P6 - Burn Down / Primavera - Burn Down

Description: Use this subject area to analyze daily project performance through burn down charts and schedule adherence metrics. Metrics include planned, actual, remaining, and emergent counts and units. Emergent data is from activities which were added after burn down began. This subject area requires project specific UDF configuration in P6.

Folder Subfolder Field Name Dimension/ Fact / Lookup Description Values Derived From / Calculated By
Project Budget - (Project)     Project Budget  
Project Budget - (Project) Current Budget Dimension The Current Budget is the sum of the Original Budget and all approved budget changes in the Budget Change Log. Value Derived From : Dim_W_PROJECT_HD_ID.CURRENT_BUDGET
Project Budget - (Project) Current Variance Dimension Computed as the Current Budget minus the Total Spending Plan. Not rolled up. Value Derived From : Dim_W_PROJECT_HD_ID.CURRENT_VARIANCE
Project Budget - (Project) Distributed Current Budget Dimension Computed as sum of the Current Budget values from one level lower. Not rolled up. Value Derived From : Dim_W_PROJECT_HD_ID.DISTRIBUTED_CURRENT_BUDGET
Project Budget - (Project) Original Budget Dimension Original budget for the project. Value Derived From : Dim_W_PROJECT_HD_ID.ORIGINAL_BUDGET
Project Budget - (Project) Proposed Budget Dimension The Proposed Budget is the sum of the Original Budget plus the Approved and Pending budgets from the budget change log. Not rolled up. Value Derived From : Dim_W_PROJECT_HD_ID.PROPOSED_BUDGET
Project Budget - (Project) Total Benefit Plan Dimension Sum of the Monthly Benefit Plan. Not rolled up. Value Derived From : Dim_W_PROJECT_HD_ID.TOTAL_BENEFIT_PLAN
Project Budget - (Project) Total Benefit Plan Tally Dimension Sum of the Monthly Benefit Plan Tally. Not rolled up. Value Derived From : Dim_W_PROJECT_HD_ID.TOTAL_BENEFIT_PLAN_TALLY
Project Budget - (Project) Total Funding Dimension The total amount of funding contributed to the project by your funding sources. Value Derived From : Dim_W_PROJECT_HD_ID.TOTAL_FUNDING
Project Budget - (Project) Total Spending Plan Dimension Sum of the Monthly Spending Plan. Not rolled up. Value Derived From : Dim_W_PROJECT_HD_ID.TOTAL_SPENDING_PLAN
Project Budget - (Project) Total Spending Plan Tally Dimension Sum of the Monthly Spending Plan Tally. Not rolled up. Value Derived From : Dim_W_PROJECT_HD_ID.TOTAL_SPENDING_PLAN_TALLY
Project Budget - (Project) Unallocated Budget Dimension Calculated as Total Current Budget - Distributed Current Budget. Value Derived From : Dim_W_PROJECT_HD_ID.UNALLOCATED_BUDGET
Project Budget - (Project) Undistributed Current Variance Dimension Computed as the Total Spending Plan minus the Total Spending Plan Tally. Not rolled up. Value Derived From : Dim_W_PROJECT_HD_ID.UNDISTRIBUTED_CURRENT_VARIANCE
Project Dates - (Project)     Project Dates  
Project Dates - (Project) Anticipated Finish Dimension Anticipated finish date of WBS, Project and EPS elements. User-entered - not dependent upon any other fields. If there are no children, the anticipated finish date will be the Finish date displayed in the columns. Value Derived From : Dim_W_PROJECT_D_Project.ANTICIPATED_FINISH_DATE
Project Dates - (Project) Anticipated Start Dimension Anticipated start date of WBS, Project and EPS elements. User-entered - not dependent upon any other fields. If there are no children, the anticipated start date will be the Start date displayed in the columns. Value Derived From : Dim_W_PROJECT_D_Project.ANTICIPATED_START_DATE
Project Dates - (Project) Data Date Dimension The current data date for the project. The project status is up to date as of the data date. The data date is modified when project actuals are applied. Value Derived From : Dim_W_PROJECT_D_Project.DATA_DATE
Project Dates - (Project) Date Added Dimension The date this activity was inserted. Value Derived From : Dim_W_PROJECT_D_Project.ADD_DATE
Project Dates - (Project) Finish Dimension The current finish date of the activity. Set to the activity remaining early finish date while the activity is not started or in progress, and the actual finish date once the activity is completed. Value Derived From : Dim_W_PROJECT_D_Project.PROJECT_FINISH_DATE
Project Dates - (Project) Forecast Finish Date Dimension An alternate end date to be optionally used by the scheduler (see Schedule dialog), which is set by the user by dragging the project bar in the Gantt Chart around while manually leveling the resource profile (in a resource analysis layout, tracking or PA). In User Preferences dialog, the user can choose to view remaining units for a resource based on the forecast dates or the remaining dates. Value Derived From : Dim_W_PROJECT_D_Project.FORECAST_FINISH_DATE
Project Dates - (Project) Forecast Start Date Dimension An alternate start date to be optionally used by the scheduler (see Schedule dialog), which is set by the user by dragging the project bar in the Gantt Chart around while manually leveling the resource profile (in a resource analysis layout, tracking or PA). In the User Preferences dialog, the user can choose to view remaining units for a resource based on the forecast dates or the remaining dates. Value Derived From : Dim_W_PROJECT_D_Project.FORECAST_START_DATE
Project Dates - (Project) Must Finish By Dimension The date by which all project activities must finish. If entered, it is used as the project late finish date by the project scheduler. Value Derived From : Dim_W_PROJECT_D_Project.PROJECT_PLANNED_FINISH_DATE
Project Dates - (Project) Planned Start Dimension The date the activity is scheduled to begin. This date is computed by the project scheduler but can be updated manually by the project manager. This date is not changed by the project scheduler after the activity has been started. Value Derived From : Dim_W_PROJECT_D_Project.PLANNED_START_DATE
Project Dates - (Project) Scheduled Finish Dimension The early finish date of the latest activity in the project, as computed by the project scheduler. Value Derived From : Dim_W_PROJECT_D_Project.SCHEDULED_FINISH_DATE
Project Dates - (Project) Start Dimension The current start date of the activity. Set to the activity remaining early start date while the activity is not started, and the actual start date once the activity is started. Value Derived From : Dim_W_PROJECT_D_Project.PROJECT_START_DATE
Project Dates - (Project) Workdown Date Dimension The date as specified in the Project level UDF sys_workdown_date Value Derived From : Dim_W_PROJECT_HD_ID.WORKDOWN_DATE
Project Durations - (Project)     Project Durations  
Project Durations - (Project) Actual Duration Dimension Actual duration is the total time from the project actual start date to the actual finish date (for completed projects), or to the current data date (for in-progress projects). Value Derived From : Dim_W_PROJECT_D_Project.ACTUAL_DURATION
Project Durations - (Project) At Completion Duration Dimension The duration at completion is the total time from the project current start date to the current finish date. Value Derived From : Dim_W_PROJECT_D_Project.AT_COMPLETION_DURATION
Project Durations - (Project) Baseline Project Duration Dimension The duration of the baseline project. Value Derived From : Dim_W_PROJECT_D_Project.BASELINE_DURATION
Project Durations - (Project) Planned Duration Dimension Planned duration is the total time from the project planned start date to the planned finish date. Value Derived From : Dim_W_PROJECT_D_Project.PLANNED_DURATION
Project Durations - (Project) Remaining Duration Dimension Remaining duration is the total time from the current data date date to the current finish date. Value Derived From : Dim_W_PROJECT_D_Project.REMAINING_DURATION
Project Durations - (Project) Variance - Baseline Project Duration Dimension The duration between the baseline project duration and the current project duration. Calculated as Planned Duration minus At Completion Duration. Value Derived From : Dim_W_PROJECT_D_Project.DURATION_VARIANCE
Project General - (Project)     General Project Information  
Project General - (Project) Added By Dimension The name of the user who added the project Value Derived From : Dim_W_PROJECT_HD_ID.ADDED_BY_NAME
Project General - (Project) Datasource Id Dimension A unique source Id created for the Primavera data source being used. Used to identify data sources when using multiple Primavera data sources. Value Derived From : Dim_W_PROJECT_HD_ID.DATASOURCE_ID
Project General - (Project) Project Leveling Priority Dimension Priority for leveling Value Derived From : Dim_W_PROJECT_HD_ID.PROJECT_PRIORITY
Project General - (Project) Project Score Dimension The Project score Value Derived From : Dim_W_PROJECT_HD_ID.OVERALL_PROJECT_SCORE
Project General - (Project) Project Description Dimension The project description Value Derived From : Dim_W_PROJECT_HD_ID.PROJECT_DESCRIPTION
Project General - (Project) Project Id Dimension The Project Id of the project Value Derived From : Dim_W_PROJECT_HD_ID.PROJECT_ID
Project General - (Project) Project Name Dimension The project name Value Derived From : Dim_W_PROJECT_HD_ID.PROJECT_NAME
Project General - (Project) Unique Project ID Dimension The Unique ID of the project Value Derived From : Dim_W_PROJECT_HD_ID.PROJECT_ID
Project General - (Project) Strategic Priority Dimension Resource designated as owner of the project Value Derived From : Dim_W_PROJECT_HD_ID.PROJECT_STRATEGIC_PRIORITY
Project General - (Project) Project Risk Exposure Dimension The calculated exposure value for the risk Value Derived From : Dim_W_PROJECT_HD_ID.PROJECT_RISK_EXPOSURE
Project General - (Project) Project Risk Level Dimension Project risk level (1 - Very Low, 2 - Low, 3 - Medium, 4 - High, 5 - Very High) Value Derived From : Dim_W_PROJECT_HD_ID.PROJECT_RISK_LEVEL
Project General - (Project) Project Risk Score Dimension The calculated score value of the impact values assigned to the risk Value Derived From : Dim_W_PROJECT_HD_ID.PROJECT_RISK_SCORE
Project General - (Project) WBS Dimension The Unique ID of the project's root level WBS Value Derived From : Dim_W_PROJECT_HD_ID.WBS_OBJECT_ID
Project General - (Project) Project Status Dimension The status of the project as active, inactive, planned or what-if Value Derived From : Dim_W_PROJECT_HD_ID.PROJECT_STATUS
Project General - (Project) Strategic Priority Dimension Range 1 to 10,000 Value Derived From : Dim_W_PROJECT_HD_ID.PROJECT_STRATEGIC_PRIORITY
Project Location - (Project) Location - (Project)   Project Location  
Project Location - (Project) Address Line 1 Dimension The first line of the address Value Derived From : Dim_W_PROJECT_HD_ID.ADDRESS_LINE1
Project Location - (Project) Address Line 2 Dimension The second line of the address Value Derived From : Dim_W_PROJECT_HD_ID.ADDRESS_LINE2
Project Location - (Project) City Name Dimension The city name for this Location Value Derived From : Dim_W_PROJECT_HD_ID.CITY_NAME
Project Location - (Project) Country Code Dimension The country code for this Location Value Derived From : Dim_W_PROJECT_HD_ID.COUNTRY_CODE
Project Location - (Project) Country Name Dimension The country name for this Location Value Derived From : Dim_W_PROJECT_HD_ID.COUNTRY_NAME
Project Location - (Project) Latitude Dimension The latitude for this Location Value Derived From : Dim_W_PROJECT_HD_ID.LATITUDE
Project Location - (Project) Location Name Dimension The name of the location Value Derived From : Dim_W_PROJECT_HD_ID.LOCATION_NAME
Project Location - (Project) Location Type Dimension Location Type Value Derived From : Dim_W_PROJECT_HD_ID.LOCATION_TYPE
Project Location - (Project) Longitude Dimension The longitude for this Location Value Derived From : Dim_W_PROJECT_HD_ID.LONGITUDE
Project Location - (Project) Municipality Name Dimension The municipality name for this Location Value Derived From : Dim_W_PROJECT_HD_ID.MUNICIPALITY_NAME
Project Location - (Project) Postal Code Dimension The postal code for this Location Value Derived From : Dim_W_PROJECT_HD_ID.POSTAL_CODE
Project Location - (Project) State/Province Code Dimension The state abbreviation for this Location Value Derived From : Dim_W_PROJECT_HD_ID.STATE_CODE
Project Location - (Project) State/Province Name Dimension The state name for this Location Value Derived From : Dim_W_PROJECT_HD_ID.STATE_NAME
Project P6 Links     Go to P6 Links  
Project P6 Links Link to Activities Dimension Go to Project Activities '<a target="_blank" href="' || VALUEOF(NQ_SESSION."DW_P6_LINK_BASE_URL") || VALUEOF("DW_P6_LINK_PROJECT_LIST_BASE_URL") || CAST (P6Core."Dim - Project HD ID"."Project WBS Object Id" AS VARCHAR ( 10 )) || '%26key%3Dactivities">' || 'Project Activities' || '</a>'
Project P6 Links Link to Documents Dimension Go to Project Documents '<a target="_blank" href="' || VALUEOF(NQ_SESSION."DW_P6_LINK_BASE_URL") || VALUEOF("DW_P6_LINK_PROJECT_LIST_BASE_URL") || CAST (P6Core."Dim - Project HD ID"."Project WBS Object Id" AS VARCHAR ( 10 )) || '%26key%3Ddocuments">' || 'Project Documents' || '</a>'
Project P6 Links Link to Issues Dimension Go to Project Issues '<a target="_blank" href="' || VALUEOF(NQ_SESSION."DW_P6_LINK_BASE_URL") || '/action/pm/lwfissuemanagement?projectId=' || CAST (P6Core."Dim - Project HD ID"."Project Object Id" AS VARCHAR ( 10 )) || '&wbsId=' || CAST (P6Core."Dim - Project HD ID"."Project WBS Object Id" AS VARCHAR ( 10 )) || '&checkTabs=true">' || 'Project Issues' || '</a>'
Project P6 Links Link to Risks Dimension Go to Project Risks '<a target="_blank" href="' || VALUEOF(NQ_SESSION."DW_P6_LINK_BASE_URL") || VALUEOF("DW_P6_LINK_PROJECT_LIST_BASE_URL") || CAST (P6Core."Dim - Project HD ID"."Project WBS Object Id" AS VARCHAR ( 10 )) || '%26key%3Drisks">' || 'Project Risks' || '</a>'
Project P6 Links Link to Team Usage Dimension Go to Project Team Usage '<a target="_blank" href="' || VALUEOF(NQ_SESSION."DW_P6_LINK_BASE_URL") || VALUEOF("DW_P6_LINK_PROJECT_LIST_BASE_URL") || CAST (P6Core."Dim - Project HD ID"."Project WBS Object Id" AS VARCHAR ( 10 )) || '%26key%3Dteamusage">' || 'Project Team Usage' || '</a>'
Project Notebooks - (Project)     Project level notebook topics.  
Project Notebooks - (Project) Create Date Dimension The date the notebook topic was created Value Derived From : Dim_W_PROJECT_NOTE_D_ID.W_CREATE_DT
Project Notebooks - (Project) Create User Dimension The user that created the notebook topic Value Derived From : Dim_W_PROJECT_NOTE_D_ID.W_CREATE_USER
Project Notebooks - (Project) Notebook Text Lookup The text of the notebook topic Lookup(DENSE "P6Core"."Lookup - Project Note D ID"."Raw Text", "P6Core"."Dim - Project Note D ID"."Note Key", "P6Core"."Dim - Project Note D ID"."Project Key")
Project Notebooks - (Project) Notebook Topic Name Dimension The name of the notebook topic Value Derived From : Dim_W_PROJECT_NOTE_D_ID.NOTEBOOK_TOPIC_NAME
Project Notebooks - (Project) Update Date Dimension The date the notebook topic was updated Value Derived From : Dim_W_PROJECT_NOTE_D_ID.W_UPDATE_DT
Project Notebooks - (Project) Update User Dimension The last user to update notebook topic Value Derived From : Dim_W_PROJECT_NOTE_D_ID.W_UPDATE_USER
           
