Facts - Activity
(
The following facts are available in the Primavera Cloud - Activity subject area:
| Folder | SubFolder | Field Name | Dimension/ Fact / Lookup | Description |
|---|---|---|---|---|
| Fact - Primavera - Activity | Units | Actual Labor Units | Fact | The actual units for all labor resources assigned to the activity |
| Fact - Primavera - Activity | Units | Actual Nonlabor Units | Fact | The actual units for all nonlabor resources assigned to the activity |
| Fact - Primavera - Activity | Units | At Completion Labor Units | Fact | The labor units at completion is the sum of the actual plus remaining units for all labor resources assigned to the activity. Computed as Actual Labor Units + Remaining Labor Units. Same as the budgeted labor units if the activity is not started and the actual labor units once the activity is completed. |
| Fact - Primavera - Activity | Units | At Completion Nonlabor Units | Fact | The nonlabor units at completion is the sum of the actual plus remaining units for all nonlabor resources assigned to the activity. Computed as Actual Nonlabor Units + Remaining Nonlabor Units. Same as the budgeted nonlabor units if the activity is not started and the actual nonlabor units once the activity is completed. |
| Fact - Primavera - Activity | Units | Baseline Actual Labor Units | Fact | The actual units for all labor resources assigned to the activity in the project baseline |
| Fact - Primavera - Activity | Units | Baseline Actual Nonlabor Units | Fact | The actual units for all nonlabor resources assigned to the activity in the project baseline |
| Fact - Primavera - Activity | Units | Baseline Planned Labor Units | Fact | The Planned units for all labor resources assigned to the activity in the project baseline. |
| Fact - Primavera - Activity | Units | Baseline Planned Nonlabor Units | Fact | The Planned units for all nonlabor resources assigned to the activity in the project baseline. |
| Fact - Primavera - Activity | Units | Earned Value Labor Units | Fact | The earned value labor units. |
| Fact - Primavera - Activity | Units | Estimate At Completion Labor Units | Fact | The estimate of all labor units at completion. |
| Fact - Primavera - Activity | Units | Estimate To Complete Units | Fact | The estimate of all labor units. |
| Fact - Primavera - Activity | Units | Planned Labor Units | Fact | The budgeted units for all labor resources assigned to the activity |
| Fact - Primavera - Activity | Units | Planned Nonlabor Units | Fact | The budgeted units for all nonlabor resources assigned to the activity |
| Fact - Primavera - Activity | Units | Planned Value Labor Units | Fact | The budgeted value of all labor units. |
| Fact - Primavera - Activity | Units | Remaining Labor Units | Fact | The remaining units for all labor resources assigned to the activity. The remaining units reflects the work remaining to be done for the activity. Before the activity is started, the remaining units are the same as the budgeted units. After the activity is completed, the remaining units are zero. |
| Fact - Primavera - Activity | Units | Remaining Nonlabor Units | Fact | The remaining units for all nonlabor resources assigned to the activity. The remaining units reflects the work remaining to be done for the activity. Before the activity is started, the remaining units are the same as the budgeted units. After the activity is completed, the remaining units are zero. |
| Fact - Primavera - Activity | Units | Remaining Late Labor Units | Fact | Remaining Late Labor Units . |
| Fact - Primavera - Activity | Units | Remaining Late Nonlabor Units | Fact | Remaining Late Nonlabor Units. |
| Fact - Primavera - Activity | Cost | Actual Cost | Fact | The actual cost associated with the activity. |
| Fact - Primavera - Activity | Cost | Baseline Planned Expense Cost | Fact | The planned cost for all expenses associated with the activity in the primary baseline. |
| Fact - Primavera - Activity | Cost | Baseline Planned Labor Cost | Fact | The planned cost for all labor resources assigned to the activity in the project baseline. |
| Fact - Primavera - Activity | Cost | Baseline Planned Material Cost | Fact | The Planned cost for all material resources assigned to the activity in the project baseline. |
| Fact - Primavera - Activity | Cost | Baseline Planned Nonlabor Cost | Fact | The Planned cost for all nonlabor resources assigned to the activity in the project baseline. |
