P6 - Activity History / Primavera - Activity History

Description: Use this subject area to analyze daily, weekly, or monthly activity level history, including changes to both facts and dimensions, to better understand changes over time. This subject area requires project-specific configuration in P6.

Folder SubFolder Field Name Dimension/ Fact / Lookup Description Values Derived From / Calculated By
Project Budget - (Project) Current Budget Dimension The Current Budget is the sum of the Original Budget and all approved budget changes in the Budget Change Log. Value Derived From : Dim_W_PROJECT_HD_Project.CURRENT_BUDGET
Project Budget - (Project) Current Variance Dimension Computed as the Current Budget minus the Total Spending Plan. Not rolled up. Value Derived From : Dim_W_PROJECT_HD_Project.CURRENT_VARIANCE
Project Budget - (Project) Distributed Current Budget Dimension Computed as sum of the Current Budget values from one level lower. Not rolled up. Value Derived From : Dim_W_PROJECT_HD_Project.DISTRIBUTED_CURRENT_BUDGET
Project Budget - (Project) Original Budget Dimension Original budget for the project. Value Derived From : Dim_W_PROJECT_HD_Project.ORIGINAL_BUDGET
Project Budget - (Project) Proposed Budget Dimension The Proposed Budget is the sum of the Original Budget plus the Approved and Pending budgets from the budget change log. Not rolled up. Value Derived From : Dim_W_PROJECT_HD_Project.PROPOSED_BUDGET
Project Budget - (Project) Total Benefit Plan Dimension Sum of the Monthly Benefit Plan. Not rolled up. Value Derived From : Dim_W_PROJECT_HD_Project.TOTAL_BENEFIT_PLAN
Project Budget - (Project) Total Benefit Plan Tally Dimension Sum of the Monthly Benefit Plan Tally. Not rolled up. Value Derived From : Dim_W_PROJECT_HD_Project.TOTAL_BENEFIT_PLAN_TALLY
Project Budget - (Project) Total Funding Dimension The total amount of funding contributed to the project by your funding sources. Value Derived From : Dim_W_PROJECT_HD_Project.TOTAL_FUNDING
Project Budget - (Project) Total Spending Plan Dimension Sum of the Monthly Spending Plan. Not rolled up. Value Derived From : Dim_W_PROJECT_HD_Project.TOTAL_SPENDING_PLAN
Project Budget - (Project) Total Spending Plan Tally Dimension Sum of the Monthly Spending Plan Tally. Not rolled up. Value Derived From : Dim_W_PROJECT_HD_Project.TOTAL_SPENDING_PLAN_TALLY
Project Budget - (Project) Unallocated Budget Dimension Calculated as Total Current Budget - Distributed Current Budget. Value Derived From : Dim_W_PROJECT_HD_Project.UNALLOCATED_BUDGET
Project Budget - (Project) Undistributed Current Variance Dimension Computed as the Total Spending Plan minus the Total Spending Plan Tally. Not rolled up. Value Derived From : Dim_W_PROJECT_HD_Project.UNDISTRIBUTED_CURRENT_VARIANCE
Activity Codes - (Activity) Current Flag Dimension Indicates if a record is current (1,0) Value Derived From : Dim_W_CODES_ACTIVITY_HD_Activity_Codes_HD.CURRENT_FLAG
Activity Codes - (Activity) Effective End Date Dimension The end date this version of the record is effective Value Derived From : Dim_W_CODES_ACTIVITY_HD_Activity_Codes_HD.EFFECTIVE_END_DATE
Activity Codes - (Activity) Effective Start Date Dimension The start date this version of the record is effective Value Derived From : Dim_W_CODES_ACTIVITY_HD_Activity_Codes_HD.EFFECTIVE_START_DATE
Project Codes - (Project) Current Flag Dimension Indicates if a record is current (1,0) Value Derived From : Dim_W_CODES_PROJECT_HD_ProjectCodes.CURRENT_FLAG
Project Codes - (Project) Effective End Date Dimension The end date this version of the record is effective Value Derived From : Dim_W_CODES_PROJECT_HD_ProjectCodes.EFFECTIVE_END_DATE
Project Codes - (Project) Effective Start Date Dimension The start date this version of the record is effective Value Derived From : Dim_W_CODES_PROJECT_HD_ProjectCodes.EFFECTIVE_START_DATE
Project Dates - (Project) Actual Finish Date Dimension Actual Finish Date Value Derived From : Dim_W_PROJECT_HD_Project.ACTUAL_FINISH_DATE
Project Dates - (Project) Anticipated Finish Dimension Anticipated finish date of WBS, Project and EPS elements. User-entered - not dependent upon any other fields. If there are no children, the anticipated finish date will be the Finish date displayed in the columns. Value Derived From : Dim_W_PROJECT_HD_Project.ANTICIPATED_FINISH_DATE
Project Dates - (Project) Anticipated Start Dimension Anticipated start date of WBS, Project and EPS elements. User-entered - not dependent upon any other fields. If there are no children, the anticipated start date will be the Start date displayed in the columns. Value Derived From : Dim_W_PROJECT_HD_Project.ANTICIPATED_START_DATE
Project Dates - (Project) Baseline Finish Date Dimension Baseline Finish Date Value Derived From : Dim_W_PROJECT_HD_Project.BASELINE_FINISH_DATE
Project Dates - (Project) Data Date Dimension The current data date for the project. The project status is up to date as of the data date. The data date is modified when project actuals are applied. Value Derived From : Dim_W_PROJECT_HD_Project.DATA_DATE
Project Dates - (Project) Date Added Dimension The date this activity was inserted. Value Derived From : Dim_W_PROJECT_HD_Project.ADD_DATE
Project Dates - (Project) Effective End Date Dimension The end date this version of the record is effective Value Derived From : Dim_W_PROJECT_HD_Project.EFFECTIVE_END_DATE
Project Dates - (Project) Effective Start Date Dimension The start date this version of the record is effective Value Derived From : Dim_W_PROJECT_HD_Project.EFFECTIVE_START_DATE
Project Dates - (Project) Finish Dimension The current finish date of the activity. Set to the activity remaining early finish date while the activity is not started or in progress, and the actual finish date once the activity is completed. Value Derived From : Dim_W_PROJECT_HD_Project.PROJECT_FINISH_DATE
Project Dates - (Project) Forecast Finish Date Dimension An alternate end date to be optionally used by the scheduler (see Schedule dialog), which is set by the user by dragging the project bar in the Gantt Chart around while manually leveling the resource profile (in a resource analysis layout, tracking or PA). In User Preferences dialog, the user can choose to view remaining units for a resource based on the forecast dates or the remaining dates. Value Derived From : Dim_W_PROJECT_HD_Project.FORECAST_FINISH_DATE
Project Dates - (Project) Forecast Start Date Dimension An alternate start date to be optionally used by the scheduler (see Schedule dialog), which is set by the user by dragging the project bar in the Gantt Chart around while manually leveling the resource profile (in a resource analysis layout, tracking or PA). In the User Preferences dialog, the user can choose to view remaining units for a resource based on the forecast dates or the remaining dates. Value Derived From : Dim_W_PROJECT_HD_Project.FORECAST_START_DATE
Project Dates - (Project) Must Finish By Dimension The date by which all project activities must finish. If entered, it is used as the project late finish date by the project scheduler. Value Derived From : Dim_W_PROJECT_HD_Project.PROJECT_PLANNED_FINISH_DATE
Project Dates - (Project) Planned Start Dimension The date the activity is scheduled to begin. This date is computed by the project scheduler but can be updated manually by the project manager. This date is not changed by the project scheduler after the activity has been started. Value Derived From : Dim_W_PROJECT_HD_Project.PLANNED_START_DATE
Project Dates - (Project) Scheduled Finish Dimension The early finish date of the latest activity in the project, as computed by the project scheduler. Value Derived From : Dim_W_PROJECT_HD_Project.SCHEDULED_FINISH_DATE
Project Dates - (Project) Start Dimension The current start date of the activity. Set to the activity remaining early start date while the activity is not started, and the actual start date once the activity is started. Value Derived From : Dim_W_PROJECT_HD_Project.PROJECT_START_DATE
Project Durations - (Project) Actual Duration Dimension Actual duration is the total time from the project actual start date to the actual finish date (for completed projects), or to the current data date (for in-progress projects). Value Derived From : Dim_W_PROJECT_HD_Project.ACTUAL_DURATION
Project Durations - (Project) At Completion Duration Dimension The duration at completion is the total time from the project current start date to the current finish date. Value Derived From : Dim_W_PROJECT_HD_Project.AT_COMPLETION_DURATION
Project Durations - (Project) Baseline Project Duration Dimension The duration of the baseline project. Value Derived From : Dim_W_PROJECT_HD_Project.BASELINE_DURATION
Project Durations - (Project) Planned Duration Dimension Planned duration is the total time from the project planned start date to the planned finish date. Value Derived From : Dim_W_PROJECT_HD_Project.PLANNED_DURATION
Project Durations - (Project) Remaining Duration Dimension Remaining duration is the total time from the current data date date to the current finish date. Value Derived From : Dim_W_PROJECT_HD_Project.REMAINING_DURATION
Project Durations - (Project) Variance - Baseline Project Duration Dimension The duration between the baseline project duration and the current project duration. Calculated as Planned Duration minus At Completion Duration. Value Derived From : Dim_W_PROJECT_HD_Project.DURATION_VARIANCE
Project Durations - (Project) Variance - Baseline Project Finish Date Dimension Variance - Baseline Project Finish Date Value Derived From : Dim_W_PROJECT_HD_Project.FINISH_DATE_VARIANCE
Project General - (Project) Added By Dimension The name of the user who added the project Value Derived From : Dim_W_PROJECT_HD_Project.ADDED_BY_NAME
Project General - (Project) Current Flag Dimension Indicates if a record is current (1,0) Value Derived From : Dim_W_PROJECT_HD_Project.CURRENT_FLAG
Project General - (Project) Datasource Id Dimension A unique source Id created for the Primavera data source being used. Used to identify data sources when using multiple Primavera data sources. Value Derived From : Dim_W_PROJECT_HD_Project.DATASOURCE_ID
Project General - (Project) Project Leveling Priority Dimension Priority for leveling Value Derived From : Dim_W_PROJECT_HD_Project.PROJECT_PRIORITY
Project General - (Project) Project Score Dimension The Project score Value Derived From : Dim_W_PROJECT_HD_Project.OVERALL_PROJECT_SCORE
Project General - (Project) Project Description Dimension The project description Value Derived From : Dim_W_PROJECT_HD_Project.PROJECT_DESCRIPTION
Project General - (Project) Project Id Dimension The Project Id of the project Value Derived From : Dim_W_PROJECT_HD_Project.PROJECT_ID
Project General - (Project) Project Name Dimension The project name Value Derived From : Dim_W_PROJECT_HD_Project.PROJECT_NAME
Project General - (Project) Unique Project ID Dimension The Unique ID of the project Value Derived From : Dim_W_PROJECT_HD_Project.PROJECT_ID
Project General - (Project) Project Owner Dimension Resource designated as owner of the project Value Derived From : Dim_W_PROJECT_HD_Project.PROJECT_OWNER
Project General - (Project) Project Risk Exposure Dimension The calculated exposure value for the risk Value Derived From : Dim_W_PROJECT_HD_Project.PROJECT_RISK_EXPOSURE
Project General - (Project) Project Risk Level Dimension Project risk level (1 - Very Low, 2 - Low, 3 - Medium, 4 - High, 5 - Very High) Value Derived From : Dim_W_PROJECT_HD_Project.PROJECT_RISK_LEVEL
Project General - (Project) Project Risk Score Dimension The calculated score value of the impact values assigned to the risk Value Derived From : Dim_W_PROJECT_HD_Project.PROJECT_RISK_SCORE
Project General - (Project) WBS Dimension The Unique ID of the project's root level WBS Value Derived From : Dim_W_PROJECT_HD_Project.WBS_OBJECT_ID
Project General - (Project) Project Status Dimension The status of the project as active, inactive, planned or what-if Value Derived From : Dim_W_PROJECT_HD_Project.PROJECT_STATUS
Project General - (Project) Strategic Priority Dimension Range 1 to 10,000 Value Derived From : Dim_W_PROJECT_HD_Project.PROJECT_STRATEGIC_PRIORITY
Project Location - (Project) Address Line 1 Dimension The first line of the address Value Derived From : Dim_W_PROJECT_HD_Project.ADDRESS_LINE1
