Facts - Activity

(

The following facts are available in the Primavera Cloud - Activity subject area:

Folder SubFolder Field Name Dimension/ Fact / Lookup Description
Fact - Primavera - Activity Units Actual Labor Units Fact The actual units for all labor resources assigned to the activity
Fact - Primavera - Activity Units Actual Nonlabor Units Fact The actual units for all nonlabor resources assigned to the activity
Fact - Primavera - Activity Units At Completion Labor Units Fact The labor units at completion is the sum of the actual plus remaining units for all labor resources assigned to the activity. Computed as Actual Labor Units + Remaining Labor Units. Same as the budgeted labor units if the activity is not started and the actual labor units once the activity is completed.
Fact - Primavera - Activity Units At Completion Nonlabor Units Fact The nonlabor units at completion is the sum of the actual plus remaining units for all nonlabor resources assigned to the activity. Computed as Actual Nonlabor Units + Remaining Nonlabor Units. Same as the budgeted nonlabor units if the activity is not started and the actual nonlabor units once the activity is completed.
Fact - Primavera - Activity Units Baseline Actual Labor Units Fact The actual units for all labor resources assigned to the activity in the project baseline
Fact - Primavera - Activity Units Baseline Actual Nonlabor Units Fact The actual units for all nonlabor resources assigned to the activity in the project baseline
Fact - Primavera - Activity Units Baseline Planned Labor Units Fact The Planned units for all labor resources assigned to the activity in the project baseline.
Fact - Primavera - Activity Units Baseline Planned Nonlabor Units Fact The Planned units for all nonlabor resources assigned to the activity in the project baseline.
Fact - Primavera - Activity Units Earned Value Labor Units Fact The earned value labor units.
Fact - Primavera - Activity Units Estimate At Completion Labor Units Fact The estimate of all labor units at completion.
Fact - Primavera - Activity Units Estimate To Complete Units Fact The estimate of all labor units.
Fact - Primavera - Activity Units Planned Labor Units Fact The budgeted units for all labor resources assigned to the activity
Fact - Primavera - Activity Units Planned Nonlabor Units Fact The budgeted units for all nonlabor resources assigned to the activity
Fact - Primavera - Activity Units Planned Value Labor Units Fact The budgeted value of all labor units.
Fact - Primavera - Activity Units Remaining Labor Units Fact The remaining units for all labor resources assigned to the activity. The remaining units reflects the work remaining to be done for the activity. Before the activity is started, the remaining units are the same as the budgeted units. After the activity is completed, the remaining units are zero.
Fact - Primavera - Activity Units Remaining Nonlabor Units Fact The remaining units for all nonlabor resources assigned to the activity. The remaining units reflects the work remaining to be done for the activity. Before the activity is started, the remaining units are the same as the budgeted units. After the activity is completed, the remaining units are zero.
Fact - Primavera - Activity Units Remaining Late Labor Units Fact Remaining Late Labor Units .
Fact - Primavera - Activity Units Remaining Late Nonlabor Units Fact Remaining Late Nonlabor Units.
Fact - Primavera - Activity Cost Actual Cost Fact The actual cost associated with the activity.
Fact - Primavera - Activity Cost Baseline Planned Expense Cost Fact The planned cost for all expenses associated with the activity in the primary baseline.
Fact - Primavera - Activity Cost Baseline Planned Labor Cost Fact The planned cost for all labor resources assigned to the activity in the project baseline.
Fact - Primavera - Activity Cost Baseline Planned Material Cost Fact The Planned cost for all material resources assigned to the activity in the project baseline.
Fact - Primavera - Activity Cost Baseline Planned Nonlabor Cost Fact The Planned cost for all nonlabor resources assigned to the activity in the project baseline.
Fact - Primavera - Activity Cost Baseline Planned Total Cost Fact The Planned total cost for the activity in the project baseline, including labor resources, nonlabor resources, material resources and project expenses.