| Fact - Primavera - Activity | Cost | Baseline Planned Total Cost | Fact | The Planned total cost for the activity in the project baseline, including labor resources, nonlabor resources, material resources and project expenses. |
| Fact - Primavera Cloud - Activity | Costs | Actual Cost | Fact | The actual cost associated with the activity. |
| Fact - Primavera Cloud - Activity | Costs | Actual Expense Cost | Fact | The actual cost for all project expenses associated with the activity |
| Fact - Primavera Cloud - Activity | Costs | Actual Labor Cost | Fact | The actual cost for all labor resources assigned to the activity. If no resources are assigned, computed as the activity Actual Labor Units * Project Default Price / Time. |
| Fact - Primavera Cloud - Activity | Costs | Actual Material Cost | Fact | The actual cost for all material resources assigned to the activity |
| Fact - Primavera Cloud - Activity | Costs | Actual NonLabor Cost | Fact | The actual cost for all nonlabor resources assigned to the activity. If no resources are assigned, computed as the activity Actual Nonlabor Units * Project Default Price / Time. |
| Fact - Primavera Cloud - Activity | Costs | Actual Total Cost | Fact | The Actual Total Cost for the activity, including labor resources, nonlabor resources, material resources, and project expenses. Actual Total Cost = Actual Labor Cost + Actual Nonlabor Cost + Actual Material Cost + Actual Expense Cost. |
| Fact - Primavera Cloud - Activity | Costs | At Completion Expense Cost | Fact | The expense cost at completion is the sum of the actual plus remaining cost for all expenses associated with the activity. Computed as Actual Expense Cost + Remaining Expense Cost. |
| Fact - Primavera Cloud - Activity | Costs | At Completion Labor Cost | Fact | The labor cost at completion is the sum of the actual plus remaining cost for all labor resources assigned to the activity. Computed as Actual Labor Cost + Remaining Labor Cost. Same as the budgeted labor cost if the activity is not started and the actual labor cost once the activity is completed. |
| Fact - Primavera Cloud - Activity | Costs | At Completion Material Cost | Fact | The material cost at completion is the sum of the actual plus remaining cost for all material resources assigned to the activity. Computed as Actual Material Cost + Remaining Material Cost. Same as the budgeted material cost if the activity is not started and the actual material cost once the activity is completed. |
| Fact - Primavera Cloud - Activity | Costs | At Completion Nonlabor Cost | Fact | The nonlabor cost at completion is the sum of the actual plus remaining cost for all nonlabor resources assigned to the activity. Computed as Actual Nonlabor Cost + Remaining Nonlabor Cost. Same as the budgeted nonlabor cost if the activity is not started and the actual nonlabor cost once the activity is completed. |
| Fact - Primavera Cloud - Activity | Costs | At Completion Total Cost | Fact | The total cost at completion for the activity, including labor resources, nonlabor resources, material resources, and project expenses. At Completion Total Cost = At Completion Labor Cost + At Completion Nonlabor Cost + At Completion Material Cost + At Completion Expense Cost. |
| Fact - Primavera Cloud - Activity | Costs | Baseline Actual Expense Cost | Fact | The actual cost for all project expenses associated with the activity in the primary baseline |
| Fact - Primavera Cloud - Activity | Costs | Baseline Actual Labor Cost | Fact | The actual cost for all labor resources assigned to the activity in the project baseline. If no resources are assigned, computed as the activity Baseline Project Actual Labor Units * Project Default Price / Time. |
| Fact - Primavera Cloud - Activity | Costs | Baseline Actual Material Cost | Fact | The actual cost for all material resources assigned to the activity in the project baseline |
| Fact - Primavera Cloud - Activity | Costs | Baseline Actual Nonlabor Cost | Fact | The actual cost for all nonlabor resources assigned to the activity in the project baseline. If no resources are assigned, computed as the activity Baseline Project Actual Nonlabor Units * Project Default Price / Time |
| Fact - Primavera Cloud - Activity | Costs | Baseline Actual Total Cost | Fact | The actual total cost for the activity in the project baseline, including labor resources, nonlabor resources, material resources and project expenses. Baseline Project Actual Total Cost = Baseline Project Actual Labor Cost + Baseline Project Actual Nonlabor Cost + Baseline Project Actual Material Cost + Baseline Project Actual Expense Cost |