Project Location - (Project) Address Line 2 Dimension The second line of the address Value Derived From : Dim_W_PROJECT_HD_Project.ADDRESS_LINE2
Project Location - (Project) City Name Dimension The city name for this Location Value Derived From : Dim_W_PROJECT_HD_Project.CITY_NAME
Project Location - (Project) Country Code Dimension The country code for this Location Value Derived From : Dim_W_PROJECT_HD_Project.COUNTRY_CODE
Project Location - (Project) Country Name Dimension The country name for this Location Value Derived From : Dim_W_PROJECT_HD_Project.COUNTRY_NAME
Project Location - (Project) Latitude Dimension The latitude for this Location Value Derived From : Dim_W_PROJECT_HD_Project.LATITUDE
Project Location - (Project) Location Name Dimension The name of the location Value Derived From : Dim_W_PROJECT_HD_Project.LOCATION_NAME
Project Location - (Project) Location Type Dimension Location Type Value Derived From : Dim_W_PROJECT_HD_Project.LOCATION_TYPE
Project Location - (Project) Longitude Dimension The longitude for this Location Value Derived From : Dim_W_PROJECT_HD_Project.LONGITUDE
Project Location - (Project) Municipality Name Dimension The municipality name for this Location Value Derived From : Dim_W_PROJECT_HD_Project.MUNICIPALITY_NAME
Project Location - (Project) Postal Code Dimension The postal code for this Location Value Derived From : Dim_W_PROJECT_HD_Project.POSTAL_CODE
Project Location - (Project) State/Province Code Dimension The state abbreviation for this Location Value Derived From : Dim_W_PROJECT_HD_Project.STATE_CODE
Project Location - (Project) State/Province Name Dimension The state name for this Location Value Derived From : Dim_W_PROJECT_HD_Project.STATE_NAME
           
Fact - Primavera -Activity History Folder          
Fact - Primavera -Activity History Period Cost Next This Period Expense Cost Fact The Expense Cost planned in the next period Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.NEXT_PER_EXPENSE_COST_P
Fact - Primavera -Activity History Period Cost Next This Period Labor Cost Fact The Labor Cost planned for the next period Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.NEXT_PER_LABOR_COST_P
Fact - Primavera -Activity History Period Cost Next This Period Material Cost Fact The Material Cost planned in the next period Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.NEXT_PER_MATERIAL_COST_P
Fact - Primavera -Activity History Period Cost Next This Period Nonlabor Cost Fact The Nonlabor Cost planned in the next period Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.NEXT_PER_NONLABOR_COST_P
Fact - Primavera -Activity History Period Cost Period Actual Cost Fact The Actual Cost for the period specified Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.ACTUAL_COST_P
Fact - Primavera -Activity History Period Cost Period Actual Expense Cost Fact The Actual Expense Cost for the period specified Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.ACTUAL_EXPENSE_COST_P
Fact - Primavera -Activity History Period Cost Period Actual Labor Cost Fact The Actual Labor Cost for the period specified Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.ACTUAL_LABOR_COST_P
Fact - Primavera -Activity History Period Cost Period Actual Material Cost Fact The Actual Material Cost for the period specified Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.ACTUAL_MATERIAL_COST_P
Fact - Primavera -Activity History Period Cost Period Actual Nonlabor Cost Fact The Actual Nonlabor Cost for the period specified Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.ACTUAL_NONLABOR_COST_P
Fact - Primavera -Activity History Period Cost Period Actual Total Cost Fact The Actual Total Cost for the period specified Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.ACTUAL_TOTAL_COST_P
Fact - Primavera -Activity History Period Cost Period At Completion Expense Cost Fact The At Completion Expense Cost for the period specified Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.AT_COMPLETION_EXPENSE_COST_P
Fact - Primavera -Activity History Period Cost Period At Completion Labor Cost Fact The At Completion Labor Cost for the period specified Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.AT_COMPLETION_LABOR_COST_P
Fact - Primavera -Activity History Period Cost Period At Completion Material Cost Fact The At Completion Material Cost for the period specified Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.AT_COMPLETION_MATERIAL_COST_P
Fact - Primavera -Activity History Period Cost Period At Completion Nonlabor Cost Fact The At Completion Nonlabor Cost for the period specified Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.AT_COMPLETION_NONLABOR_COST_P
Fact - Primavera -Activity History Period Cost Period At Completion Total Cost Fact The At Completion Total Cost for the period specified Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.AT_COMPLETION_TOTAL_COST_P
Fact - Primavera -Activity History Period Cost Period Baseline Actual Expense Cost Fact The Baseline Actual Expense Cost for the period specified Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.BL_ACTUAL_EXPENSE_COST_P
Fact - Primavera -Activity History Period Cost Period Baseline Actual Labor Cost Fact The Baseline Actual Labor Cost for the period specified Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.BL_ACTUAL_LABOR_COST_P
Fact - Primavera -Activity History Period Cost Period Baseline Actual Material Cost Fact The Baseline Actual Material Cost for the period specified Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.BL_ACTUAL_MATERIAL_COST_P
Fact - Primavera -Activity History Period Cost Period Baseline Actual Nonlabor Cost Fact The Baseline Actual Nonlabor Cost for the period specified Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.BL_ACTUAL_NONLABOR_COST_P
Fact - Primavera -Activity History Period Cost Period Baseline Actual Total Cost Fact The Baseline Actual Total Cost for the period specified Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.BL_ACTUAL_TOTAL_COST_P
Fact - Primavera -Activity History Period Cost Period Baseline Project Expense Cost Fact The Baseline Project Expense Cost for the period specified Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.BL_PLANNED_EXPENSE_COST_P
Fact - Primavera -Activity History Period Cost Period Baseline Project Labor Cost Fact The Baseline Project Labor Cost for the period specified Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.BL_PLANNED_LABOR_COST_P
Fact - Primavera -Activity History Period Cost Period Baseline Project Material Cost Fact The Baseline Project Material Cost for the period specified Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.BL_PLANNED_MATERIAL_COST_P
Fact - Primavera -Activity History Period Cost Period Baseline Project Nonlabor Cost Fact The Baseline Project Nonlabor Cost for the period specified Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.BL_PLANNED_NONLABOR_COST_P
Fact - Primavera -Activity History Period Cost Period Baseline Project Total Cost Fact The Baseline Project Total Cost for the period specified Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.BL_PLANNED_TOTAL_COST_P
Fact - Primavera -Activity History Period Cost Period Earned Value Cost Fact The Earned Value Cost for the period specified Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.EARNED_VALUE_COST_P
Fact - Primavera -Activity History Period Cost Period Estimate At Completion Cost Fact The Estimate at Completion Cost for the period specified Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.EST_AT_COMPLETION_COST_P
Fact - Primavera -Activity History Period Cost Period Estimate To Completion Cost Fact The Estimate To Completion Cost for the period specified Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.EST_TO_COMPLETE_COST_P
Fact - Primavera -Activity History Period Cost Period Planned Expense Cost Fact The Planned Expense Cost for the period specified Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.PLANNED_EXPENSE_COST_P
Fact - Primavera -Activity History Period Cost Period Planned Labor Cost Fact The Planned Labor Cost for the period specified Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.PLANNED_LABOR_COST_P
Fact - Primavera -Activity History Period Cost Period Planned Material Cost Fact The Planned Material Cost for the period specified Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.PLANNED_MATERIAL_COST_P
Fact - Primavera -Activity History Period Cost Period Planned Nonlabor Cost Fact The Planned Nonlabor Cost for the period specified Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.PLANNED_NONLABOR_COST_P
Fact - Primavera -Activity History Period Cost Period Planned Total Cost Fact The Planned Total Cost for the period specified Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.PLANNED_TOTAL_COST_P
Fact - Primavera -Activity History Period Cost Period Planned Value Cost Fact The Planned Value Cost for the period specified Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.PLANNED_VALUE_COST_P
Fact - Primavera -Activity History Period Cost Period Remaining Expense Cost Fact The Remaining Expense Cost for the period specified Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.REMAINING_EXPENSE_COST_P
Fact - Primavera -Activity History Period Cost Period Remaining Labor Cost Fact The Remaining Labor Cost for the period specified Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.REMAINING_LABOR_COST_P
Fact - Primavera -Activity History Period Cost Period Remaining Late Expense Cost Fact The Remaining Late Expense Cost for the period specified Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.REMAINING_LATE_EXPENSE_COST_P
Fact - Primavera -Activity History Period Cost Period Remaining Late Labor Cost Fact The Remaining Late Labor Cost for the period specified Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.REMAINING_LATE_LABOR_COST_P
Fact - Primavera -Activity History Period Cost Period Remaining Late Material Cost Fact The Remaining Late Material Cost for the period specified Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.REMAINING_LATE_MATERIAL_COST_P
Fact - Primavera -Activity History Period Cost Period Remaining Late Nonlabor Cost Fact The Remaining Late Nonlabor Cost for the period specified Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.REMAINING_LATE_NONLABOR_COST_P
Fact - Primavera -Activity History Period Cost Period Remaining Late Total Cost Fact The Remaining Late Total Cost for the period specified Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.REMAINING_LATE_TOTAL_COST_P
Fact - Primavera -Activity History Period Cost Period Remaining Material Cost Fact The Remaining Material Cost for the period specified Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.REMAINING_MATERIAL_COST_P
Fact - Primavera -Activity History Period Cost Period Remaining Nonlabor Cost Fact The Remaining Nonlabor Cost for the period specified Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.REMAINING_NONLABOR_COST_P
Fact - Primavera -Activity History Period Cost Period Remaining Total Cost Fact The Remaining Total Cost for the period specified Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.REMAINING_TOTAL_COST_P
Fact - Primavera -Activity History Period Cost Previous This Period Expense Cost Fact The Expense Cost planned in the previous period Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.PREV_THIS_PER_EXPENSE_COST
Fact - Primavera -Activity History Period Cost Previous This Period Labor Cost Fact The Period Labor Cost planned in the previous period Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.PREV_THIS_PER_LABOR_COST
Fact - Primavera -Activity History Period Cost Previous This Period Material Cost Fact The Material Cost planned in the previous period Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.PREV_THIS_PER_MATERIAL_COST
Fact - Primavera -Activity History Period Cost Previous This Period Nonlabor Cost Fact The Nonlabor Cost planned in the previous period Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.PREV_THIS_PER_NONLABOR_COST
Fact - Primavera -Activity History Costs Actual Expense Cost Fact The actual cost for all project expenses associated with the activity. Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.ACTUAL_EXPENSE_COST
Fact - Primavera -Activity History Costs Actual Labor Cost Fact The actual cost for all labor resources assigned to the activity. If no resources are assigned, computed as the activity Actual Labor Units * Project Default Price / Time. Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.ACTUAL_LABOR_COST