         
Fact - Primavera Cloud - Activity Costs Actual Cost Fact The actual cost associated with the activity.
Fact - Primavera Cloud - Activity Costs Actual Expense Cost Fact The actual cost for all project expenses associated with the activity
Fact - Primavera Cloud - Activity Costs Actual Labor Cost Fact The actual cost for all labor resources assigned to the activity. If no resources are assigned, computed as the activity Actual Labor Units * Project Default Price / Time.
Fact - Primavera Cloud - Activity Costs Actual Material Cost Fact The actual cost for all material resources assigned to the activity
Fact - Primavera Cloud - Activity Costs Actual NonLabor Cost Fact The actual cost for all nonlabor resources assigned to the activity. If no resources are assigned, computed as the activity Actual Nonlabor Units * Project Default Price / Time.
Fact - Primavera Cloud - Activity Costs Actual Total Cost Fact The Actual Total Cost for the activity, including labor resources, nonlabor resources, material resources, and project expenses. Actual Total Cost = Actual Labor Cost + Actual Nonlabor Cost + Actual Material Cost + Actual Expense Cost.
Fact - Primavera Cloud - Activity Costs At Completion Expense Cost Fact The expense cost at completion is the sum of the actual plus remaining cost for all expenses associated with the activity. Computed as Actual Expense Cost + Remaining Expense Cost.
Fact - Primavera Cloud - Activity Costs At Completion Labor Cost Fact The labor cost at completion is the sum of the actual plus remaining cost for all labor resources assigned to the activity. Computed as Actual Labor Cost + Remaining Labor Cost. Same as the budgeted labor cost if the activity is not started and the actual labor cost once the activity is completed.
Fact - Primavera Cloud - Activity Costs At Completion Material Cost Fact The material cost at completion is the sum of the actual plus remaining cost for all material resources assigned to the activity. Computed as Actual Material Cost + Remaining Material Cost. Same as the budgeted material cost if the activity is not started and the actual material cost once the activity is completed.
Fact - Primavera Cloud - Activity Costs At Completion Nonlabor Cost Fact The nonlabor cost at completion is the sum of the actual plus remaining cost for all nonlabor resources assigned to the activity. Computed as Actual Nonlabor Cost + Remaining Nonlabor Cost. Same as the budgeted nonlabor cost if the activity is not started and the actual nonlabor cost once the activity is completed.
Fact - Primavera Cloud - Activity Costs At Completion Total Cost Fact The total cost at completion for the activity, including labor resources, nonlabor resources, material resources, and project expenses. At Completion Total Cost = At Completion Labor Cost + At Completion Nonlabor Cost + At Completion Material Cost + At Completion Expense Cost.
Fact - Primavera Cloud - Activity Costs Baseline Actual Expense Cost Fact The actual cost for all project expenses associated with the activity in the primary baseline
Fact - Primavera Cloud - Activity Costs Baseline Actual Labor Cost Fact The actual cost for all labor resources assigned to the activity in the project baseline. If no resources are assigned, computed as the activity Baseline Project Actual Labor Units * Project Default Price / Time.
Fact - Primavera Cloud - Activity Costs Baseline Actual Material Cost Fact The actual cost for all material resources assigned to the activity in the project baseline
Fact - Primavera Cloud - Activity Costs Baseline Actual Nonlabor Cost Fact The actual cost for all nonlabor resources assigned to the activity in the project baseline. If no resources are assigned, computed as the activity Baseline Project Actual Nonlabor Units * Project Default Price / Time
Fact - Primavera Cloud - Activity Costs Baseline Actual Total Cost Fact The actual total cost for the activity in the project baseline, including labor resources, nonlabor resources, material resources and project expenses. Baseline Project Actual Total Cost = Baseline Project Actual Labor Cost + Baseline Project Actual Nonlabor Cost + Baseline Project Actual Material Cost + Baseline Project Actual Expense Cost
Fact - Primavera Cloud - Activity Costs Baseline Planned Expense Cost Fact The planned cost for all expenses associated with the activity in the primary baseline.