Fact - Primavera - Burn Down Folder          
Fact - Primavera - Burn Down Costs Actual Cost Fact The actual non-overtime plus overtime cost for the resource assignment on the activity. Calculated as Actual Regular Cost plus Actual Overtime Cost. Value Derived From : Fact_W_ACTIVITY_WORK_DOWN_HF_WDAct.ACTUAL_COST
Fact - Primavera - Burn Down Costs Actual Cost Burn Fact The actual cost distributed over the activity duration Value Derived From : Fact_W_ACTIVITY_WORK_DOWN_HF_WDAct.ACTUAL_COST_BURN
Fact - Primavera - Burn Down Costs Baseline Cost Fact Planned Cost from the Burn Down snapshot Value Derived From : Fact_W_ACTIVITY_WORK_DOWN_HF_WDAct.BASELINE_COST
Fact - Primavera - Burn Down Costs Baseline Cost Burn Fact The expected remaining cost distributed over the activity duration based on Burn Down snapshot Value Derived From : Fact_W_ACTIVITY_WORK_DOWN_HF_WDAct.BASELINE_COST_BURN
Fact - Primavera - Burn Down Costs At Completion Cost Fact The sum of the Actual Costs plus Remaining Costs Value Derived From : Fact_W_ACTIVITY_WORK_DOWN_HF_WDAct.COMPLETE_COST
Fact - Primavera - Burn Down Costs Remaining Cost Fact The remaining cost for the resource assignment on the activity. Calculated as Remaining Units multiplied by Cost/Time. Value Derived From : Fact_W_ACTIVITY_WORK_DOWN_HF_WDAct.REMAINING_COST
Fact - Primavera - Burn Down Costs Remaining Cost Burn Fact The remaining cost distributed over the activity duration Value Derived From : Fact_W_ACTIVITY_WORK_DOWN_HF_WDAct.REMAINING_COST_BURN
           