Fact - Primavera -Activity History Costs Actual Material Cost Fact The actual cost for all material resources assigned to the activity. Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.ACTUAL_MATERIAL_COST
Fact - Primavera -Activity History Costs Actual NonLabor Cost Fact The actual cost for all nonlabor resources assigned to the activity. If no resources are assigned, computed as the activity Actual Nonlabor Units * Project Default Price / Time. Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.ACTUAL_NONLABOR_COST
Fact - Primavera -Activity History Costs Actual Total Cost Fact The Actual Total Cost for the activity, including labor resources, nonlabor resources, material resources, and project expenses. Actual Total Cost = Actual Labor Cost + Actual Nonlabor Cost + Actual Material Cost + Actual Expense Cost. Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.ACTUAL_TOTAL_COST
Fact - Primavera -Activity History Costs At Completion Expense Cost Fact The expense cost at completion is the sum of the actual plus remaining cost for all expenses associated with the activity. Computed as Actual Expense Cost + Remaining Expense Cost. Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.AT_COMPLETION_EXPENSE_COST
Fact - Primavera -Activity History Costs At Completion Labor Cost Fact The labor cost at completion is the sum of the actual plus remaining cost for all labor resources assigned to the activity. Computed as Actual Labor Cost + Remaining Labor Cost. Same as the budgeted labor cost if the activity is not started and the actual labor cost once the activity is completed. Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.AT_COMPLETION_LABOR_COST
Fact - Primavera -Activity History Costs At Completion Material Cost Fact The material cost at completion is the sum of the actual plus remaining cost for all material resources assigned to the activity. Computed as Actual Material Cost + Remaining Material Cost. Same as the budgeted material cost if the activity is not started and the actual material cost once the activity is completed. Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.AT_COMPLETION_MATERIAL_COST
Fact - Primavera -Activity History Costs At Completion Nonlabor Cost Fact The nonlabor cost at completion is the sum of the actual plus remaining cost for all nonlabor resources assigned to the activity. Computed as Actual Nonlabor Cost + Remaining Nonlabor Cost. Same as the budgeted nonlabor cost if the activity is not started and the actual nonlabor cost once the activity is completed. Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.AT_COMPLETION_NONLABOR_COST
Fact - Primavera -Activity History Costs At Completion Total Cost Fact The total cost at completion for the activity, including labor resources, nonlabor resources, material resources, and project expenses. At Completion Total Cost = At Completion Labor Cost + At Completion Nonlabor Cost + At Completion Material Cost + At Completion Expense Cost. Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.AT_COMPLETION_TOTAL_COST
Fact - Primavera -Activity History Costs Baseline Actual Expense Cost Fact The actual cost for all project expenses associated with the activity in the primary baseline Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.BL_ACTUAL_EXPENSE_COST
Fact - Primavera -Activity History Costs Baseline Actual Labor Cost Fact The actual cost for all labor resources assigned to the activity in the project baseline. If no resources are assigned, computed as the activity Baseline Project Actual Labor Units * Project Default Price / Time. Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.BL_ACTUAL_LABOR_COST
Fact - Primavera -Activity History Costs Baseline Actual Material Cost Fact The actual cost for all material resources assigned to the activity in the project baseline Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.BL_ACTUAL_MATERIAL_COST
Fact - Primavera -Activity History Costs Baseline Actual Nonlabor Cost Fact The actual cost for all nonlabor resources assigned to the activity in the project baseline. If no resources are assigned, computed as the activity Baseline Project Actual Nonlabor Units * Project Default Price / Time Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.BL_ACTUAL_NONLABOR_COST
Fact - Primavera -Activity History Costs Baseline Actual Total Cost Fact The actual total cost for the activity in the project baseline, including labor resources, nonlabor resources, material resources and project expenses. Baseline Project Actual Total Cost = Baseline Project Actual Labor Cost + Baseline Project Actual Nonlabor Cost + Baseline Project Actual Material Cost + Baseline Project Actual Expense Cost Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.BL_ACTUAL_TOTAL_COST
Fact - Primavera -Activity History Costs Baseline Project Expense Cost Fact The cost for all the project expenses associated with the activity in the project baseline. Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.BL_PLANNED_EXPENSE_COST
Fact - Primavera -Activity History Costs Baseline Project Labor Cost Fact The cost for all the labor resources assigned to an activity in the project baseline. Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.BL_PLANNED_LABOR_COST
Fact - Primavera -Activity History Costs Baseline Project Material Cost Fact Budgeted or (At Completion)cost for all material resources assigned to the activity in the project baseline. Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.BL_PLANNED_MATERIAL_COST
Fact - Primavera -Activity History Costs Baseline Project Nonlabor Cost Fact The cost for all the Nonlabor resources assigned to an activity in the project baseline Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.BL_PLANNED_NONLABOR_COST
Fact - Primavera -Activity History Costs Baseline Project Total Cost Fact The total cost of the activity in the project baseline, including labor resources, non-labor resources, material resources, and project expenses. Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.BL_PLANNED_TOTAL_COST
Fact - Primavera -Activity History Costs Planned Expense Cost Fact The budgeted cost for all project expenses associated with the activity. Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.PLANNED_EXPENSE_COST
Fact - Primavera -Activity History Costs Planned Labor Cost Fact The budgeted costs for all labor resources assigned to the activity. If no resources are assigned, computed as the activity Budgeted Labor Units * Project Default Price / Time. Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.PLANNED_LABOR_COST
Fact - Primavera -Activity History Costs Planned Material Cost Fact The budgeted costs for all material resources assigned to the activity. If no resources are assigned, computed as the activity Budgeted Labor Units * Project Default Price / Time. Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.PLANNED_MATERIAL_COST
Fact - Primavera -Activity History Costs Planned Nonlabor Cost Fact The budgeted costs for all nonlabor resources assigned to the activity. Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.PLANNED_NONLABOR_COST
Fact - Primavera -Activity History Costs Planned Total Cost Fact The budgeted total cost for the activity, including labor resources, nonlabor resources, material resources, and project expenses. Budgeted Total Cost = Budgeted Labor Cost + Budgeted Nonlabor Cost + Budgeted Material Cost + Budgeted Expense Cost. Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.PLANNED_TOTAL_COST
Fact - Primavera -Activity History Costs Remaining Expense Cost Fact The remaining cost for all project expenses associated with the activity. Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.REMAINING_EXPENSE_COST
Fact - Primavera -Activity History Costs Remaining Labor Cost Fact The remaining cost for all labor resources assigned to the activity. If no resources are assigned, computed as the activity Remaining Labor Units * Project Default Price / Time. Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.REMAINING_LABOR_COST
Fact - Primavera -Activity History Costs Remaining Late Expense Cost Fact Remaining Late Expense Cost Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.REMAINING_LATE_EXPENSE_COST
Fact - Primavera -Activity History Costs Remaining Late Labor Cost Fact Remaining Late Labor Cost Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.REMAINING_LATE_LABOR_COST
Fact - Primavera -Activity History Costs Remaining Late Material Cost Fact Remaining Late Material Cost Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.REMAINING_LATE_MATERIAL_COST
Fact - Primavera -Activity History Costs Remaining Late Nonlabor Cost Fact Remaining Late Nonlabor Cost Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.REMAINING_LATE_NONLABOR_COST
Fact - Primavera -Activity History Costs Period Remaining Late Total Cost Fact The Remaining Late Total Cost for the period specified Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.REMAINING_LATE_TOTAL_COST
Fact - Primavera -Activity History Costs Remaining Material Cost Fact The remaining cost for all material resources assigned to the activity. Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.REMAINING_MATERIAL_COST
Fact - Primavera -Activity History Costs Remaining Nonlabor Cost Fact The remaining cost for all nonlabor resources assigned to the activity. If no resources are assigned, computed as the activity Remaining Nonlabor Units * Project Default Price / Time. Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.REMAINING_NONLABOR_COST
Fact - Primavera -Activity History Costs Remaining Total Cost Fact The remaining total cost for the activity, including labor resources, nonlabor resources, material resources, and project expenses. Remaining Total Cost = Remaining Labor Cost + Remaining Nonlabor Cost + Remaining Material Cost + Remaining Expense Cost. Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.REMAINING_TOTAL_COST
Fact - Primavera -Activity History Dates Actual Finish Fact The date on which the activity actually finished Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.ACTUAL_FINISH_DATE
Fact - Primavera -Activity History Dates Actual Start Fact The date on which the activity actually started Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.ACTUAL_START_DATE
Fact - Primavera -Activity History Dates Baseline Project Finish Fact The Project Baseline Planned Finish Date. Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.BASELINE_FINISH_DATE
Fact - Primavera -Activity History Dates Baseline Project Start Fact The Project Baseline Planned Start Date. Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.BASELINE_START_DATE
Fact - Primavera -Activity History Dates Finish Fact The current finish date of the activity. Set to the activity remaining early finish date while the activity is not started or in progress, and the actual finish date once the activity is completed. Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.FINISH_DATE
Fact - Primavera -Activity History Dates Planned Finish Fact The date the activity is scheduled to finish. This date is computed by the project scheduler but can be updated manually by the project manager. This date is not changed by the project scheduler after the activity has been started. Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.PLANNED_FINISH_DATE
Fact - Primavera -Activity History Dates Planned Start Fact The date the activity is scheduled to begin. This date is computed by the project scheduler but can be updated manually by the project manager. This date is not changed by the project scheduler after the activity has been started. Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.PLANNED_START_DATE
Fact - Primavera -Activity History Dates Remaining Finish Fact Remaining Finish Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.REMAINING_FINISH_DATE
Fact - Primavera -Activity History Dates Remaining Start Fact Remaining Start Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.REMAINING_START_DATE
Fact - Primavera -Activity History Dates Start Fact The current start date of the activity. Set to the activity remaining early start date while the activity is not started, and the actual start date once the activity is started. Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.START_DATE