| Fact - Primavera Cloud - Activity | Costs | Baseline Planned Expense Cost | Fact | The planned cost for all expenses associated with the activity in the primary baseline. |
| Fact - Primavera Cloud - Activity | Costs | Baseline Planned Labor Cost | Fact | The planned cost for all labor resources assigned to the activity in the project baseline. |
| Fact - Primavera Cloud - Activity | Costs | Baseline Planned Material Cost | Fact | The Planned cost for all material resources assigned to the activity in the project baseline. |
| Fact - Primavera Cloud - Activity | Costs | Baseline Planned Nonlabor Cost | Fact | The Planned cost for all nonlabor resources assigned to the activity in the project baseline. |
| Fact - Primavera Cloud - Activity | Costs | Baseline Project Total Cost | Fact | The total cost of the activity in the project baseline, including labor resources, non-labor resources, material resources, and project expenses. |
| Fact - Primavera Cloud - Activity | Cost | Earned Value Cost | Fact | The earned value cost. |
| Fact - Primavera Cloud - Activity | Cost | Estimate At Completion Cost | Fact | The estimate cost at completion. |
| Fact - Primavera Cloud - Activity | Cost | Estimate To Complete Cost | Fact | The estimate cost to complete. |
| Fact - Primavera Cloud - Activity | Costs | Planned Expense Cost | Fact | The budgeted cost for all project expenses associated with the activity. |
| Fact - Primavera Cloud - Activity | Costs | Planned Labor Cost | Fact | The budgeted costs for all labor resources assigned to the activity. If no resources are assigned, computed as the activity Budgeted Labor Units * Project Default Price / Time. |
| Fact - Primavera Cloud - Activity | Costs | Planned Material Cost | Fact | The budgeted costs for all material resources assigned to the activity. If no resources are assigned, computed as the activity Budgeted Labor Units * Project Default Price / Time. |
| Fact - Primavera Cloud - Activity | Costs | Planned Nonlabor Cost | Fact | The budgeted costs for all nonlabor resources assigned to the activity. |
| Fact - Primavera Cloud - Activity | Costs | Planned Total Cost | Fact | The budgeted total cost for the activity, including labor resources, nonlabor resources, material resources, and project expenses. Budgeted Total Cost = Budgeted Labor Cost + Budgeted Nonlabor Cost + Budgeted Material Cost + Budgeted Expense Cost. |
| Fact - Primavera Cloud - Activity | Costs | Planned Value Cost | Fact | The planned cost for the activity. |
| Fact - Primavera Cloud - Activity | Costs | Remaining Expense Cost | Fact | The remaining cost for all project expenses associated with the activity. |
| Fact - Primavera Cloud - Activity | Costs | Remaining Labor Cost | Fact | The remaining cost for all labor resources assigned to the activity. If no resources are assigned, computed as the activity Remaining Labor Units * Project Default Price / Time. |
| Fact - Primavera Cloud - Activity | Costs | Remaining Material Cost | Fact | The remaining cost for all material resources assigned to the activity. |
| Fact - Primavera Cloud - Activity | Costs | Remaining Nonlabor Cost | Fact | The remaining cost for all nonlabor resources assigned to the activity. If no resources are assigned, computed as the activity Remaining Nonlabor Units * Project Default Price / Time. |
| Fact - Primavera Cloud - Activity | Costs | Remaining Total Cost | Fact | The remaining total cost for the activity, including labor resources, nonlabor resources, material resources, and project expenses. Remaining Total Cost = Remaining Labor Cost + Remaining Nonlabor Cost + Remaining Material Cost + Remaining Expense Cost. |
| Fact - Primavera Cloud - Activity | Costs | Remaining Late Expense Cost | Fact | Remaining Late Expense Cost |
| Fact - Primavera Cloud - Activity | Costs | Remaining Late Labor Cost | Fact | Remaining Late Labor Cost |
| Fact - Primavera Cloud - Activity | Costs | Remaining Late Material Cost | Fact | Remaining Late Material Cost |
| Fact - Primavera Cloud - Activity | Costs | Remaining Late Nonlabor Cost | Fact | Remaining Late Nonlabor Cost |
| Fact - Primavera Cloud - Activity | Costs | Remaining Late Total Cost | Fact | Remaining late total cost. |
| Fact - Primavera - Activity | Metrics | # Of Activities | Fact | # Of Activities |
| Fact - Primavera Cloud - Activity | Metrics | # Of Projects | Fact | # Of Projects |