Activity Folder          
Activity Dates - (Activity)     Activity Dates  
Activity Dates - (Activity) Actual Finish Dimension The date on which the activity actually finished Value Derived From : Dim_W_ACTIVITY_D_Activity.ACTUAL_FINISH_DATE
Activity Dates - (Activity) Actual Start Dimension The date on which the activity actually started Value Derived From : Dim_W_ACTIVITY_D_Activity.ACTUAL_START_DATE
Activity Dates - (Activity) Baseline Project Finish Dimension The Project Baseline Planned Finish Date. Value Derived From : Dim_W_ACTIVITY_D_Activity.BASELINE_FINISH_DATE
Activity Dates - (Activity) Baseline Project Start Dimension The Project Baseline Planned Start Date. Value Derived From : Dim_W_ACTIVITY_D_Activity.BASELINE_START_DATE
Activity Dates - (Activity) Data Date Dimension The current data date for the project. The project status is up to date as of the data date. The data date is modified when project actuals are applied. Value Derived From : Dim_W_ACTIVITY_D_Activity.DATA_DATE
Activity Dates - (Activity) Early Finish Dimension The earliest possible date the activity can finish. This date is calculated by the project scheduler based on activity relationships, schedule constraints, and resource availability. Value Derived From : Dim_W_ACTIVITY_D_Activity.EARLY_FINISH_DATE
Activity Dates - (Activity) Early Start Dimension The earliest possible date the remaining work for the activity can begin. This date is calculated by the project scheduler based on activity relationships, schedule constraints, and resource availability. Value Derived From : Dim_W_ACTIVITY_D_Activity.EARLY_START_DATE
Activity Dates - (Activity) Expected Finish Dimension The date the activity is expected to finish. Typically, this date is entered in the Timesheets module by the primary resource. Value Derived From : Dim_W_ACTIVITY_D_Activity.EXPECT_FINISH_DATE
Activity Dates - (Activity) External Early Start Dimension The External Early Start date is the earliest finish date of all lost external relationships. This field is populated only during import when a relationship is lost because it does not exist in the current database. This date may be used to calculate the start date of the current activity in place of the true relationship when scheduling. Value Derived From : Dim_W_ACTIVITY_D_Activity.EXTERNAL_EARLY_START_DATE
Activity Dates - (Activity) External Late Finish Dimension The External Late Finish date is the latest start date of all lost external relationships. This field is populated only during import when a relationship is lost because it does not exist in the current database. This date may be used to calculate the finish date of the current activity in place of the true relationship when scheduling. Value Derived From : Dim_W_ACTIVITY_D_Activity.EXTERNAL_LATE_FINISH_DATE
Activity Dates - (Activity) Finish Dimension The current finish date of the activity. Set to the activity remaining early finish date while the activity is not started or in progress, and the actual finish date once the activity is completed. Value Derived From : Dim_W_ACTIVITY_D_Activity.FINISH_DATE
Activity Dates - (Activity) Late Finish Dimension The latest possible date the activity must finish without delaying the project finish date. This date is calculated by the project scheduler based on activity relationships, schedule constraints, and resource availability. Value Derived From : Dim_W_ACTIVITY_D_Activity.LATE_FINISH_DATE
Activity Dates - (Activity) Late Start Dimension The latest possible date the remaining work for the activity must begin without delaying the project finish date. This date is calculated by the project scheduler based on activity relationships, schedule constraints, and resource availability. Value Derived From : Dim_W_ACTIVITY_D_Activity.LATE_START_DATE
Activity Dates - (Activity) Planned Finish Dimension The date the activity is scheduled to finish. This date is computed by the project scheduler but can be updated manually by the project manager. This date is not changed by the project scheduler after the activity has been started. Value Derived From : Dim_W_ACTIVITY_D_Activity.PLANNED_FINISH_DATE
Activity Dates - (Activity) Planned Start Dimension The date the activity is scheduled to begin. This date is computed by the project scheduler but can be updated manually by the project manager. This date is not changed by the project scheduler after the activity has been started. Value Derived From : Dim_W_ACTIVITY_D_Activity.PLANNED_START_DATE
Activity Dates - (Activity) Primary Constraint Date Dimension The constraint date for the activity, if the activity has a constraint. The activity's constraint type determines whether this is a start date or finish date. Activity constraints are used by the project scheduler. Value Derived From : Dim_W_ACTIVITY_D_Activity.PRIMARY_CONSTRAINT_DATE
Activity Dates - (Activity) Remaining Early Finish Dimension The date the remaining work for the activity is scheduled to finish. This date is computed by the project scheduler but can be updated manually by the project manager. Before the activity is started, the remaining finish date is the same as the planned finish date. This is the finish date that Progress Reporter users follow. Value Derived From : Dim_W_ACTIVITY_D_Activity.REMAINING_FINISH_DATE
Activity Dates - (Activity) Remaining Early Start Dimension The date the remaining work for the activity is scheduled to begin. This date is computed by the project scheduler but can be updated manually by the project manager. Before the activity is started, the remaining start date is the same as the planned start date. This is the start date that Progress Reporter users follow. Value Derived From : Dim_W_ACTIVITY_D_Activity.REMAINING_START_DATE
Activity Dates - (Activity) Remaining Late Finish Dimension Remaining late end date is calculated by the scheduler. Value Derived From : Dim_W_ACTIVITY_D_Activity.REMAINING_LATE_FINISH_DATE
Activity Dates - (Activity) Remaining Late Start Dimension Remaining late start date is calculated by the scheduler. Value Derived From : Dim_W_ACTIVITY_D_Activity.REMAINING_LATE_START_DATE
Activity Dates - (Activity) Resume Date Dimension The date progress is resumed on an activity. Value Derived From : Dim_W_ACTIVITY_D_Activity.RESUME_DATE
Activity Dates - (Activity) Secondary Constraint Date Dimension The second constraint date for the activity, if the activity has a constraint. Value Derived From : Dim_W_ACTIVITY_D_Activity.SECONDARY_CONSTRAINT_DATE
Activity Dates - (Activity) Start Dimension The current start date of the activity. Set to the activity remaining early start date while the activity is not started, and the actual start date once the activity is started. Value Derived From : Dim_W_ACTIVITY_D_Activity.START_DATE
Activity Dates - (Activity) Suspend Date Dimension The date progress is suspended on an activity. Value Derived From : Dim_W_ACTIVITY_D_Activity.SUSPEND_DATE
Activity Durations - (Activity)     Activity Durations  
Activity Durations - (Activity) Actual Duration Dimension Actual duration is the total working time from the activity actual start date to the actual finish date (for completed activities), or to the current data date (for in-progress activities). The actual working time is computed using the activity's calendar. Value Derived From : Dim_W_ACTIVITY_D_Activity.ACTUAL_DURATION
Activity Durations - (Activity) At Completion Duration Dimension The duration at completion is the total working time from the activity's current start date to the current finish date. The current start date is the planned start date until the activity is started, then it is the actual start date. The current finish date is the activity planned finish date while the activity is not started, the remaining finish date while the activity is in progress, and the actual finish date once the activity is completed. The total working time is computed using the activity's calendar. Value Derived From : Dim_W_ACTIVITY_D_Activity.AT_COMPLETION_DURATION
Activity Durations - (Activity) Baseline Project Duration Dimension The duration for the activity in the primary baseline. Value Derived From : Dim_W_ACTIVITY_D_Activity.BASELINE_DURATION
Activity Durations - (Activity) Baseline Planned Duration Dimension Baseline Planned Duration is the total working time from the baseline activity planned start date to the baseline planned finish date. The baseline planned working time is computed using the activity's calendar. Value Derived From : Dim_W_ACTIVITY_D_Activity.BASELINE_PLANNED_DURATION