Fact - Primavera -Activity History Durations Actual Duration Fact Actual duration is the total working time from the activity actual start date to the actual finish date (for completed activities), or to the current data date (for in-progress activities). The actual working time is computed using the activity's calendar. Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.ACTUAL_DURATION
Fact - Primavera -Activity History Durations At Completion Duration Fact The duration at completion is the total working time from the activity's current start date to the current finish date. The current start date is the planned start date until the activity is started, then it is the actual start date. The current finish date is the activity planned finish date while the activity is not started, the remaining finish date while the activity is in progress, and the actual finish date once the activity is completed. The total working time is computed using the activity's calendar. Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.AT_COMPLETION_DURATION
Fact - Primavera -Activity History Durations Baseline Project Duration Fact The duration for the activity in the primary baseline. Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.BASELINE_DURATION
Fact - Primavera -Activity History Durations Variance - Baseline Project Duration Fact Variance duration is the duration between the activity' Baseline project duration and the At Completion duration. Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.DURATION_VARIANCE
Fact - Primavera -Activity History Durations Planned Duration Fact Planned Duration is the planned working time for the resource assignment on the activity, from the resource's planned start date to the planned finish date. The planned working time is computed using the calendar determined by the Activity Type. Resource Dependent activities use the resource's calendar; other activity types use the activity's calendar. This is the duration that Progress Reporter users follow and the schedule variance is measured against. Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.PLANNED_DURATION
Fact - Primavera -Activity History Durations Remaining Duration Fact Remaining duration is the total working time from the activity remaining start date to the remaining finish date. The remaining working time is computed using the activity's calendar. Before the activity is started, the remaining duration is the same as the Original Duration. After the activity is completed the remaining duration is zero. Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.REMAINING_DURATION
Fact - Primavera -Activity History Durations Total Float Fact The amount of time the activity can be delayed before delaying the project finish date. Total float can be computed as Late Start - Early Start or as Late Finish - Early Finish; this option can be set when running the project scheduler. Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.TOTAL_FLOAT
Fact - Primavera -Activity History Earned Value (Cost) Accounting Variance (Cost) Fact Accounting Variance is the Planned Value minus the Actual Cost. A negative value indicates that Actual Cost have exceeded the Planned Value "P6Core"."Fact - Activity Spread H"."Planned Value Cost" - "P6Core"."Fact - Activity Spread H"."Actual Cost"
Fact - Primavera -Activity History Earned Value (Cost) Budget At Completion (Cost) Fact Budget at Completion is the baseline Labor Cost + baseline Nonlabor Cost + baseline Expense Cost + baseline Material Cost. Same as the baseline Total Cost. Value Derived From: "P6Core"."Fact - Activity Spread H"."Baseline Project Total Cost"
Fact - Primavera -Activity History Earned Value (Cost) Cost Performance Index (Cost) Fact Cost Performance Index is the Earned Value divided by the Actual Cost. A value less than 1 indicates that Actual Cost have exceeded the Planned Value. Value Derived From: "P6Core"."Fact - Activity Spread H"."Earned Value Cost" / "P6Core"."Fact - Activity Spread H"."Actual Cost"
Fact - Primavera -Activity History Earned Value (Cost) Cost Schedule Index (Cost) Fact Cost Schedule Index By Cost Value Derived From: "P6Core"."Fact - Activity Spread H"."Cost Performance Index - (CPI)" * "P6Core"."Fact - Activity Spread H"."Schedule Performance Index (SPI) - Cost"
Fact - Primavera -Activity History Earned Value (Cost) Cost Variance (Cost) Fact Cost Variance is the Earned Value minus the Actual Cost. A negative value indicates that Actual Cost have exceeded the Planned Value. Valued Derived From: "P6Core"."Fact - Activity Spread H"."Earned Value Cost" - "P6Core"."Fact - Activity Spread H"."Actual Cost"
Fact - Primavera -Activity History Earned Value (Cost) Cost Variance Index (Cost) Fact Cost Variance Index is the Cost Variance divided by Earned Value. Value Derived From: "P6Core"."Fact - Activity Spread H"."Cost Variance" / "P6Core"."Fact - Activity Spread H"."Earned Value Cost"
Fact - Primavera -Activity History Earned Value (Cost) Earned Value (Cost) Fact Earned value cost for the project Value Derived From: sum(Fact_W_ACTIVITY_HISTORY_F_Activity_History.EARNED_VALUE_COST)
Fact - Primavera -Activity History Earned Value (Cost) Estimate At Completion (Cost) Fact Estimate Cost at Completion is the Actual Cost plus the Estimate to Complete Cost. The method for computing Estimate to Complete depends on the Earned Value technique selected for the activity's WBS. Value Derived From: sum(Fact_W_ACTIVITY_HISTORY_F_Activity_History.EST_AT_COMPLETION_COST)
Fact - Primavera -Activity History Earned Value (Cost) Estimate to Complete (Cost) Fact Calculated Estimate To Complete using specified technique Value Derived From: sum(Fact_W_ACTIVITY_HISTORY_F_Activity_History.EST_TO_COMPLETE_COST)
Fact - Primavera -Activity History Earned Value (Cost) Planned Value (Cost) Fact Planned cost of work scheduled for the project Derived From: sum(Fact_W_ACTIVITY_HISTORY_F_Activity_History.PLANNED_VALUE_COST)
Fact - Primavera -Activity History Earned Value (Cost) Schedule Performance Index (Cost) Fact Schedule Performance Index is the Earned Value divided by Planned Value. A value less than 1 indicates that less work was actually performed than was scheduled. Derived From: "P6Core"."Fact - Activity Spread H"."Earned Value Cost" / "P6Core"."Fact - Activity Spread H"."Planned Value Cost"
Fact - Primavera -Activity History Earned Value (Cost) Schedule Variance (Cost) Fact Schedule Variance is the Earned Value minus the Planned Value. A negative value indicates that less work was actually performed than was scheduled. Derived From: "P6Core"."Fact - Activity Spread H"."Earned Value Cost" - "P6Core"."Fact - Activity Spread H"."Planned Value Cost"
Fact - Primavera -Activity History Earned Value (Cost) Schedule Variance Index (Cost) Fact Schedule Variance Index is the Schedule Variance divided by Planned Value. Derived From: "P6Core"."Fact - Activity Spread H"."Schedule Variance - Cost" / "P6Core"."Fact - Activity Spread H"."Planned Value Cost"
Fact - Primavera -Activity History Earned Value (Cost) To Complete Performance Index - BAC (Cost) Fact The To Complete Performance Index is (Budget at Completion - Earned Value) / (Budget at Completion (BAC)- Actual Cost). ("P6Core"."Fact - Activity Spread H"."Baseline Project Total Cost" - "P6Core"."Fact - Activity Spread H"."Earned Value Cost") / ("P6Core"."Fact - Activity Spread H"."Baseline Project Total Cost" - "P6Core"."Fact - Activity Spread H"."Actual Cost")
Fact - Primavera -Activity History Earned Value (Cost) To Complete Performance Index - EAC (Cost) Fact The To Complete Performance Index is (Budget at Completion - Earned Value) / (Estimate at Completion - Actual Cost). Derived From: ("P6Core"."Fact - Activity Spread H"."Baseline Project Total Cost" - "P6Core"."Fact - Activity Spread H"."Earned Value Cost") / ("P6Core"."Fact - Activity Spread H"."Estimate At Completion Cost" - "P6Core"."Fact - Activity Spread H"."Actual Cost")
Fact - Primavera -Activity History Earned Value (Cost) Variance At Completion (Cost) Fact Variance At Completion is the Budget At Completion (baseline total cost) minus Estimate At Completion. Derived From: "P6Core"."Fact - Activity Spread H"."Baseline Project Total Cost" - "P6Core"."Fact - Activity Spread H"."Estimate At Completion Cost"
Fact - Primavera -Activity History Earned Value (Units) Accounting Variance (Units) Fact Accounting Variance Labor Units is the Planned Value Labor Units minus the Actual Units. Negative value indicates that Actual Units have exceeded the Planned Value Labor Units. Derived From: "P6Core"."Fact - Activity Spread H"."Planned Value Labor Units" - "P6Core"."Fact - Activity Spread H"."Actual Labor Units"
Fact - Primavera -Activity History Earned Value (Units) Budget At Completion (Units) Fact Budget at Completion Labor Units is the baseline Labor Units + baseline Nonlabor Labor Units + baseline Expense Labor Units + baseline Material Labor Units. Same as the baseline Total Labor Units. Derived From: "P6Core"."Fact - Activity Spread H"."Baseline Project Labor Units"
Fact - Primavera -Activity History Earned Value (Units) Cost Performance Index (Units) Fact Cost Performance Index Labor Units is the Earned Value Labor Units / Actual Labor Units. Derived From: "P6Core"."Fact - Activity Spread H"."Earned Value Labor Units" / "P6Core"."Fact - Activity Spread H"."Actual Labor Units"
Fact - Primavera -Activity History Earned Value (Units) Cost Schedule Index (Units) Fact Cost Schedule Index By Units Derived From: "P6Core"."Fact - Activity Spread H"."Cost Performance Index (CPI) - Labor Units" * "P6Core"."Fact - Activity Spread H"."Schedule Performance Index (SPI) - Labor Units"
Fact - Primavera -Activity History Earned Value (Units) Cost Variance (Units) Fact Cost Variance Labor Units is Earned Value Labor Units minus Actual Labor Units. Derived From: "P6Core"."Fact - Activity Spread H"."Earned Value Labor Units" - "P6Core"."Fact - Activity Spread H"."Actual Labor Units"
Fact - Primavera -Activity History Earned Value (Units) Cost Variance Index (Units) Fact Cost Variance Index is the Cost Variance divided by Earned Value. Derived From: "P6Core"."Fact - Activity Spread H"."Cost Variance - Labor Units" / "P6Core"."Fact - Activity Spread H"."Earned Value Labor Units"
Fact - Primavera -Activity History Earned Value (Units) Earned Value (Units) Fact Earned Value Labor Units Performed is the portion of the baseline Labor Units that is actually completed as of the project data date. Computed as baseline Labor Units * Performance % Complete. The Earned Value Labor Units is essentially the labor units earned value for the activity. The method for computing the Performance % Complete depends on the earned value technique selected for the activity's WBS. The baseline Labor Units is taken from the baseline. Derives From: sum(Fact_W_ACTIVITY_HISTORY_F_Activity_History.EARNED_VALUE_LABOR_UNITS)
Fact - Primavera -Activity History Earned Value (Units) Estimate At Completion (Units) Fact Estimate At Completion Labor Units is calculated as Actual Labor Units + Estimate To Complete Labor Units. (Estimate To Complete Labor Units is calculated based off of the Earned Value setting on the WBS.) Derives From: sum(Fact_W_ACTIVITY_HISTORY_F_Activity_History.EST_AT_COMPLETION_LABOR_UNITS)
Fact - Primavera -Activity History Earned Value (Units) Estimate To Complete (Units) Fact The estimated quantity to complete of the activity. Computed as either the remaining total units for the activity, or as Performance Factor * (Baseline Budgeted Labor Units - Budgeted Quantity of Work Performed), depending on the Earned Value Technique selected for the activity's WBS. Derives From: sum(Fact_W_ACTIVITY_HISTORY_F_Activity_History.EST_TO_COMPLETE_LABOR_UNITS)
Fact - Primavera -Activity History Earned Value (Units) Planned Value (Units) Fact Planned Value Labor Units Scheduled is the portion of the baseline Labor Units that is scheduled to be completed as of the project data date. For activities without resource assignments, and for activity resource assignments that do not have resource curves, computed as baseline Labor Units * Schedule % Complete. For activity resource assignments that do have resource curves, the curve distribution is additionally factored into the calculation. The Schedule % Complete specifies how much of the activity's baseline duration has been completed so far. The baseline Labor Units is taken from the baseline. Derives From: sum(Fact_W_ACTIVITY_HISTORY_F_Activity_History.PLANNED_VALUE_LABOR_UNITS)
