P6 - Resource Utilization / Primavera - Resource Utilization

Description: Use this subject area to analyze resource utilization details including actual, available, planned, remaining, at completion, and resource limit units.

Folder Subfolder Field Name Dimension/ Fact / Lookup Description Values Derived From / Calculated By
Fact - Primavera - Resource Utilization Metrics     Metrics  
Fact - Primavera - Resource Utilization Metrics # Of Resources Fact # Of Resources count(distinct Fact_W_RESOURCE_LIMIT_F_Resource_Limit.RESOURCE_WID)
Fact - Primavera - Resource Utilization Usage/Capacity     Usage/Capacity  
Fact - Primavera - Resource Utilization Usage/Capacity Actual Units Fact The actual number of units incurred Value Derived From : Fact_W_RESOURCE_LIMIT_F_Resource_Limit.ACTUAL_UNITS
Fact - Primavera - Resource Utilization Usage/Capacity At Completion Units Fact The sum of the actual units and remaining units for the resource assignment on the activity. Calculated as Actual Units plus Remaining Units. P6Core."Fact - Resource Utilization"."Actual Units" + "P6Core"."Fact - Resource Utilization"."Remaining Units"
Fact - Primavera - Resource Utilization Usage/Capacity Available Units Fact Available Units Value Derived From : Fact_W_RESOURCE_LIMIT_F_Resource_Limit.AVAILABLE_UNITS
Fact - Primavera - Resource Utilization Usage/Capacity Limit Fact Limit Value Derived From : Fact_W_RESOURCE_LIMIT_F_Resource_Limit.LIMIT
Fact - Primavera - Resource Utilization Usage/Capacity Planned Units Fact The planned units of work for the resource assignment on the activity. Value Derived From : Fact_W_RESOURCE_LIMIT_F_Resource_Limit.PLANNED_UNITS
Fact - Primavera - Resource Utilization Usage/Capacity Remaining Units Fact The remaining units of work to be performed by the resource on the activity. Calculated as Planned Units minus Actual Units. Value Derived From : Fact_W_RESOURCE_LIMIT_F_Resource_Limit.REMAINING_UNITS