Activity Durations - (Activity) Free Float Dimension The amount of time the activity can be delayed before delaying the start date of any successor activity. Value Derived From : Dim_W_ACTIVITY_D_Activity.FREE_FLOAT
Activity Durations - (Activity) Original Duration Dimension Original Duration is the total working time from the activity planned start date to the planned finish date. The planned working time is computed using the activity's calendar. Value Derived From : Dim_W_ACTIVITY_D_Activity.PLANNED_DURATION
Activity Durations - (Activity) Remaining Duration Dimension Remaining duration is the total working time from the activity remaining start date to the remaining finish date. The remaining working time is computed using the activity's calendar. Before the activity is started, the remaining duration is the same as the Original Duration. After the activity is completed the remaining duration is zero. Value Derived From : Dim_W_ACTIVITY_D_Activity.REMAINING_DURATION
Activity Durations - (Activity) Remaining Float Dimension The amount of time remaining by which the activity can be delayed before delaying the project finish date. Computed as Late Finish - Remaining Finish. If the remaining finish is the same as the early finish ( in general, when the activity is not started), then the remaining float is the same as the total float. Value Derived From : Dim_W_ACTIVITY_D_Activity.REMAINING_FLOAT
Activity Durations - (Activity) Total Float Dimension The amount of time the activity can be delayed before delaying the project finish date. Total float can be computed as Late Start - Early Start or as Late Finish - Early Finish; this option can be set when running the project scheduler. Value Derived From : Dim_W_ACTIVITY_D_Activity.TOTAL_FLOAT
Activity Durations - (Activity) Variance - Baseline Project Duration Dimension Variance duration is the duration between the activity' Baseline project duration and the At Completion duration. Value Derived From : Dim_W_ACTIVITY_D_Activity.DURATION_VARIANCE
Activity Durations - (Activity) Variance - Baseline Project Finish Date Dimension Variance Finish Date is the duration between the Baseline project finish date and the finish date in the current project. Value Derived From : Dim_W_ACTIVITY_D_Activity.FINISH_DATE_VARIANCE
Activity Durations - (Activity) Variance - Baseline Project Start Date Dimension Variance Start Date is the duration between the Baseline project start date and the start date in the current project. Value Derived From : Dim_W_ACTIVITY_D_Activity.START_DATE_VARIANCE
Activity General - (Activity)     General Activity Information  
Activity General - (Activity) Activity ID Dimension A short ID which uniquely identifies the activity within the project. Value Derived From : Dim_W_ACTIVITY_HD_ID.ACTIVITY_ID
Activity General - (Activity) Activity Name Dimension The name of the activity. The activity name does not have to be unique. Value Derived From : Dim_W_ACTIVITY_HD_ID.ACTIVITY_NAME
Activity General - (Activity) Owner Dimension User who owns the activity. Value Derived From : Dim_W_ACTIVITY_HD_ID.ACTIVITY_OWNER
Activity General - (Activity) Activity Status Dimension The current status of the activity, either Not Started, In Progress, or Completed. Value Derived From : Dim_W_ACTIVITY_HD_ID.ACTIVITY_STATUS
Activity General - (Activity) Activity Type Dimension The type of activity, either 'Task Dependent', 'Resource Dependent', 'Level of Effort', 'Start Milestone' or 'Finish Milestone'. A Task Dependent activity is scheduled using the activity's calendar rather than the calendars of the assigned resources. A Resource Dependent activity is scheduled using the calendars of the assigned resources. This type is used when several resources are assigned to the activity, but they may work separately. A Start/Finish Milestone is a zero-duration activity, marking a significant start/end of project event. A Level of Effort activity has a duration which is determined by its dependent activities. Administration-type activities are typically level of effort. Value Derived From : Dim_W_ACTIVITY_HD_ID.ACTIVITY_TYPE
Activity General - (Activity) Auto Compute Actuals Dimension Identifies whether the actual and remaining units, start date, finish date, and percent complete for the activity are computed automatically using the planned dates, budgeted units and the activity's schedule percent complete. If this option is selected, the actual/remaining units and actual dates are automatically updated when project actuals are applied. This assumes that all work for the activity proceeds according to plan. Value Derived From : Dim_W_ACTIVITY_HD_ID.AUTO_COMPUTE_ACTUALS_FLAG
Activity General - (Activity) Calendar Name Dimension The calendar assigned to the activity. Activity calendars can be assigned from the global calendar pool or the project calendar pool. Value Derived From : Dim_W_ACTIVITY_HD_ID.CALENDAR_NAME
Activity General - (Activity) Criticality Index Dimension Criticality Index Value Derived From : Dim_W_ACTIVITY_HD_ID.CRITICALITY_INDEX
Activity General - (Activity) Duration Type Dimension The duration type of the activity. One of Fixed Units per Time, Fixed Duration, or Fixed Units. For Fixed Units per Time activities, the resource units per time are constant when the activity duration or units are changed. This type is used when an activity has fixed resources with fixed productivity output per time period. For Fixed Duration activities, the activity duration is constant as the units or resource units per time are changed. This type is used when the activity is to be completed within a fixed time period regardless of the resources assigned. For Fixed Units activities, the activity units are constant when the duration or resource units per time are changed. This type is used when the total amount of work is fixed, and increasing the resources can decrease the activity duration. Value Derived From : Dim_W_ACTIVITY_HD_ID.DURATION_TYPE
Activity General - (Activity) Critical Dimension Indicates whether the activity is critical. An activity is critical when its Total Float is below the critical duration specified for the project. Delaying critical activities will delay the finish date of the project. Value Derived From : Dim_W_ACTIVITY_HD_ID.IS_CRITICAL
Activity General - (Activity) Longest Path Dimension Indicates whether an activity is on the longest path. The longest path is defined as activities that are on the critical path and determine the end date of the project. Defining critical activities based on the longest path in the project provides an alternative to viewing critical activities based on float. Value Derived From : Dim_W_ACTIVITY_HD_ID.IS_LONGEST_PATH
Activity General - (Activity) Activity Leveling Priority Dimension The activity priority can be used to prioritize activities in a project when performing resource leveling. Value Derived From : Dim_W_ACTIVITY_HD_ID.LEVELING_PRIORITY
Activity General - (Activity) Percent Complete Type Dimension The activity percent complete type is one of Duration, Units, or Physical. The percent complete type controls whether the Activity % Complete is tied to the Duration % Complete, the Units % Complete, or the Physical % Complete for the activity. Set the percent complete type to Duration for activities which are duration driven, for example, administration tasks and training classes. Set the percent complete type to Physical for activities which are work-product driven, for example, creating a document or a product. Set the percent complete type to Units for activities which are work effort driven, for example, providing a consulting service. Value Derived From : Dim_W_ACTIVITY_HD_ID.COMPLETE_PCT_TYPE
Activity General - (Activity) Primary Constraint Dimension The type of constraint applied to the activity start or finish date. Activity constraints are used by the project scheduler. Start date constraints are 'Start On', 'Start On or Before', 'Start On or After' and 'Mandatory Start'. Finish date constraints are 'Finish On', 'Finish On or Before', 'Finish On or After' and 'Mandatory Finish'. Another type of constraint, 'As Late as Possible', schedules the activity as late as possible based on the available free float. Value Derived From : Dim_W_ACTIVITY_HD_ID.PRIMARY_CONSTRAINT_TYPE
Activity General - (Activity) Primary Resource Dimension The primary resource for the activity. The primary resource is responsible for the overall work on the activity and updates the activity status using Progress Reporter. Value Derived From : Dim_W_ACTIVITY_HD_ID.PRIMARY_RESOURCE_NAME