Fact - Primavera -Activity History Earned Value (Units) Schedule Performance Index (Units) Fact Schedule Performance Index Labor Units is the Earned Value Labor Units divided by Planned Value Labor Units. Derives From: "P6Core"."Fact - Activity Spread H"."Earned Value Cost" / "P6Core"."Fact - Activity Spread H"."Planned Value Cost"
Fact - Primavera -Activity History Earned Value (Units) Schedule Variance (Units) Fact Schedule Variance Labor Units is the Earned Value Labor Units minus Planned Value Labor Units. Derives From: "P6Core"."Fact - Activity Spread H"."Earned Value Labor Units" - "P6Core"."Fact - Activity Spread H"."Planned Value Labor Units"
Fact - Primavera -Activity History Earned Value (Units) Schedule Variance Index (Units) Fact Schedule Variance Index is the Schedule Variance Labor Units divided by the Planned Value Labor Units. Derives From: "P6Core"."Fact - Activity Spread H"."Schedule Variance - Labor Units" / "P6Core"."Fact - Activity Spread H"."Planned Value Labor Units"
Fact - Primavera -Activity History Earned Value (Units) To Complete Performance Index - BAC (Units) Fact The To Complete Performance Index is (Budget at Completion (BAC) - Earned Value Labor Units) / (Budget at Completion (BAC) - Actual Labor Units). Derives From: ("P6Core"."Fact - Activity Spread H"."Budget At Completion (BAC) - Labor Units" - "P6Core"."Fact - Activity Spread H"."Earned Value Labor Units") / ("P6Core"."Fact - Activity Spread H"."Budget At Completion (BAC) - Labor Units" - "P6Core"."Fact - Activity Spread H"."Actual Labor Units")
Fact - Primavera -Activity History Earned Value (Units) To Complete Performance Index - EAC (Units) Fact The To Complete Performance Index is (Budget at Completion (EAC) - Earned Value Labor Units) / (Estimated at Completion - Actual Labor Units). Derives From: ("P6Core"."Fact - Activity Spread H"."Budget At Completion (BAC) - Labor Units" - "P6Core"."Fact - Activity Spread H"."Earned Value Labor Units") / ("P6Core"."Fact - Activity Spread H"."Estimate At Completion - Labor Units" - "P6Core"."Fact - Activity Spread H"."Actual Labor Units")
Fact - Primavera -Activity History Earned Value (Units) Variance At Completion (Units) Fact Variance At Completion is the Planned Labor Units minus Estimate At Completion Labor Units. Derives From: "P6Core"."Fact - Activity Spread H"."Baseline Project Labor Units" - "P6Core"."Fact - Activity Spread H"."Estimate At Completion - Labor Units"
Fact - Primavera -Activity History Units Actual Labor Units Fact The actual units for all labor resources assigned to the activity. Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.ACTUAL_LABOR_UNITS
Fact - Primavera -Activity History Units Actual Nonlabor Units Fact The actual units for all nonlabor resources assigned to the activity. Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.ACTUAL_NONLABOR_UNITS
Fact - Primavera -Activity History Units At Completion Labor Units Fact The labor units at completion is the sum of the actual plus remaining units for all labor resources assigned to the activity. Computed as Actual Labor Units + Remaining Labor Units. Same as the budgeted labor units if the activity is not started and the actual labor units once the activity is completed. Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.AT_COMPLETION_LABOR_UNITS
Fact - Primavera -Activity History Units At Completion Nonlabor Units Fact The nonlabor units at completion is the sum of the actual plus remaining units for all nonlabor resources assigned to the activity. Computed as Actual Nonlabor Units + Remaining Nonlabor Units. Same as the budgeted nonlabor units if the activity is not started and the actual nonlabor units once the activity is completed. Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.AT_COMPLETION_NONLABOR_UNITS
Fact - Primavera -Activity History Units Baseline Actual Labor Units Fact The actual units for all labor resources assigned to the activity in the project baseline Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.BL_ACTUAL_LABOR_UNITS
Fact - Primavera -Activity History Units Baseline Actual Nonlabor Units Fact The actual units for all nonlabor resources assigned to the activity in the project baseline Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.BL_ACTUAL_NONLABOR_UNITS
Fact - Primavera -Activity History Units Baseline Project Labor Units Fact The sum of the Budgeted (or At Completion) units for all labor resources assigned to the activity in the project baseline. Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.BL_PLANNED_LABOR_UNITS
Fact - Primavera -Activity History Period Units Baseline Project Nonlabor Units Fact The sum of the Budgeted (or At Completion) units for all nonlabor resources assigned to the activity in the project baseline Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.BL_PLANNED_NONLABOR_UNITS
Fact - Primavera -Activity History Period Units Next This Period Labor Units Fact This Period Labor Units for the period after the period specified Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.NEXT_PER_LABOR_UNITS_P
Fact - Primavera -Activity History Period Units Next This Period Nonlabor Units Fact This Period Nonlabor Units for the period after the period specified Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.NEXT_PER_NONLABOR_UNITS_P
Fact - Primavera -Activity History Period Units Period Actual Labor Units Fact Period Actual Labor Units Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.ACTUAL_LABOR_UNITS_P
Fact - Primavera -Activity History Period Units Period Actual Nonlabor Units Fact The Actual Nonlabor Units for the period specified Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.ACTUAL_NONLABOR_UNITS_P
Fact - Primavera -Activity History Period Units Period At Completion Labor Units Fact The At Completion Labor Units for the period specified Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.AT_COMPLETION_LABOR_UNITS_P
Fact - Primavera -Activity History Period Units Period Baseline Actual Labor Units Fact The Baseline Actual Labor Units for the period specified Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.BL_ACTUAL_LABOR_UNITS_P
Fact - Primavera -Activity History Period Units Period Baseline Actual Nonlabor Units Fact The Baseline Actual Nonlabor Units for the period specified Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.BL_ACTUAL_NONLABOR_UNITS_P
Fact - Primavera -Activity History Period Units Period Baseline Project Labor Units Fact The Baseline Project Labor Units for the period specified Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.BL_PLANNED_LABOR_UNITS_P
Fact - Primavera -Activity History Period Units Period Baseline Project Nonlabor Units Fact The Baseline Project Nonlabor Units for the period specified Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.BL_PLANNED_NONLABOR_UNITS_P
Fact - Primavera -Activity History Period Units Period Earned Value Labor Units Fact The Earned Value Labor Units for the period specified Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.EARNED_VALUE_LABOR_UNITS_P
Fact - Primavera -Activity History Period Units Period Estimate At Completion Labor Units Fact The Estimate At Completion Labor Units for the period specified Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.EST_AT_COMPL_LABOR_UNITS_P
Fact - Primavera -Activity History Period Units Period Estimate To Completion Labor Units Fact The Estimate to Completion Labor Units for the period specified Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.EST_TO_COMPLETE_LABOR_UNITS_P
Fact - Primavera -Activity History Period Units Period Planned Labor Units Fact Period Planned Labor Units Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.PLANNED_LABOR_UNITS_P
Fact - Primavera -Activity History Period Units Period Planned Nonlabor Units Fact The Planned Nonlabor Units for the period specified Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.PLANNED_NONLABOR_UNITS_P
Fact - Primavera -Activity History Period Units Period Planned Value Labor Units Fact The Planned Value Labor Units for the period specified Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.PLANNED_VALUE_LABOR_UNITS_P
Fact - Primavera -Activity History Period Units Period Remaining Labor Units Fact The Remaining Labor Units for the period specified Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.REMAINING_LABOR_UNITS_P
Fact - Primavera -Activity History Period Units Period Remaining Late Labor Units Fact The Remaining Late Labor Units for the period specified Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.REMAINING_LATE_LABOR_UNITS_P
Fact - Primavera -Activity History Period Units Period Remaining Late Nonlabor Units Fact The Remaining Late Nonlabor Units for the period specified Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.REM_LATE_NONLABOR_UNITS_P
Fact - Primavera -Activity History Period Units Period Remaining Nonlabor Units Fact The Remaining Nonlabor Units for the period specified Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.REMAINING_NONLABOR_UNITS_P
Fact - Primavera -Activity History Period Units Period At Completion Nonlabor Units Fact The At Completion Nonlabor Units for the period specified Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.AT_COMPLETION_NONLABOR_UNITS_P
Fact - Primavera -Activity History Units Planned Labor Units Fact The budgeted units for all labor resources assigned to the activity. Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.PLANNED_LABOR_UNITS
Fact - Primavera -Activity History Units Planned Nonlabor Units Fact The budgeted units for all nonlabor resources assigned to the activity. Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.PLANNED_NONLABOR_UNITS
Fact - Primavera -Activity History Period Units Previous This Period Labor Units Fact Previous This Period Labor Units Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.PREV_THIS_PER_LABOR_UNITS
Fact - Primavera -Activity History Period Units Previous This Period Nonlabor Units Fact The Nonlabor Units planned for the previous period Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.PREV_THIS_PER_NONLABOR_UNITS
Fact - Primavera -Activity History Units Remaining Labor Units Fact The remaining units for all labor resources assigned to the activity. The remaining units reflects the work remaining to be done for the activity. Before the activity is started, the remaining units are the same as the budgeted units. After the activity is completed, the remaining units are zero. Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.REMAINING_LABOR_UNITS
Fact - Primavera -Activity History Units Remaining Late Labor Units Fact Remaining Late Labor Units Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.REMAINING_LATE_LABOR_UNITS
Fact - Primavera -Activity History Units Remaining Late Nonlabor Units Fact Remaining Late Nonlabor Units Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.REMAINING_LATE_NONLABOR_UNITS
Fact - Primavera -Activity History Units Remaining Nonlabor Units Fact The remaining units for all nonlabor resources assigned to the activity. The remaining units reflects the work remaining to be done for the activity. Before the activity is started, the remaining units are the same as the budgeted units. After the activity is completed, the remaining units are zero. Value Derived From : Fact_W_ACTIVITY_HISTORY_F_Activity_History.REMAINING_NONLABOR_UNITS
Fact - Primavera -Activity History Metrics # Of Activities Fact # Of Activities Value Derived From: count(distinct Fact_W_ACTIVITY_HISTORY_F_Activity_History.ACTIVITY_WID)
Fact - Primavera -Activity History Metrics # Of Projects Fact # Of Projects Value Derived From: count(distinct Fact_W_ACTIVITY_HISTORY_F_Activity_History.PROJECT_WID)
Fact - Primavera -Activity History Metrics Completed Last Period Fact Activities with Completed status at the time of the previous ETL run Value Derived From: sum(Fact_W_ACTIVITY_HISTORY_F_Activity_History.COMPLETED_LAST_PERIOD)
Fact - Primavera -Activity History Metrics Completed This Period Fact Activities whose actual finish date fell between the period start and period end for this ETL run Value Derived From: sum(Fact_W_ACTIVITY_HISTORY_F_Activity_History.COMPLETED_THIS_PERIOD)
Fact - Primavera -Activity History Metrics Delayed This Period Fact Activities planned to start between the period start and period end with no actual start date Value Derived From: sum(Fact_W_ACTIVITY_HISTORY_F_Activity_History.DELAYED_THIS_PERIOD)
