
This Step Cum.

Determine state of system

15-

30

15-

30

Investigate and determine the state of the MPS system. This may take anywhere from 15 to 30 minutes.

Cannot proceed with backout until failure analysis is complete. Some hand-fixes may be required before proceeding with backout.

Contact the My Oracle Support by following the instructions on the front page or the instructions in the Appendix E.

Backout

MPS A and

MPS B

8

90-120

Backout MPS A and then

MPS B.

N/A

Procedure 33

Post-backout

health check

7

15

Run the syscheck utility

to verify the MPS server

is operationally sound.

Verify that the backout

was successful.

Procedure 3