Activity General - (Activity) Secondary Constraint Dimension The second type of constraint applied to the activity start or finish date. Value Derived From : Dim_W_ACTIVITY_HD_ID.SECONDARY_CONSTRAINT_TYPE
Activity General - (Activity) WBS Code Dimension The WBS for the activity. Value Derived From : Dim_W_ACTIVITY_HD_ID.WBS_CODE
Activity General - (Activity) WBS Name Dimension The Work Breakdown Structure Name. Value Derived From : Dim_W_ACTIVITY_HD_ID.WBS_NAME
Activity Location - (Activity)     Activity Location  
Activity Location - (Activity) Address Line 1 Dimension The first line of the address Value Derived From : Dim_W_ACTIVITY_HD_ID.ADDRESS_LINE1
Activity Location - (Activity) Address Line 2 Dimension The second line of the address Value Derived From : Dim_W_ACTIVITY_HD_ID.ADDRESS_LINE2
Activity Location - (Activity) City Name Dimension The city name for this Location Value Derived From : Dim_W_ACTIVITY_HD_ID.CITY_NAME
Activity Location - (Activity) Country Code Dimension The country code for this Location Value Derived From : Dim_W_ACTIVITY_HD_ID.COUNTRY_CODE
Activity Location - (Activity) Country Name Dimension The country name for this Location Value Derived From : Dim_W_ACTIVITY_HD_ID.COUNTRY_NAME
Activity Location - (Activity) Latitude Dimension The latitude for this Location Value Derived From : Dim_W_ACTIVITY_HD_ID.LATITUDE
Activity Location - (Activity) Location Name Dimension The name of the location Value Derived From : Dim_W_ACTIVITY_HD_ID.LOCATION_NAME
Activity Location - (Activity) Location Type Dimension Location Type Value Derived From : Dim_W_ACTIVITY_HD_ID.LOCATION_TYPE
Activity Location - (Activity) Longitude Dimension The longitude for this Location Value Derived From : Dim_W_ACTIVITY_HD_ID.LONGITUDE
Activity Location - (Activity) Municipality Name Dimension The municipality name for this Location Value Derived From : Dim_W_ACTIVITY_HD_ID.MUNICIPALITY_NAME
Activity Location - (Activity) Postal Code Dimension The postal code for this Location Value Derived From : Dim_W_ACTIVITY_HD_ID.POSTAL_CODE
Activity Location - (Activity) State/Province Code Dimension The state abbreviation for this Location Value Derived From : Dim_W_ACTIVITY_HD_ID.STATE_CODE
Activity Location - (Activity) State/Province Name Dimension The state name for this Location Value Derived From : Dim_W_ACTIVITY_HD_ID.STATE_NAME
Activity Multiple Float Paths - (Activity)     Activity Multiple Float Paths  
Activity Multiple Float Paths - (Activity) Float Path Dimension The project scheduler determines the most critical and sub-critical paths. The float path field identifies the critical path that each activity is on. The number starts from 1 (where 1 is most critical) to the max number of float paths identified by the scheduler. This field is used when determining multiple float paths using the Free Float and Total Float method. Value Derived From : Dim_W_ACTIVITY_HD_ID.FLOAT_PATH
Activity Multiple Float Paths - (Activity) Float Path Order Dimension This field is computed by the project scheduler and identifies the order in which the activities were processed within the float path. Value Derived From : Dim_W_ACTIVITY_HD_ID.FLOAT_PATH_ORDER
Activity Percent Completes - (Activity)     Activity Percent Completes  
Activity Percent Completes - (Activity) Duration % Of Planned Dimension The percent complete of the activity duration. Computed as (Planned Duration - Remaining Duration)/Original Duration * 100. Always in the range 0 to 100. The Planned Duration is taken from the current plan, not from the baseline. Value Derived From : Dim_W_ACTIVITY_HD_ID.DURATION_PCT_OF_PLANNED
Activity Percent Completes - (Activity) Duration % Complete Dimension The percent complete of the activity duration. Computed as (Original Duration - Remaining Duration)/Original Duration * 100. Always in the range 0 to 100. The Original Duration is taken from the current plan, not from the baseline. Value Derived From : Dim_W_ACTIVITY_HD_ID.DURATION_PCT_COMPLETE
Activity Percent Completes - (Activity) Expense Cost % Complete Dimension Percent complete of cost for all expenses associated with an activity. Computed as Actual Expense Cost / At Completion Expense Cost* 100. Always in the range 0 to 100. Value Derived From : Dim_W_ACTIVITY_HD_ID.EXPENSE_COST_PCT_COMPLETE
Activity Percent Completes - (Activity) Labor Units % Complete Dimension The percent complete of units for all labor resources for the activity. Computed as Actual Labor Units / At Completion Labor Units * 100. Always in the range 0 to 100. Value Derived From : Dim_W_ACTIVITY_HD_ID.LABOR_UNITS_PCT_COMPLETE
Activity Percent Completes - (Activity) Nonlabor Cost % Complete Dimension The percent complete of cost for all nonlabor resources assigned to the activity. Computed as Actual Nonlabor Cost / At Completion Nonlabor Cost * 100. Always in the range 0 to 100. Value Derived From : Dim_W_ACTIVITY_HD_ID.NONLABOR_COST_PCT_COMPLETE
Activity Percent Completes - (Activity) Nonlabor Units % Complete Dimension The percent complete of units for all nonlabor resources for the activity. Computed as Actual Nonlabor Units / At Completion Nonlabor Units * 100. Always in the range 0 to 100. Value Derived From : Dim_W_ACTIVITY_HD_ID.NONLABOR_UNITS_PCT_COMPLETE
Activity Percent Completes - (Activity) Percent Complete Dimension The activity percent complete. This value is tied to the activity Duration % Complete, Units % Complete, or Physical % Complete, depending on the setting for the activity's Percent Complete Type, which is one of Duration, Units, or Physical. Always in the range 0 to 100. Value Derived From : Dim_W_ACTIVITY_HD_ID.PERCENT_COMPLETE
Activity Percent Completes - (Activity) Performance % Complete Dimension The activity performance percent complete. The performance percent complete is used to compute earned value and may be based on the Activity % Complete, on the 0/100 rule, on the 50/50 rule, etc., depending on the technique for computing earned-value percent complete for the activity's WBS. The Performance % Complete specifies what percentage of the activity's planned worth has been earned so far. Value Derived From : Dim_W_ACTIVITY_HD_ID.PERFORMANCE_PCT_COMPLETE
Activity Percent Completes - (Activity) Physical % Complete Dimension The physical percent complete can either be user entered or calculated from the activity's weighted steps. There is a project setting specifying this. Value Derived From : Dim_W_ACTIVITY_HD_ID.PHYSICAL_PCT_COMPLETE
Activity Percent Completes - (Activity) Schedule % Complete Dimension The activity schedule percent complete. The Schedule % Complete specifies how much of the activity's baseline duration has been completed so far. Computed based on where the current data date falls between the activity's baseline start and finish dates. If the data date is earlier than the baseline Start, the Schedule % Complete is 0. If the data date is later than the baseline Finish, the Schedule % Complete is 100. The Schedule % Complete indicates how much of the activity duration should be currently completed, relative to the selected baseline. Value Derived From : Dim_W_ACTIVITY_HD_ID.SCHEDULE_PCT_COMPLETE
Activity Percent Completes - (Activity) Units % Complete Dimension The percent complete of units for all labor and nonlabor resources assigned to the activity. Computed as Actual Units / At Completion Units * 100. Always in the range 0 to 100. Value Derived From : Dim_W_ACTIVITY_HD_ID.UNITS_PCT_COMPLETE
Activity Notebooks - (Activity)     Activity level notebook topics.  
Activity Notebooks - (Activity) Create Date Dimension The date the notebook topic was created Value Derived From : Dim_W_ACTIVITY_NOTE_D_Activity_Note.W_CREATE_DT
Activity Notebooks - (Activity) Create User Dimension The user that created the notebook topic Value Derived From : Dim_W_ACTIVITY_NOTE_D_Activity_Note.W_CREATE_USER
Activity Notebooks - (Activity) Notebook Text   The text of the notebook topic Value Derived From : LOOKUP(DENSE "P6Core"."Lookup - Activity Note"."Raw Text", "P6Core"."Dim - Activity Note"."Note Key", "P6Core"."Dim - Activity Note"."Activity Key")
Activity Notebooks - (Activity) Notebook Topic Name Dimension The name of the notebook topic Value Derived From : Dim_W_ACTIVITY_NOTE_D_Activity_Note.NOTEBOOK_TOPIC_NAME
Activity Notebooks - (Activity) Update Date Dimension The date the notebook topic was updated Value Derived From : Dim_W_ACTIVITY_NOTE_D_Activity_Note.W_UPDATE_DT
Activity Notebooks - (Activity) Update User Dimension The last user to update notebook topic Value Derived From : Dim_W_ACTIVITY_NOTE_D_Activity_Note.W_UPDATE_USER
           
