Selecting Projects for Burn Down Calculations
For a project to be included in the Burn Down tables and subject area, you must configure specific project UDF and History Level settings in P6.
To select which P6 EPPM projects to include in Burn Down tables and metrics:
- Sign in to P6 EPPM.
- In P6, click Projects.
- On the Projects navigation bar, click EPS.
- On the EPS page:
- Select a project.
- From the Row Actions menu, select Set Project Preferences.
- In the Project Preferences pane, click Analytics & Services.
- On the Analytics & Services page, click the History Level list and then select Activity.
- In the Project Preferences dialog box, click Save and Close.
- On the Projects navigation bar, click EPS.
- On the EPS page, add the sys_workdown and sys_workdown_date UDF columns to the page.
- For the projects you want to add to the Burn Down subject area: