Project Status Dashboard

Description: .

Number of Canvases: 1

Default Canvas: Project Status

Canvas/Dashboard Name: Project Status

Data Source(s): Unifier

Subject Area: Unifier - Cost Sheet

Datasets: Not applicable

Dashboard

Figure 5-5 Project Status Dashboard


Project Status Dashboard

Table 59: Project Status - Dimensions

Canvas Dimension / Attribute Subject Area / Dataset
Project Status Project Status Unifier - Cost Sheet
Project Status Project Hierarchy Unifier - Cost Sheet
Project Status Project Name Unifier - Cost Sheet

Table 60: Project Status – Measures

Canvas Fact / Measure Measure Type Subject Area / Dataset
Project Status Revised Budget Fact Unifier - Cost Sheet
Project Status Projected Cost Calculated from Fact Unifier - Cost Sheet
Project Status Estimated Cost At Completion Calculated from Fact Unifier - Cost Sheet
Project Status Projected Over Under Calculated from Fact Unifier - Cost Sheet
Project Status % Projected / Forecast Calculated from Fact Unifier - Cost Sheet
Project Status % Projected / Budget Calculated from Fact Unifier - Cost Sheet
Project Status Approved Budget Revisions Fact Unifier - Cost Sheet
Project Status % Forecast Calculated from Fact Unifier - Cost Sheet
Project Status Project Count Fact Unifier - Cost Sheet
Project Status Original Budget Fact Unifier - Cost Sheet
Project Status Approved Commitment Changes Calculated from Fact Unifier - Cost Sheet
Project Status Pending Contracts, cos & POs Calculated from Fact Unifier - Cost Sheet
Project Status Non Commitment Cost Calculated from Fact Unifier - Cost Sheet
Project Status Total Costs Incurred Calculated from Fact Unifier - Cost Sheet
Project Status Estimate to Complete (ETC) Calculated from Fact Unifier - Cost Sheet
Project Status % Projected Costs Calculated from Fact Unifier - Cost Sheet

Table 61: Project Status - Filters

Canvas Filter Type Is Expression Filter Dimension / Attribute / Measure Subject Area / Dataset
Project Status Dashboard No Datasource ID Unifier - Cost Sheet
Project Status Dashboard No Project Name Unifier - Cost Sheet
Project Status Visualization Yes "Primavera - Cost Sheet"."General - (Project)"."Project Status" is not null Unifier - Cost Sheet

Table 62: Project Status - Calculated Members

Calculated Member Expression Source Subject Area / Dataset
Projected Cost

"Primavera - Cost Sheet"."Costs"."User Defined Column 14"+"Primavera - Cost Sheet"."Costs"."Revised Commitments"+"Primavera - Cost Sheet"."Costs"."User Defined Column 6"

 

Derived From Fact Unifier - Cost Sheet
Estimated Cost At Completion

"Primavera - Cost Sheet"."Costs"."User Defined Column 7" + "Primavera - Cost Sheet"."Costs"."User Defined Column 13"

 

Derived From Fact Unifier - Cost Sheet
Projected Over Under

"Primavera - Cost Sheet"."Costs"."Revised Budget" - ("Primavera - Cost Sheet"."Costs"."User Defined Column 7" + "Primavera - Cost Sheet"."Costs"."User Defined Column 13")

 

Derived From Fact Unifier - Cost Sheet
% Projected / Forecast

(("Primavera - Cost Sheet"."Costs"."User Defined Column 14"+"Primavera - Cost Sheet"."Costs"."Revised Commitments"+"Primavera - Cost Sheet"."Costs"."User Defined Column 6") / ("Primavera - Cost Sheet"."Costs"."User Defined Column 7" + "Primavera - Cost Sheet"."Costs"."User Defined Column 13"))

 

Derived From Fact Unifier - Cost Sheet
% Forecast / Budget

("Primavera - Cost Sheet"."Costs"."User Defined Column 7" + "Primavera - Cost Sheet"."Costs"."User Defined Column 13") / "Primavera - Cost Sheet"."Costs"."Revised Budget"

 

Derived From Fact Unifier - Cost Sheet
% Forecast

1-(("Primavera - Cost Sheet"."Costs"."User Defined Column 14"+"Primavera - Cost Sheet"."Costs"."Revised Commitments"+"Primavera - Cost Sheet"."Costs"."User Defined Column 6") / ("Primavera - Cost Sheet"."Costs"."User Defined Column 7" + "Primavera - Cost Sheet"."Costs"."User Defined Column 13"))

 

Derived From Fact Unifier - Cost Sheet
Project Count COUNT(DISTINCT "Primavera - Cost Sheet"."General - (Project)"."Project Object Id") Derived From Fact Unifier - Cost Sheet
Pending Contracts, Cos & POs

"Primavera - Cost Sheet"."Costs"."Pending PO Amendments"+"Primavera - Cost Sheet"."Costs"."Pending Change Orders"

 

Derived From Fact Unifier - Cost Sheet
Non Commitment Cost

"Primavera - Cost Sheet"."Costs"."User Defined Column 6"

 

Derived From Fact Unifier - Cost Sheet
Total Costs Incurred

"Primavera - Cost Sheet"."Costs"."User Defined Column 7"

 

Derived From Fact Unifier - Cost Sheet
% Projected Costs

"Primavera - Cost Sheet"."Costs"."User Defined Column 7"/("Primavera - Cost Sheet"."Costs"."User Defined Column 14"+"Primavera - Cost Sheet"."Costs"."Revised Commitments"+"Primavera - Cost Sheet"."Costs"."User Defined Column 6")* 100

 

Derived From Fact Unifier - Cost Sheet
Estimate to Complete (ETC)

"Primavera - Cost Sheet"."Costs"."User Defined Column 13"

 

Derived From Fact Unifier - Cost Sheet