Fact - Primavera -Activity History Metrics Emergent Count Fact Activities added before the period start date of this ETL run Value Derived From: sum(Fact_W_ACTIVITY_HISTORY_F_Activity_History.EMERGENT_WORK)
Fact - Primavera -Activity History Metrics In Progress Last Period Fact Activities with In Progress status at the time of the previous ETL run Value Derived From: sum(Fact_W_ACTIVITY_HISTORY_F_Activity_History.IN_PROGRESS_LAST_PERIOD)
Fact - Primavera -Activity History Metrics In Progress This Period Fact Activities whose actual start date fell between the period start and period end for this ETL run Value Derived From: sum(Fact_W_ACTIVITY_HISTORY_F_Activity_History.IN_PROGRESS_THIS_PERIOD)
Fact - Primavera -Activity History Metrics Not Started Last Period Fact Activities with Not Started status at the time of the previous ETL run Value Derived From: sum(Fact_W_ACTIVITY_HISTORY_F_Activity_History.NOT_STARTED_LAST_PERIOD)
Fact - Primavera -Activity History Metrics Not Started This Period Fact The number of activities that are Not Started during the specific Project History Interval. Value Derived From: sum(Fact_W_ACTIVITY_HISTORY_F_Activity_History.NOT_STARTED_ACTIVITY_COUNT)
Fact - Primavera -Activity History Metrics Risk Exposure Fact The calculated exposure value for the risk Value Derived From: sum(Fact_W_ACTIVITY_HISTORY_F_Activity_History.PROJECT_RISK_EXPOSURE)
Fact - Primavera -Activity History Metrics Risk Score Fact The calculated score value of the impact values assigned to the risk Value Derived From: sum(Fact_W_ACTIVITY_HISTORY_F_Activity_History.PROJECT_RISK_SCORE)
Fact - Primavera -Activity History Percent Completes Cost % Complete Fact The percent complete of cost for all labor resources, nonlabor resources, material resources, and expenses for the activity. Computed as Actual Total Cost / At Completion Total Cost * 100. Always in the range 0 to 100. Value Derived From: sum(Fact_W_ACTIVITY_HISTORY_F_Activity_History.ACTUAL_TOTAL_COST) / nullif( sum(Fact_W_ACTIVITY_HISTORY_F_Activity_History.AT_COMPLETION_TOTAL_COST) , 0) * 100
Fact - Primavera -Activity History Percent Completes Cost % of Planned Fact The proportion of the cost budget that has been spent. Computed as actual total cost / baseline total cost. Value Derived From: "P6Core"."Fact - Activity Spread H"."Actual Cost" / "P6Core"."Fact - Activity Spread H"."Budget at Completion" * 100
Fact - Primavera -Activity History Percent Completes Expense Cost % Complete Fact The percent complete of cost for all expenses associated with the wbs. Computed as Actual Expense Cost / At Complete Expense Cost * 100. Always in the range 0 to 100. Value Derived From: "P6Core"."Fact - Activity Spread H"."Actual Expense Cost" / "P6Core"."Fact - Activity Spread H"."At Completion Expense Cost" * 100
Fact - Primavera -Activity History Percent Completes Labor Cost % Complete Fact The percent complete of cost for all labor resources assigned to the wbs. Computed as Actual Labor Cost / At Complete Labor Cost * 100. Always in the range 0 to 100. sum(Fact_W_ACTIVITY_HISTORY_F_Activity_History.ACTUAL_LABOR_COST) / nullif( sum(Fact_W_ACTIVITY_HISTORY_F_Activity_History.AT_COMPLETION_LABOR_COST) , 0) * 100
Fact - Primavera -Activity History Percent Completes Labor Units % Complete Fact The percent complete of units for all labor resources for the activity. Computed as Actual Labor Units / At Completion Labor Units * 100. Always in the range 0 to 100. sum(Fact_W_ACTIVITY_HISTORY_F_Activity_History.ACTUAL_LABOR_UNITS) / nullif( sum(Fact_W_ACTIVITY_HISTORY_F_Activity_History.AT_COMPLETION_LABOR_UNITS) , 0) * 100
Fact - Primavera -Activity History Percent Completes Material Cost % Complete Fact The percent complete of cost for all material resources assigned to the wbs. Computed as Actual Material Cost / At Complete Material Cost * 100. Always in the range 0 to 100. sum(Fact_W_ACTIVITY_HISTORY_F_Activity_History.ACTUAL_MATERIAL_COST) / nullif( sum(Fact_W_ACTIVITY_HISTORY_F_Activity_History.AT_COMPLETION_MATERIAL_COST) , 0) * 100
Fact - Primavera -Activity History Percent Completes Nonlabor Cost % Complete Fact The percent complete of cost for all nonlabor resources assigned to the wbs. Computed as Actual Nonlabor Cost / At Complete Nonlabor Cost * 100. Always in the range 0 to 100. sum(Fact_W_ACTIVITY_HISTORY_F_Activity_History.ACTUAL_NONLABOR_COST) / nullif( sum(Fact_W_ACTIVITY_HISTORY_F_Activity_History.AT_COMPLETION_NONLABOR_COST) , 0) * 100
Fact - Primavera -Activity History Percent Completes Nonlabor Units % Complete Fact The percent complete of units for all nonlabor resources for the activity. Computed as Actual Nonlabor Units / At Completion Nonlabor Units * 100. Always in the range 0 to 100. sum(Fact_W_ACTIVITY_HISTORY_F_Activity_History.ACTUAL_NONLABOR_UNITS) / nullif( sum(Fact_W_ACTIVITY_HISTORY_F_Activity_History.AT_COMPLETION_NONLABOR_UNITS) , 0) * 100
Fact - Primavera -Activity History Percent Completes Performance % Complete Fact The activity performance percent complete. The performance percent complete is used to compute earned value and may be based on the Activity % Complete, on the 0/100 rule, on the 50/50 rule, etc., depending on the technique for computing earned-value percent complete for the activity's WBS. The Performance % Complete specifies what percentage of the activity's planned worth has been earned so far. P6Core."Fact - Activity Spread H"."Earned Value Cost" / P6Core."Fact - Activity Spread H"."Budget at Completion" * 100
Fact - Primavera -Activity History Percent Completes Perfomance % Complete (Units) Fact Perfomance % Complete (Units) IFNULL(P6Core."Fact - Activity Spread H"."Earned Value Labor Units", 0) / IFNULL(P6Core."Fact - Activity Spread H"."Budget At Completion (BAC) - Labor Units", 0) * 100
Fact - Primavera -Activity History Percent Completes Schedule % Complete Fact Schedule % Complete P6Core."Fact - Activity Spread H"."Planned Value Cost" / P6Core."Fact - Activity Spread H"."Budget at Completion" * 100
Fact - Primavera -Activity History Percent Completes Schedule % Complete (Units) Fact Schedule % Complete (Units) IFNULL(P6Core."Fact - Activity Spread H"."Earned Value Labor Units", 0) / IFNULL(P6Core."Fact - Activity Spread H"."Budget At Completion (BAC) - Labor Units", 0) * 100
Fact - Primavera -Activity History Percent Completes Units % Complete Fact The percent complete of units for all labor and nonlabor resources assigned to the activity. Computed as Actual Units / At Completion Units * 100. Always in the range 0 to 100. ( IFNULL(P6Core."Fact - Activity Spread H"."Actual Labor Units", 0) + IFNULL(P6Core."Fact - Activity Spread H"."Actual Nonlabor Units", 0)) / ( IFNULL(P6Core."Fact - Activity Spread H"."At Completion Labor Units", 0) + IFNULL(P6Core."Fact - Activity Spread H"."At Completion Nonlabor Units", 0)) * 100
           
Activity Folder          
Activity Dates - (Activity) Actual Finish Dimension The date on which the activity actually finished Dim_W_ACTIVITY_HD_Activity.ACTUAL_FINISH_DATE"
Activity Dates - (Activity) Actual Start Dimension The date on which the activity actually started Value Derived From : Dim_W_ACTIVITY_HD_Activity.ACTUAL_START_DATE
Activity Dates - (Activity) Baseline Project Finish Dimension The Project Baseline Planned Finish Date. Value Derived From : Dim_W_ACTIVITY_HD_Activity.BASELINE_FINISH_DATE
Activity Dates - (Activity) Baseline Project Start Dimension The Project Baseline Planned Start Date. Value Derived From : Dim_W_ACTIVITY_HD_Activity.BASELINE_START_DATE
Activity Dates - (Activity) Data Date Dimension The current data date for the project. The project status is up to date as of the data date. The data date is modified when project actuals are applied. Value Derived From : Dim_W_ACTIVITY_HD_Activity.DATA_DATE
Activity Dates - (Activity) Early Finish Dimension The earliest possible date the activity can finish. This date is calculated by the project scheduler based on activity relationships, schedule constraints, and resource availability. Value Derived From : Dim_W_ACTIVITY_HD_Activity.EARLY_FINISH_DATE
Activity Dates - (Activity) Early Start Dimension The earliest possible date the remaining work for the activity can begin. This date is calculated by the project scheduler based on activity relationships, schedule constraints, and resource availability. Value Derived From : Dim_W_ACTIVITY_HD_Activity.EARLY_START_DATE
Activity Dates - (Activity) Effective End Date Dimension The end date this version of the record is effective Value Derived From : Dim_W_ACTIVITY_HD_Activity.EFFECTIVE_END_DATE
Activity Dates - (Activity) Effective Start Date Dimension The start date this version of the record is effective Value Derived From : Dim_W_ACTIVITY_HD_Activity.EFFECTIVE_START_DATE
Activity Dates - (Activity) Expected Finish Dimension The date the activity is expected to finish. Typically, this date is entered in the Timesheets module by the primary resource. Value Derived From : Dim_W_ACTIVITY_HD_Activity.EXPECT_FINISH_DATE
Activity Dates - (Activity) External Early Start Dimension The External Early Start date is the earliest finish date of all lost external relationships. This field is populated only during import when a relationship is lost because it does not exist in the current database. This date may be used to calculate the start date of the current activity in place of the true relationship when scheduling. Value Derived From : Dim_W_ACTIVITY_HD_Activity.EXTERNAL_EARLY_START_DATE
Activity Dates - (Activity) External Late Finish Dimension The External Late Finish date is the latest start date of all lost external relationships. This field is populated only during import when a relationship is lost because it does not exist in the current database. This date may be used to calculate the finish date of the current activity in place of the true relationship when scheduling. Value Derived From : Dim_W_ACTIVITY_HD_Activity.EXTERNAL_LATE_FINISH_DATE
Activity Dates - (Activity) Finish Dimension The current finish date of the activity. Set to the activity remaining early finish date while the activity is not started or in progress, and the actual finish date once the activity is completed. Value Derived From : Dim_W_ACTIVITY_HD_Activity.FINISH_DATE
Activity Dates - (Activity) Late Finish Dimension The latest possible date the activity must finish without delaying the project finish date. This date is calculated by the project scheduler based on activity relationships, schedule constraints, and resource availability. Value Derived From : Dim_W_ACTIVITY_HD_Activity.LATE_FINISH_DATE
Activity Dates - (Activity) Late Start Dimension The latest possible date the remaining work for the activity must begin without delaying the project finish date. This date is calculated by the project scheduler based on activity relationships, schedule constraints, and resource availability. Value Derived From : Dim_W_ACTIVITY_HD_Activity.LATE_START_DATE
Activity Dates - (Activity) Planned Finish Dimension The date the activity is scheduled to finish. This date is computed by the project scheduler but can be updated manually by the project manager. This date is not changed by the project scheduler after the activity has been started. Value Derived From : Dim_W_ACTIVITY_HD_Activity.PLANNED_FINISH_DATE
Activity Dates - (Activity) Planned Start Dimension The date the activity is scheduled to begin. This date is computed by the project scheduler but can be updated manually by the project manager. This date is not changed by the project scheduler after the activity has been started. Value Derived From : Dim_W_ACTIVITY_HD_Activity.PLANNED_START_DATE
Activity Dates - (Activity) Primary Constraint Date Dimension The constraint date for the activity, if the activity has a constraint. The activity's constraint type determines whether this is a start date or finish date. Activity constraints are used by the project scheduler. Value Derived From : Dim_W_ACTIVITY_HD_Activity.PRIMARY_CONSTRAINT_DATE
Activity Dates - (Activity) Remaining Early Finish Dimension The date the remaining work for the activity is scheduled to finish. This date is computed by the project scheduler but can be updated manually by the project manager. Before the activity is started, the remaining finish date is the same as the planned finish date. This is the finish date that Progress Reporter users follow. Value Derived From : Dim_W_ACTIVITY_HD_Activity.REMAINING_FINISH_DATE
