2 GENERAL DESCRIPTION
This document defines the step-by-step actions performed to execute a software full upgrade to E5APPB-02. The LSMS application can be installed or upgraded based on the table below.
Table 2-1 Install-Full Upgrade paths for E5APPB-02
| TPD Release for IPM | LSMS Initial Installation Release |
|---|---|
|
8.10.1.5.0_150.14.0 or later |
14.1.Y |
|
Full upgrade Source Release |
Full upgrade Destination Release |
|
13.5.X |
14.1.0.Y |
|
14.0.0.4 |
14.1.0.Y |
Table 2-2 DIU Source and Target Version
| DIU Source version | DIU Target version |
|---|---|
|
14.0.0.4 |
14.1.0.0.Y |
Note:
LSMS 14.1.Y is supported on E5APPB-02 cards only.The LSMS upgrade paths are shown in the figures below. The general timeline for all processes to perform a software upgrade, from pre-upgrade backups to a final system health check, is also included below.
Figure 2-1 Full upgrade Path - LSMS 13.5.X to 14.1.Y

Figure 2-2 Full upgrade Path - LSMS 14.0.0.X to 14.0.0.Y

Figure 2-3 Dual Image Upgrade Path – LSMS 14.1.0.0.X