Fact - Primavera Cloud - Activity Costs Baseline Planned Labor Cost Fact The planned cost for all labor resources assigned to the activity in the project baseline.
Fact - Primavera Cloud - Activity Costs Baseline Planned Material Cost Fact The Planned cost for all material resources assigned to the activity in the project baseline.
Fact - Primavera Cloud - Activity Costs Baseline Planned Nonlabor Cost Fact The Planned cost for all nonlabor resources assigned to the activity in the project baseline.
Fact - Primavera Cloud - Activity Costs Baseline Project Total Cost Fact The total cost of the activity in the project baseline, including labor resources, non-labor resources, material resources, and project expenses.
Fact - Primavera Cloud - Activity Cost Earned Value Cost Fact The earned value cost.
Fact - Primavera Cloud - Activity Cost Estimate At Completion Cost Fact The estimate cost at completion.
Fact - Primavera Cloud - Activity Cost Estimate To Complete Cost Fact The estimate cost to complete.
Fact - Primavera Cloud - Activity Costs Planned Expense Cost Fact The budgeted cost for all project expenses associated with the activity.
Fact - Primavera Cloud - Activity Costs Planned Labor Cost Fact The budgeted costs for all labor resources assigned to the activity. If no resources are assigned, computed as the activity Budgeted Labor Units * Project Default Price / Time.
Fact - Primavera Cloud - Activity Costs Planned Material Cost Fact The budgeted costs for all material resources assigned to the activity. If no resources are assigned, computed as the activity Budgeted Labor Units * Project Default Price / Time.
Fact - Primavera Cloud - Activity Costs Planned Nonlabor Cost Fact The budgeted costs for all nonlabor resources assigned to the activity.
Fact - Primavera Cloud - Activity Costs Planned Total Cost Fact The budgeted total cost for the activity, including labor resources, nonlabor resources, material resources, and project expenses. Budgeted Total Cost = Budgeted Labor Cost + Budgeted Nonlabor Cost + Budgeted Material Cost + Budgeted Expense Cost.
Fact - Primavera Cloud - Activity Costs Planned Value Cost Fact The planned cost for the activity.
Fact - Primavera Cloud - Activity Costs Remaining Expense Cost Fact The remaining cost for all project expenses associated with the activity.
Fact - Primavera Cloud - Activity Costs Remaining Labor Cost Fact The remaining cost for all labor resources assigned to the activity. If no resources are assigned, computed as the activity Remaining Labor Units * Project Default Price / Time.
Fact - Primavera Cloud - Activity Costs Remaining Material Cost Fact The remaining cost for all material resources assigned to the activity.
Fact - Primavera Cloud - Activity Costs Remaining Nonlabor Cost Fact The remaining cost for all nonlabor resources assigned to the activity. If no resources are assigned, computed as the activity Remaining Nonlabor Units * Project Default Price / Time.
Fact - Primavera Cloud - Activity Costs Remaining Total Cost Fact The remaining total cost for the activity, including labor resources, nonlabor resources, material resources, and project expenses. Remaining Total Cost = Remaining Labor Cost + Remaining Nonlabor Cost + Remaining Material Cost + Remaining Expense Cost.
Fact - Primavera Cloud - Activity Costs Remaining Late Expense Cost Fact Remaining Late Expense Cost
Fact - Primavera Cloud - Activity Costs Remaining Late Labor Cost Fact Remaining Late Labor Cost
Fact - Primavera Cloud - Activity Costs Remaining Late Material Cost Fact Remaining Late Material Cost
Fact - Primavera Cloud - Activity Costs Remaining Late Nonlabor Cost Fact Remaining Late Nonlabor Cost
Fact - Primavera Cloud - Activity Costs Remaining Late Total Cost Fact Remaining late total cost.
Fact - Primavera - Activity Metrics # Of Activities Fact # Of Activities
Fact - Primavera Cloud - Activity Metrics # Of Projects Fact # Of Projects