Activity Dates - (Activity) Remaining Early Start Dimension The date the remaining work for the activity is scheduled to begin. This date is computed by the project scheduler but can be updated manually by the project manager. Before the activity is started, the remaining start date is the same as the planned start date. This is the start date that Progress Reporter users follow. Value Derived From : Dim_W_ACTIVITY_HD_Activity.REMAINING_START_DATE
Activity Dates - (Activity) Remaining Late Finish Dimension Remaining late end date is calculated by the scheduler. Value Derived From : Dim_W_ACTIVITY_HD_Activity.REMAINING_LATE_FINISH_DATE
Activity Dates - (Activity) Remaining Late Start Dimension Remaining late start date is calculated by the scheduler. Value Derived From : Dim_W_ACTIVITY_HD_Activity.REMAINING_LATE_START_DATE
Activity Dates - (Activity) Resume Date Dimension The date progress is resumed on an activity. Value Derived From : Dim_W_ACTIVITY_HD_Activity.RESUME_DATE
Activity Dates - (Activity) Secondary Constraint Date Dimension The second constraint date for the activity, if the activity has a constraint. Value Derived From : Dim_W_ACTIVITY_HD_Activity.SECONDARY_CONSTRAINT_DATE
Activity Dates - (Activity) Start Dimension The current start date of the activity. Set to the activity remaining early start date while the activity is not started, and the actual start date once the activity is started. Value Derived From : Dim_W_ACTIVITY_HD_Activity.START_DATE
Activity Dates - (Activity) Suspend Date Dimension The date progress is suspended on an activity. Value Derived From : Dim_W_ACTIVITY_HD_Activity.SUSPEND_DATE
Activity Durations - (Activity) Actual Duration Dimension Actual duration is the total working time from the activity actual start date to the actual finish date (for completed activities), or to the current data date (for in-progress activities). The actual working time is computed using the activity's calendar. Value Derived From : Dim_W_ACTIVITY_HD_Activity.ACTUAL_DURATION
Activity Durations - (Activity) At Completion Duration Dimension The duration at completion is the total working time from the activity's current start date to the current finish date. The current start date is the planned start date until the activity is started, then it is the actual start date. The current finish date is the activity planned finish date while the activity is not started, the remaining finish date while the activity is in progress, and the actual finish date once the activity is completed. The total working time is computed using the activity's calendar. Value Derived From : Dim_W_ACTIVITY_HD_Activity.AT_COMPLETION_DURATION
Activity Durations - (Activity) Baseline Project Duration Dimension The duration for the activity in the primary baseline. Value Derived From : Dim_W_ACTIVITY_HD_Activity.BASELINE_DURATION
Activity Durations - (Activity) Baseline Planned Duration Dimension Baseline Planned Duration is the total working time from the baseline activity planned start date to the baseline planned finish date. The baseline planned working time is computed using the activity's calendar. Value Derived From : Dim_W_ACTIVITY_HD_Activity.BASELINE_PLANNED_DURATION
Activity Durations - (Activity) Free Float Dimension The amount of time the activity can be delayed before delaying the start date of any successor activity. Value Derived From : Dim_W_ACTIVITY_HD_Activity.FREE_FLOAT
Activity Durations - (Activity) Original Duration Dimension Original Duration is the total working time from the activity planned start date to the planned finish date. The planned working time is computed using the activity's calendar. Value Derived From : Dim_W_ACTIVITY_HD_Activity.PLANNED_DURATION
Activity Durations - (Activity) Remaining Duration Dimension Remaining duration is the total working time from the activity remaining start date to the remaining finish date. The remaining working time is computed using the activity's calendar. Before the activity is started, the remaining duration is the same as the Original Duration. After the activity is completed the remaining duration is zero. Value Derived From : Dim_W_ACTIVITY_HD_Activity.REMAINING_DURATION
Activity Durations - (Activity) Remaining Float Dimension The amount of time remaining by which the activity can be delayed before delaying the project finish date. Computed as Late Finish - Remaining Finish. If the remaining finish is the same as the early finish ( in general, when the activity is not started), then the remaining float is the same as the total float. Value Derived From : Dim_W_ACTIVITY_HD_Activity.REMAINING_FLOAT
Activity Durations - (Activity) Total Float Dimension The amount of time the activity can be delayed before delaying the project finish date. Total float can be computed as Late Start - Early Start or as Late Finish - Early Finish; this option can be set when running the project scheduler. Value Derived From : Dim_W_ACTIVITY_HD_Activity.TOTAL_FLOAT
Activity Durations - (Activity) Variance - Baseline Project Duration Dimension Variance duration is the duration between the activity' Baseline project duration and the At Completion duration. Value Derived From : Dim_W_ACTIVITY_HD_Activity.DURATION_VARIANCE
Activity Durations - (Activity) Variance - Baseline Project Finish Date Dimension Variance Finish Date is the duration between the Baseline project finish date and the finish date in the current project. Value Derived From : Dim_W_ACTIVITY_HD_Activity.FINISH_DATE_VARIANCE
Activity Durations - (Activity) Variance - Baseline Project Start Date Dimension Variance Start Date is the duration between the Baseline project start date and the start date in the current project. Value Derived From : Dim_W_ACTIVITY_HD_Activity.START_DATE_VARIANCE
Activity General - (Activity) Activity ID Dimension A short ID which uniquely identifies the activity within the project. Value Derived From : Dim_W_ACTIVITY_HD_Activity.ACTIVITY_ID
Activity General - (Activity) Activity Name Dimension The name of the activity. The activity name does not have to be unique. Value Derived From : Dim_W_ACTIVITY_HD_Activity.ACTIVITY_NAME
Activity General - (Activity) Owner Dimension User who owns the activity. Value Derived From : Dim_W_ACTIVITY_HD_Activity.ACTIVITY_OWNER
Activity General - (Activity) Activity Status Dimension The current status of the activity, either Not Started, In Progress, or Completed. Value Derived From : Dim_W_ACTIVITY_HD_Activity.ACTIVITY_STATUS
Activity General - (Activity) Activity Type Dimension The type of activity, either 'Task Dependent', 'Resource Dependent', 'Level of Effort', 'Start Milestone' or 'Finish Milestone'. A Task Dependent activity is scheduled using the activity's calendar rather than the calendars of the assigned resources. A Resource Dependent activity is scheduled using the calendars of the assigned resources. This type is used when several resources are assigned to the activity, but they may work separately. A Start/Finish Milestone is a zero-duration activity, marking a significant start/end of project event. A Level of Effort activity has a duration which is determined by its dependent activities. Administration-type activities are typically level of effort. Value Derived From : Dim_W_ACTIVITY_HD_Activity.ACTIVITY_TYPE
Activity General - (Activity) Auto Compute Actuals Dimension Identifies whether the actual and remaining units, start date, finish date, and percent complete for the activity are computed automatically using the planned dates, budgeted units and the activity's schedule percent complete. If this option is selected, the actual/remaining units and actual dates are automatically updated when project actuals are applied. This assumes that all work for the activity proceeds according to plan. Value Derived From : Dim_W_ACTIVITY_HD_Activity.AUTO_COMPUTE_ACTUALS_FLAG
Activity General - (Activity) Calendar Name Dimension The calendar assigned to the activity. Activity calendars can be assigned from the global calendar pool or the project calendar pool. Value Derived From : Dim_W_ACTIVITY_HD_Activity.CALENDAR_NAME
Activity General - (Activity) Criticality Index Dimension Criticality Index Value Derived From : Dim_W_ACTIVITY_HD_Activity.CRITICALITY_INDEX
Activity General - (Activity) Current Flag Dimension Indicates if a record is current (1,0) Value Derived From : Dim_W_ACTIVITY_HD_Activity.CURRENT_FLAG
Activity General - (Activity) Duration Type Dimension The duration type of the activity. One of Fixed Units per Time, Fixed Duration, or Fixed Units. For Fixed Units per Time activities, the resource units per time are constant when the activity duration or units are changed. This type is used when an activity has fixed resources with fixed productivity output per time period. For Fixed Duration activities, the activity duration is constant as the units or resource units per time are changed. This type is used when the activity is to be completed within a fixed time period regardless of the resources assigned. For Fixed Units activities, the activity units are constant when the duration or resource units per time are changed. This type is used when the total amount of work is fixed, and increasing the resources can decrease the activity duration. Value Derived From : Dim_W_ACTIVITY_HD_Activity.DURATION_TYPE
Activity General - (Activity) Critical Dimension Indicates whether the activity is critical. An activity is critical when its Total Float is below the critical duration specified for the project. Delaying critical activities will delay the finish date of the project. Value Derived From : Dim_W_ACTIVITY_HD_Activity.CRITICALITY_INDEX
Activity General - (Activity) Longest Path Dimension Indicates whether an activity is on the longest path. The longest path is defined as activities that are on the critical path and determine the end date of the project. Defining critical activities based on the longest path in the project provides an alternative to viewing critical activities based on float. Value Derived From : Dim_W_ACTIVITY_HD_Activity.IS_LONGEST_PATH
Activity General - (Activity) Activity Leveling Priority Dimension The activity priority can be used to prioritize activities in a project when performing resource leveling. Value Derived From : Dim_W_ACTIVITY_HD_Activity.LEVELING_PRIORITY
Activity General - (Activity) Percent Complete Type Dimension The activity percent complete type is one of Duration, Units, or Physical. The percent complete type controls whether the Activity % Complete is tied to the Duration % Complete, the Units % Complete, or the Physical % Complete for the activity. Set the percent complete type to Duration for activities which are duration driven, for example, administration tasks and training classes. Set the percent complete type to Physical for activities which are work-product driven, for example, creating a document or a product. Set the percent complete type to Units for activities which are work effort driven, for example, providing a consulting service. Value Derived From : Dim_W_ACTIVITY_HD_Activity.COMPLETE_PCT_TYPE
Activity General - (Activity) Primary Constraint Dimension The type of constraint applied to the activity start or finish date. Activity constraints are used by the project scheduler. Start date constraints are 'Start On', 'Start On or Before', 'Start On or After' and 'Mandatory Start'. Finish date constraints are 'Finish On', 'Finish On or Before', 'Finish On or After' and 'Mandatory Finish'. Another type of constraint, 'As Late as Possible', schedules the activity as late as possible based on the available free float. Value Derived From : Dim_W_ACTIVITY_HD_Activity.PRIMARY_CONSTRAINT_TYPE
Activity General - (Activity) Primary Resource Dimension The primary resource for the activity. The primary resource is responsible for the overall work on the activity and updates the activity status using Progress Reporter. Value Derived From : Dim_W_ACTIVITY_HD_Activity.PRIMARY_RESOURCE_NAME
Activity General - (Activity) Secondary Constraint Dimension The second type of constraint applied to the activity start or finish date. Value Derived From : Dim_W_ACTIVITY_HD_Activity.SECONDARY_CONSTRAINT_TYPE