Resource Assignment Folder          
Resource Assignment Dates - (Resource Assignment)        
Resource Assignment Dates - (Resource Assignment) Actual Finish Dimension The date on which the assignment is complete. Value Derived From : Dim_W_ASSIGNMENT_HD_ID.ACTUAL_FINISH_DATE
Resource Assignment Dates - (Resource Assignment) Actual Start Dimension The date on which the assignment actually started. Value Derived From : Dim_W_ASSIGNMENT_HD_ID.ACTUAL_START_DATE
Resource Assignment Dates - (Resource Assignment) Planned Finish Dimension The date the assignment is scheduled to be finished. Value Derived From : Dim_W_ASSIGNMENT_HD_ID.PLANNED_FINISH_DATE
Resource Assignment Dates - (Resource Assignment) Planned Start Dimension The date work on the assignment is scheduled to begin. Value Derived From : Dim_W_ASSIGNMENT_HD_ID.PLANNED_START_DATE
Resource Assignment Dates - (Resource Assignment) Remaining Finish Dimension The date the assignment is scheduled to be finished. This date can be updated manually by the user. Before the activity is started, this date is the same as the Planned Finish date. Value Derived From : Dim_W_ASSIGNMENT_HD_ID.REMAINING_FINISH_DATE
Resource Assignment Dates - (Resource Assignment) Remaining Start Dimension The date the assignment is scheduled to begin. This date can be updated manually by the user. Before the activity is started, this date is the same as the Planned Start date. Value Derived From : Dim_W_ASSIGNMENT_HD_ID.REMAINING_START_DATE
Resource Assignment General - (Resource Assignment) Resource Name Dimension The name of the resource for this assignment Value Derived From : Dim_W_ASSIGNMENT_HD_ID.RESOURCE_NAME
Resource Assignment General - (Resource Assignment) Role Name Dimension The name of the role for this assignment Value Derived From : Dim_W_ASSIGNMENT_HD_ID.ROLE_NAME
           
