Activity Look Ahead Dashboard

Description: This dashboard provides a list of upcoming activities for the next 3 days, 1 week, 2 weeks, and for the next 30, 60, and 90 days.

Number of Canvases: 2

Default Canvas: Next 3 Days

Canvas/Dashboard Name: Activity Look Ahead Dashboard

Data Source(s): P6 - EPPM

Subject Area: P6 – Activity

Datasets: Not applicable

Dashboard

Canvases

Figure 4-8 Activity Look Ahead Dashboard


Activity Look Ahead Dashboard

Figure 4-9 Activity Look Ahead Details Dashboard


Activity Look Ahead Details Dashboard

Table 23: Activity Look Ahead - Dimensions

Canvas Dimension / Attribute Subject Area / Dataset
All Canvas Activity Status P6 – Activity
All Canvas Critical P6 – Activity
All Canvas Primary Resource P6 – Activity
All Canvas Start P6 – Activity
Activity Details Finish P6 – Activity
Activity Details Activity Name P6 – Activity

Table 24: Activity Look Ahead – Measures

Canvas Fact / Measure Measure Type Subject Area / Dataset
Next N Days # of Activities Fact P6 – Activity

Table 25: Activity Look Ahead – Filters

Canvas Filter Type Is Expression Filter Dimension / Attribute / Measure Subject Area / Dataset
Next N Days Dashboard No Portfolio Name P6 - Activity
All Canvas Dashboard No Project Name P6 - Activity
Next 3 Days Dashboard Yes

(CAST("Primavera - Activity"."Dates - (Activity)"."Start" AS DATE) BETWEEN CAST("Primavera - Activity"."Dates - (Project)"."Data Date" AS DATE) AND TIMESTAMPADD(SQL_TSI_DAY,3,CAST("Primavera - Activity"."Dates - (Project)"."Data Date" AS DATE)))

 

P6 - Activity
Next 7 Days Dashboard Yes

(CAST("Primavera - Activity"."Dates - (Activity)"."Start" AS DATE) BETWEEN CAST("Primavera - Activity"."Dates - (Project)"."Data Date" AS DATE) AND TIMESTAMPADD(SQL_TSI_DAY,7,CAST("Primavera - Activity"."Dates - (Project)"."Data Date" AS DATE)))

 

P6 - Activity
Next 14 Days Dashboard Yes

(CAST("Primavera - Activity"."Dates - (Activity)"."Start" AS DATE) BETWEEN CAST("Primavera - Activity"."Dates - (Project)"."Data Date" AS DATE) AND TIMESTAMPADD(SQL_TSI_DAY,14,CAST("Primavera - Activity"."Dates - (Project)"."Data Date" AS DATE)))

 

P6 - Activity
Next 30 Days Dashboard Yes

(CAST("Primavera - Activity"."Dates - (Activity)"."Start" AS DATE) BETWEEN CAST("Primavera - Activity"."Dates - (Project)"."Data Date" AS DATE) AND TIMESTAMPADD(SQL_TSI_DAY,30,CAST("Primavera - Activity"."Dates - (Project)"."Data Date" AS DATE)))

 

P6 - Activity
Next 60 Days Dashboard Yes

(CAST("Primavera - Activity"."Dates - (Activity)"."Start" AS DATE) BETWEEN CAST("Primavera - Activity"."Dates - (Project)"."Data Date" AS DATE) AND TIMESTAMPADD(SQL_TSI_DAY,60,CAST("Primavera - Activity"."Dates - (Project)"."Data Date" AS DATE)))

 

P6 - Activity
Next 90 Days Dashboard Yes

(CAST("Primavera - Activity"."Dates - (Activity)"."Start" AS DATE) BETWEEN CAST("Primavera - Activity"."Dates - (Project)"."Data Date" AS DATE) AND TIMESTAMPADD(SQL_TSI_DAY,90,CAST("Primavera - Activity"."Dates - (Project)"."Data Date" AS DATE)))

 

P6 - Activity

Table 26: Activity Look Ahead – Calculated Members

Calculated Member Expression Source Subject Area / Dataset
Schedule % Complete (PRCNT)

"Primavera - Activity"."Percent Complete"."Schedule % Complete" / 100

 

Derived From Fact P6 - Activity