Activity General - (Activity) WBS Code Dimension The WBS for the activity. Value Derived From : Dim_W_ACTIVITY_HD_Activity.WBS_CODE
Activity General - (Activity) WBS Name Dimension The Work Breakdown Structure Name. Value Derived From : Dim_W_ACTIVITY_HD_Activity.WBS_NAME
Activity Location - (Activity) Address Line 1 Dimension The first line of the address Value Derived From : Dim_W_ACTIVITY_HD_Activity.ADDRESS_LINE1
Activity Location - (Activity) Address Line 2 Dimension The second line of the address Value Derived From : Dim_W_ACTIVITY_HD_Activity.ADDRESS_LINE2
Activity Location - (Activity) City Name Dimension The city name for this Location Value Derived From : Dim_W_ACTIVITY_HD_Activity.CITY_NAME
Activity Location - (Activity) Country Code Dimension The country code for this Location Value Derived From : Dim_W_ACTIVITY_HD_Activity.COUNTRY_CODE
Activity Location - (Activity) Country Name Dimension The country name for this Location Value Derived From : Dim_W_ACTIVITY_HD_Activity.COUNTRY_NAME
Activity Location - (Activity) Latitude Dimension The latitude for this Location Value Derived From : Dim_W_ACTIVITY_HD_Activity.LATITUDE
Activity Location - (Activity) Location Name Dimension The name of the location Value Derived From : Dim_W_ACTIVITY_HD_Activity.LOCATION_NAME
Activity Location - (Activity) Location Type Dimension Location Type Value Derived From : Dim_W_ACTIVITY_HD_Activity.LOCATION_TYPE
Activity Location - (Activity) Longitude Dimension The longitude for this Location Value Derived From : Dim_W_ACTIVITY_HD_Activity.LONGITUDE
Activity Location - (Activity) Municipality Name Dimension The municipality name for this Location Value Derived From : Dim_W_ACTIVITY_HD_Activity.MUNICIPALITY_NAME
Activity Location - (Activity) Postal Code Dimension The postal code for this Location Value Derived From : Dim_W_ACTIVITY_HD_Activity.POSTAL_CODE
Activity Location - (Activity) State/Province Code Dimension The state abbreviation for this Location Value Derived From : Dim_W_ACTIVITY_HD_Activity.STATE_CODE
Activity Location - (Activity) State/Province Name Dimension The state name for this Location Value Derived From : Dim_W_ACTIVITY_HD_Activity.STATE_NAME
Activity Percent Completes - (Activity) Duration % Of Planned Dimension The percent complete of the activity duration. Computed as (Planned Duration - Remaining Duration)/Original Duration * 100. Always in the range 0 to 100. The Planned Duration is taken from the current plan, not from the baseline. Value Derived From : Dim_W_ACTIVITY_HD_Activity.DURATION_PCT_OF_PLANNED
Activity Percent Completes - (Activity) Duration % Complete Dimension The percent complete of the activity duration. Computed as (Original Duration - Remaining Duration)/Original Duration * 100. Always in the range 0 to 100. The Original Duration is taken from the current plan, not from the baseline. Value Derived From : Dim_W_ACTIVITY_HD_Activity.DURATION_PCT_COMPLETE
Activity Percent Completes - (Activity) Expense Cost % Complete Dimension Percent complete of cost for all expenses associated with an activity. Computed as Actual Expense Cost / At Completion Expense Cost* 100. Always in the range 0 to 100. Value Derived From : Dim_W_ACTIVITY_HD_Activity.EXPENSE_COST_PCT_COMPLETE
Activity Percent Completes - (Activity) Labor Units % Complete Dimension The percent complete of units for all labor resources for the activity. Computed as Actual Labor Units / At Completion Labor Units * 100. Always in the range 0 to 100. Value Derived From : Dim_W_ACTIVITY_HD_Activity.LABOR_UNITS_PCT_COMPLETE
Activity Percent Completes - (Activity) Nonlabor Cost % Complete Dimension The percent complete of cost for all nonlabor resources assigned to the activity. Computed as Actual Nonlabor Cost / At Completion Nonlabor Cost * 100. Always in the range 0 to 100. Value Derived From : Dim_W_ACTIVITY_HD_Activity.NONLABOR_COST_PCT_COMPLETE
Activity Percent Completes - (Activity) Nonlabor Units % Complete Dimension The percent complete of units for all nonlabor resources for the activity. Computed as Actual Nonlabor Units / At Completion Nonlabor Units * 100. Always in the range 0 to 100. Value Derived From : Dim_W_ACTIVITY_HD_Activity.NONLABOR_UNITS_PCT_COMPLETE
Activity Percent Completes - (Activity) Percent Complete Dimension The activity percent complete. This value is tied to the activity Duration % Complete, Units % Complete, or Physical % Complete, depending on the setting for the activity's Percent Complete Type, which is one of Duration, Units, or Physical. Always in the range 0 to 100. Value Derived From : Dim_W_ACTIVITY_HD_Activity.PERCENT_COMPLETE
Activity Percent Completes - (Activity) Performance % Complete Dimension The activity performance percent complete. The performance percent complete is used to compute earned value and may be based on the Activity % Complete, on the 0/100 rule, on the 50/50 rule, etc., depending on the technique for computing earned-value percent complete for the activity's WBS. The Performance % Complete specifies what percentage of the activity's planned worth has been earned so far. Value Derived From : Dim_W_ACTIVITY_HD_Activity.PERFORMANCE_PCT_COMPLETE
Activity Percent Completes - (Activity) Physical % Complete Dimension The physical percent complete can either be user entered or calculated from the activity's weighted steps. There is a project setting specifying this. Value Derived From : Dim_W_ACTIVITY_HD_Activity.PHYSICAL_PCT_COMPLETE
Activity Percent Completes - (Activity) Schedule % Complete Dimension The activity schedule percent complete. The Schedule % Complete specifies how much of the activity's baseline duration has been completed so far. Computed based on where the current data date falls between the activity's baseline start and finish dates. If the data date is earlier than the baseline Start, the Schedule % Complete is 0. If the data date is later than the baseline Finish, the Schedule % Complete is 100. The Schedule % Complete indicates how much of the activity duration should be currently completed, relative to the selected baseline. Value Derived From : Dim_W_ACTIVITY_HD_Activity.SCHEDULE_PCT_COMPLETE
Activity Percent Completes - (Activity) Units % Complete Dimension The percent complete of units for all labor and nonlabor resources assigned to the activity. Computed as Actual Units / At Completion Units * 100. Always in the range 0 to 100. Value Derived From : Dim_W_ACTIVITY_HD_Activity.UNITS_PCT_COMPLETE
           
WBS Folder          
WBS   Current Flag Dimension Indicates if a record is current (1,0) Value Derived From : Dim_W_WBS_HD_Wbs.CURRENT_FLAG
WBS   Effective End Date Dimension The end date this version of the record is effective Value Derived From : Dim_W_WBS_HD_Wbs.EFFECTIVE_END_DATE
WBS   Effective Start Date Dimension The start date this version of the record is effective Value Derived From : Dim_W_WBS_HD_Wbs.EFFECTIVE_START_DATE
WBS   Unique Project ID Dimension The Unique ID of the project Value Derived From : Dim_W_WBS_HD_Wbs.PROJECT_OBJECT_ID
WBS   WBS Name Dimension The Work Breakdown Structure Name. Value Derived From : Dim_W_WBS_HD_Wbs.WBS_NAME
WBS   WBS Unique Id Dimension The Unique ID of the WBS Value Derived From : Dim_W_WBS_HD_Wbs.WBS_OBJECT_ID
WBS WBS Hierarchy - (WBS) Full Path Name Dimension Full path for wbs hierarchy Value Derived From : Dim_W_WBS_HIERARCHY_D_WbsHier_ID.FULL_PATH_NAME
WBS WBS Hierarchy - (WBS) WBS Code (Project Level) Dimension A short code assigned to each WBS element for identification. Each WBS element is uniquely identified by concatenating its own code together with its parents codes Value Derived From : Dim_W_WBS_HIERARCHY_D_WbsHier_ID.PROJ_LEVEL_SHORT_NAME
WBS WBS Hierarchy - (WBS) WBS Name (Project Level) Dimension The name of the WBS element Value Derived From : Dim_W_WBS_HIERARCHY_D_WbsHier_ID.PROJ_LEVEL_NAME
WBS WBS Hierarchy - (WBS) WBS ID Level 1 Dimension WBS ID Level 1 Value Derived From : Dim_W_WBS_HIERARCHY_D_WbsHier_ID.WBS_ID_LV1
WBS WBS Hierarchy - (WBS) WBS ID Level 10 Dimension WBS ID Level 10 Value Derived From : Dim_W_WBS_HIERARCHY_D_WbsHier_ID.WBS_ID_LV10
WBS WBS Hierarchy - (WBS) WBS ID Level 11 Dimension WBS ID Level 11 Value Derived From : Dim_W_WBS_HIERARCHY_D_WbsHier_ID.WBS_ID_LV11
WBS WBS Hierarchy - (WBS) WBS ID Level 12 Dimension WBS ID Level 12 Value Derived From : Dim_W_WBS_HIERARCHY_D_WbsHier_ID.WBS_ID_LV12
WBS WBS Hierarchy - (WBS) WBS ID Level 13 Dimension WBS ID Level 13 Value Derived From : Dim_W_WBS_HIERARCHY_D_WbsHier_ID.WBS_ID_LV13
WBS WBS Hierarchy - (WBS) WBS ID Level 14 Dimension WBS ID Level 14 Value Derived From : Dim_W_WBS_HIERARCHY_D_WbsHier_ID.WBS_ID_LV14
WBS WBS Hierarchy - (WBS) WBS ID Level 15 Dimension WBS ID Level 15 Value Derived From : Dim_W_WBS_HIERARCHY_D_WbsHier_ID.WBS_ID_LV15
WBS WBS Hierarchy - (WBS) WBS ID Level 16 Dimension WBS ID Level 16 Value Derived From : Dim_W_WBS_HIERARCHY_D_WbsHier_ID.WBS_ID_LV16
WBS WBS Hierarchy - (WBS) WBS ID Level 17 Dimension WBS ID Level 17 Value Derived From : Dim_W_WBS_HIERARCHY_D_WbsHier_ID.WBS_ID_LV17
WBS WBS Hierarchy - (WBS) WBS ID Level 2 Dimension WBS ID Level 2 Value Derived From : Dim_W_WBS_HIERARCHY_D_WbsHier_ID.WBS_ID_LV2
WBS WBS Hierarchy - (WBS) WBS ID Level 3 Dimension WBS ID Level 3 Value Derived From : Dim_W_WBS_HIERARCHY_D_WbsHier_ID.WBS_ID_LV3
WBS WBS Hierarchy - (WBS) WBS ID Level 4 Dimension WBS ID Level 4 Value Derived From : Dim_W_WBS_HIERARCHY_D_WbsHier_ID.WBS_ID_LV4
WBS WBS Hierarchy - (WBS) WBS ID Level 5 Dimension WBS ID Level 5 Value Derived From : Dim_W_WBS_HIERARCHY_D_WbsHier_ID.WBS_ID_LV5
WBS WBS Hierarchy - (WBS) WBS ID Level 6 Dimension WBS ID Level 6 Value Derived From : Dim_W_WBS_HIERARCHY_D_WbsHier_ID.WBS_ID_LV6
WBS WBS Hierarchy - (WBS) WBS ID Level 7 Dimension WBS ID Level 7 Value Derived From : Dim_W_WBS_HIERARCHY_D_WbsHier_ID.WBS_ID_LV7
WBS WBS Hierarchy - (WBS) WBS ID Level 8 Dimension WBS ID Level 8 Value Derived From : Dim_W_WBS_HIERARCHY_D_WbsHier_ID.WBS_ID_LV8
WBS WBS Hierarchy - (WBS) WBS ID Level 9 Dimension WBS ID Level 9 Value Derived From : Dim_W_WBS_HIERARCHY_D_WbsHier_ID.WBS_ID_LV9
WBS WBS Hierarchy - (WBS) WBS Name Level 1 Dimension WBS Name Level 1 Value Derived From : Dim_W_WBS_HIERARCHY_D_WbsHier_ID.WBS_NAME_LV1
WBS WBS Hierarchy - (WBS) WBS Name Level 10 Dimension WBS Name Level 10 Value Derived From : Dim_W_WBS_HIERARCHY_D_WbsHier_ID.WBS_NAME_LV10
WBS WBS Hierarchy - (WBS) WBS Name Level 11 Dimension WBS Name Level 11 Value Derived From : Dim_W_WBS_HIERARCHY_D_WbsHier_ID.WBS_NAME_LV11
WBS WBS Hierarchy - (WBS) WBS Name Level 12 Dimension WBS Name Level 12 Value Derived From : Dim_W_WBS_HIERARCHY_D_WbsHier_ID.WBS_NAME_LV12
WBS WBS Hierarchy - (WBS) WBS Name Level 13 Dimension WBS Name Level 13 Value Derived From : Dim_W_WBS_HIERARCHY_D_WbsHier_ID.WBS_NAME_LV13
WBS WBS Hierarchy - (WBS) WBS Name Level 14 Dimension WBS Name Level 14 Value Derived From : Dim_W_WBS_HIERARCHY_D_WbsHier_ID.WBS_NAME_LV14
WBS WBS Hierarchy - (WBS) WBS Name Level 15 Dimension WBS Name Level 15 Value Derived From : Dim_W_WBS_HIERARCHY_D_WbsHier_ID.WBS_NAME_LV15
WBS WBS Hierarchy - (WBS) WBS Name Level 16 Dimension WBS Name Level 16 Value Derived From : Dim_W_WBS_HIERARCHY_D_WbsHier_ID.WBS_NAME_LV16
WBS WBS Hierarchy - (WBS) WBS Name Level 17 Dimension WBS Name Level 17 Value Derived From : Dim_W_WBS_HIERARCHY_D_WbsHier_ID.WBS_NAME_LV17
WBS WBS Hierarchy - (WBS) WBS Name Level 2 Dimension WBS Name Level 2 Value Derived From : Dim_W_WBS_HIERARCHY_D_WbsHier_ID.WBS_NAME_LV2
WBS WBS Hierarchy - (WBS) WBS Name Level 3 Dimension WBS Name Level 3 Value Derived From : Dim_W_WBS_HIERARCHY_D_WbsHier_ID.WBS_NAME_LV3
WBS WBS Hierarchy - (WBS) WBS Name Level 4 Dimension WBS Name Level 4 Value Derived From : Dim_W_WBS_HIERARCHY_D_WbsHier_ID.WBS_NAME_LV4
WBS WBS Hierarchy - (WBS) WBS Name Level 5 Dimension WBS Name Level 5 Value Derived From : Dim_W_WBS_HIERARCHY_D_WbsHier_ID.WBS_NAME_LV5
WBS WBS Hierarchy - (WBS) WBS Name Level 6 Dimension WBS Name Level 6 Value Derived From : Dim_W_WBS_HIERARCHY_D_WbsHier_ID.WBS_NAME_LV6
WBS WBS Hierarchy - (WBS) WBS Name Level 7 Dimension WBS Name Level 7 Value Derived From : Dim_W_WBS_HIERARCHY_D_WbsHier_ID.WBS_NAME_LV7
WBS WBS Hierarchy - (WBS) WBS Name Level 8 Dimension WBS Name Level 8 Value Derived From : Dim_W_WBS_HIERARCHY_D_WbsHier_ID.WBS_NAME_LV8
WBS WBS Hierarchy - (WBS) WBS Name Level 9 Dimension WBS Name Level9 Value Derived From : Dim_W_WBS_HIERARCHY_D_WbsHier_ID.WBS_NAME_LV9