Resource Folder          
Resource General - (Resource)     General Resource Information  
Resource General - (Resource) Active Dimension Indicates whether the resource is currently active. Nonactive resources may have left the organization but are not deleted from the system since they may have actual hours. Value Derived From : Dim_W_RESOURCE_HD_ID.ACTIVE_FLAG
Resource General - (Resource) Datasource Id Dimension A unique source Id created for the Primavera data source being used. Used to identify data sources when using multiple Primavera data sources. Value Derived From : Dim_W_RESOURCE_HD_ID.DATASOURCE_ID
Resource General - (Resource) Primary Role Name Dimension The name of the role that is assigned as the resource's primary role. Value Derived From : Dim_W_RESOURCE_HD_ID.PRIMARY_ROLE_NAME
Resource General - (Resource) Unique Primary Role Id Dimension The unique Id of the role that is assigned as the resource's primary role. Value Derived From : Dim_W_RESOURCE_HD_ID.PRIMARY_ROLE_OBJECT_ID
Resource General - (Resource) Resource ID Dimension A short code which uniquely identifies the resource. Value Derived From : Dim_W_RESOURCE_HD_ID.RESOURCE_ID
Resource General - (Resource) Resource Name Dimension The name of the resource Value Derived From : Dim_W_RESOURCE_HD_ID.RESOURCE_NAME
Resource General - (Resource) Title Dimension The title of the resource Value Derived From : Dim_W_RESOURCE_HD_ID.RESOURCE_TITLE
Resource General - (Resource) Resource Type Dimension Indicates whether the resource is labor, nonlabor, or material. Value Derived From : Dim_W_RESOURCE_HD_ID.RESOURCE_TYPE
Resource Codes - (Resource)     Resource Codes
Resource Location - (Resource)     Resource Location  
Resource Location - (Resource) Address Line 1 Dimension The first line of the address Value Derived From : Dim_W_RESOURCE_HD_ID.ADDRESS_LINE1
Resource Location - (Resource) Address Line 2 Dimension The second line of the address Value Derived From : Dim_W_RESOURCE_HD_ID.ADDRESS_LINE2
Resource Location - (Resource) City Name Dimension The city name for this Location Value Derived From : Dim_W_RESOURCE_HD_ID.CITY_NAME
Resource Location - (Resource) Country Code Dimension The country code for this Location Value Derived From : Dim_W_RESOURCE_HD_ID.COUNTRY_CODE
Resource Location - (Resource) Country Name Dimension The country name for this Location Value Derived From : Dim_W_RESOURCE_HD_ID.COUNTRY_NAME
Resource Location - (Resource) Latitude Dimension The latitude for this Location Value Derived From : Dim_W_RESOURCE_HD_ID.LATITUDE
Resource Location - (Resource) Location Name Dimension The name of the location Value Derived From : Dim_W_RESOURCE_HD_ID.LOCATION_NAME
Resource Location - (Resource) Location Type Dimension Location Type Value Derived From : Dim_W_RESOURCE_HD_ID.LOCATION_TYPE
Resource Location - (Resource) Longitude Dimension The longitude for this Location Value Derived From : Dim_W_RESOURCE_HD_ID.LONGITUDE
Resource Location - (Resource) Municipality Name Dimension The municipality name for this Location Value Derived From : Dim_W_RESOURCE_HD_ID.MUNICIPALITY_NAME
Resource Location - (Resource) Postal Code Dimension The postal code for this Location Value Derived From : Dim_W_RESOURCE_HD_ID.POSTAL_CODE
Resource Location - (Resource) State/Province Code Dimension The state abbreviation for this Location Value Derived From : Dim_W_RESOURCE_HD_ID.STATE_CODE
Resource Location - (Resource) State/Province Name Dimension The state name for this Location Value Derived From : Dim_W_RESOURCE_HD_ID.STATE_NAME
           
Time Folder          
Time Interval     Interval  
Time Interval Interval End Date Dimension The end date of the Interval (1/8/2013 12:00am) Value Derived From : Dim_W_INTERVAL_D_Interval.END_DATE
Time Interval Interval Name Dimension Interval Name (2013-W01) Value Derived From : Dim_W_INTERVAL_D_Interval.INTERVAL_NAME
Time Interval Interval Start Date Dimension The start date of the Interval (1/1/2013 12:00am) Value Derived From : Dim_W_INTERVAL_D_Interval.START_DATE
           
           
           
           
           
           
           
           
           
           
           
           
           
           
           
           
           
           
           
           
           
           
           
           
           
           
           
           
           
           
           
           
           
           
           
           
           
           
           
           
           
Fact - Primavera - Burn Down Folder          
Fact - Primavera - Burn Down Metrics     Metrics  
Fact - Primavera - Burn Down Metrics Actual Reported Finish (Yesterday) Fact The number of activities whose Actual Finish date was one day ago Value Derived From : Fact_W_ACTIVITY_WORK_DOWN_HF_WDAct.YDA_REPORTED_COMPLETE_CNT
Fact - Primavera - Burn Down Metrics Actual Reported Starts (Yesterday) Fact The number of activities whose Actual Start date was one day ago Value Derived From : Fact_W_ACTIVITY_WORK_DOWN_HF_WDAct.YDA_REPORTED_START_CNT
Fact - Primavera - Burn Down Metrics Baseline Completed Count Fact The number of activities in Burn Down snapshot that are completed during this time interval Value Derived From : Fact_W_ACTIVITY_WORK_DOWN_HF_WDAct.BASE_COMPLETE_CNT
Fact - Primavera - Burn Down Metrics Baseline In Progress Count Fact The number of activities in Burn Down snapshot that are in progress during this time interval Value Derived From : Fact_W_ACTIVITY_WORK_DOWN_HF_WDAct.BASE_IN_PROGRESS_CNT
Fact - Primavera - Burn Down Metrics Baseline Not Started Count Fact The number of activities in Burn Down snapshot that are not started during this time interval Value Derived From : Fact_W_ACTIVITY_WORK_DOWN_HF_WDAct.BASE_NOT_START_CNT
Fact - Primavera - Burn Down Metrics Baseline Planned Finish Date Fact Activity Planned Finish Date as of baseline(T-0) date Value Derived From : Fact_W_ACTIVITY_WORK_DOWN_HF_WDAct.BL_PLANNED_FINISH_DATE
Fact - Primavera - Burn Down Metrics Completed Count Fact The number of activities that are completed during this time interval Value Derived From : Fact_W_ACTIVITY_WORK_DOWN_HF_WDAct.COMPLETE_CNT
Fact - Primavera - Burn Down Metrics Emergent Remaining Count Fact The number of remaining In Progress and Not Started activities that did not exist in the Burn Down snapshot Value Derived From : Fact_W_ACTIVITY_WORK_DOWN_HF_WDAct.EMERGENT_REMAINING_CNT
Fact - Primavera - Burn Down Metrics In Progress Count Fact The number of activities that are in progress during this time interval Value Derived From : Fact_W_ACTIVITY_WORK_DOWN_HF_WDAct.IN_PROGRESS_CNT
Fact - Primavera - Burn Down Metrics Emergent Count Fact The number of activities added that are not in Burn Down snapshot sum(Fact_W_ASSIGNMENT_WORK_DOWN_HF_WDA.EMERGENT_REMAINING_CNT)
Fact - Primavera - Burn Down Metrics Non-Emergent Remaining Count Fact The number of remaining In Progress and Not Started activities that existed in the Burn Down snapshot Value Derived From : Fact_W_ACTIVITY_WORK_DOWN_HF_WDAct.NON_EMERGENT_REMAINING_CNT
Fact - Primavera - Burn Down Metrics Not Scheduled and Completed Count Fact The number of activities that were not scheduled to be completed based on the Burn Down snapshot and were actually completed during this time interval Value Derived From : Fact_W_ACTIVITY_WORK_DOWN_HF_WDAct.NOT_SCHEDULED_COMPLETED_CNT
Fact - Primavera - Burn Down Metrics Not Started Count Fact The number of activities that are not started during this time interval Value Derived From : Fact_W_ACTIVITY_WORK_DOWN_HF_WDAct.NOT_START_CNT
Fact - Primavera - Burn Down Metrics Schedule Freeze Planned Finish Date Fact Activity Planned Finish Date as of Schedule Freeze date Value Derived From : Fact_W_ACTIVITY_WORK_DOWN_HF_WDAct.TF_PLANNED_FINISH_DATE
Fact - Primavera - Burn Down Metrics Scheduled and Completed Count Fact The number of activities that were scheduled to be completed based on the Burn Down snapshot and were actually completed during this time interval Value Derived From : Fact_W_ACTIVITY_WORK_DOWN_HF_WDAct.SCHEDULED_COMPLETED_CNT
Fact - Primavera - Burn Down Metrics Scheduled Finishes (Yesterday) Fact The number of activities whose Planned Finish date was one day ago Value Derived From : Fact_W_ACTIVITY_WORK_DOWN_HF_WDAct.YDA_SCHEDULED_COMPLETE_CNT
Fact - Primavera - Burn Down Metrics Scheduled Finishes Today Fact The number of activities whose Finish date is today Value Derived From : Fact_W_ACTIVITY_WORK_DOWN_HF_WDAct.TODAY_SCHEDULED_COMPLETE_CNT
Fact - Primavera - Burn Down Metrics Scheduled Finishes to Date Fact The number of activities whose Finish date is on or before the project Data Date Value Derived From : Fact_W_ACTIVITY_WORK_DOWN_HF_WDAct.TO_DATE_SCHEDULED_COMPLETE_CNT
Fact - Primavera - Burn Down Metrics Scheduled Starts (Yesterday) Fact The number of activities whose Planned Start date was one day ago Value Derived From : Fact_W_ACTIVITY_WORK_DOWN_HF_WDAct.YDA_SCHEDULED_START_CNT
Fact - Primavera - Burn Down Metrics Scheduled and Not Completed Count Fact The number of activities that were scheduled to be completed based on the Burn Down snapshot and were not completed during this time interval Value Derived From : Fact_W_ACTIVITY_WORK_DOWN_HF_WDAct.SCHEDULED_NOT_COMPLETED_CNT
Fact - Primavera - Burn Down Metrics Update Time Fact The database time this ETL run started Value Derived From : Fact_W_ACTIVITY_WORK_DOWN_HF_WDAct.UPDATE_TS
Fact - Primavera - Burn Down Units     Units  
Fact - Primavera - Burn Down Units Actual Period Units Fact The actual number of units incurred of current period Value Derived From : Fact_W_ASSIGNMENT_WORK_DOWN_HF_WDA.ACTUAL_PERIOD_UNITS
Fact - Primavera - Burn Down Units Actual Units Fact The actual number of units incurred Value Derived From : Fact_W_ASSIGNMENT_WORK_DOWN_HF_WDA.ACTUAL_UNITS
Fact - Primavera - Burn Down Units Actual Units Burn Fact The actual units distributed over the activity duration Value Derived From : Fact_W_ASSIGNMENT_WORK_DOWN_HF_WDA.ACTUAL_UNITS_BURN
Fact - Primavera - Burn Down Units Baseline Units Fact Planned Units from the Burn Down snapshot Value Derived From : Fact_W_ASSIGNMENT_WORK_DOWN_HF_WDA.BASELINE_UNITS
Fact - Primavera - Burn Down Units Baseline Remaining Units Burn Fact The expected remaining units distributed over the activity duration based on Burn Down snapshot sum(Fact_W_ASSIGNMENT_WORK_DOWN_HF_WDA.REMAINING_UNITS_BURN)
Fact - Primavera - Burn Down Units At Completion Units Fact The sum of the Actual Units plus Remaining Units sum(Fact_W_ASSIGNMENT_WORK_DOWN_HF_WDA.COMPLETE_UNITS)
Fact - Primavera - Burn Down Units Emergent Remaining Units Burn Fact Emergent activity remaining units distributed over the activity duration Value Derived From : Fact_W_ASSIGNMENT_WORK_DOWN_HF_WDA.EMERGENT_UNITS_BURN
Fact - Primavera - Burn Down Units Non-Emergent Remaining Units Burn Fact Non-Emergent activity remaining units distributed over the activity duration Value Derived From : Fact_W_ASSIGNMENT_WORK_DOWN_HF_WDA.NON_EMERGENT_UNITS_BURN
Fact - Primavera - Burn Down Units Remaining Units Fact The remaining units of work to be performed by the resource on the activity. Calculated as Planned Units minus Actual Units. Value Derived From : Fact_W_ASSIGNMENT_WORK_DOWN_HF_WDA.REMAINING_UNITS
Fact - Primavera - Burn Down Units Remaining Units Burn Fact The remaining units distributed over the activity duration Value Derived From : Fact_W_ASSIGNMENT_WORK_DOWN_HF_WDA.REMAINING_UNITS_BURN