P6 - Work Planning / Primavera - Work Planning

Description: Use this subject area to analyze weekly work planning process by comparing project scope and schedule freeze dates each week. In this way, potential risks such as activity planned start date changes can quickly be identified. This subject area requires project specific UDF configuration in P6.

Folder Subfolder Field Name Dimension/ Fact / Lookup Description Values Derived From / Calculated By
Fact - Primavera - Spread Snapshot History Metrics     Metrics  
Fact - Primavera - Spread Snapshot History Metrics Actual Finish Fact The date on which the activity actually finished Value Derived From : Fact_W_WORK_PROCESS_HF_WorkProcess.CS_FINISHED
Fact - Primavera - Spread Snapshot History Metrics Actual Start Fact The date on which the activity actually started Value Derived From : Fact_W_WORK_PROCESS_HF_WorkProcess.CS_STARTED
Fact - Primavera - Spread Snapshot History Metrics Previous Snapshot Finished Fact Activities that were Scheduled to Finish since the previous week's Snapshot and Actually finished during their Scheduled week Value Derived From : Fact_W_WORK_PROCESS_HF_WorkProcess.PS_FINISHED
Fact - Primavera - Spread Snapshot History Metrics Previous Snapshot Lost Record Fact Lost Activities since the previous week's Snapshot Value Derived From : Fact_W_WORK_PROCESS_HF_WorkProcess.PS_LOST_RECORD
Fact - Primavera - Spread Snapshot History Metrics Previous Snapshot New Record Fact New Activities since the previous week's Snapshot Value Derived From : Fact_W_WORK_PROCESS_HF_WorkProcess.PS_NEW_RECORD
Fact - Primavera - Spread Snapshot History Metrics Previous Snapshot Planned Date Change Fact Planned Date Changes to Activities since the previous week's Snapshot Value Derived From : Fact_W_WORK_PROCESS_HF_WorkProcess.PS_PLANNED_DATE_CHANGE
Fact - Primavera - Spread Snapshot History Metrics Previous Snapshot Scheduled Finish Fact Activities Scheduled to Finish since the previous week's Snapshot Value Derived From : Fact_W_WORK_PROCESS_HF_WorkProcess.PS_SCHEDULED_FINISH
Fact - Primavera - Spread Snapshot History Metrics Previous Snapshot Scheduled Start Fact Activities Scheduled to Start since the previous week's Snapshot Value Derived From : Fact_W_WORK_PROCESS_HF_WorkProcess.PS_SCHEDULED_START
Fact - Primavera - Spread Snapshot History Metrics Previous Snapshot Started Fact Activities that were Scheduled to Start since the previous week's Snapshot and Actually started during their Scheduled week Value Derived From : Fact_W_WORK_PROCESS_HF_WorkProcess.PS_STARTED
Fact - Primavera - Spread Snapshot History Metrics Schedule Freeze Finished Fact Activities that were Scheduled to Finish as of Schedule Freeze and Actually finished during their Scheduled week Value Derived From : Fact_W_WORK_PROCESS_HF_WorkProcess.TF_FINISHED
Fact - Primavera - Spread Snapshot History Metrics Schedule Freeze Lost Record Fact Lost Activities since the Schedule Freeze Snapshot Value Derived From : Fact_W_WORK_PROCESS_HF_WorkProcess.TF_LOST_RECORD
Fact - Primavera - Spread Snapshot History Metrics Schedule Freeze New Record Fact New Activities added since the Schedule Freeze Snapshot Value Derived From : Fact_W_WORK_PROCESS_HF_WorkProcess.TF_NEW_RECORD
Fact - Primavera - Spread Snapshot History Metrics Schedule Freeze Planned Date Change Fact Planned Date Changes to Activities since the Schedule Freeze Snapshot Value Derived From : Fact_W_WORK_PROCESS_HF_WorkProcess.TF_PLANNED_DATE_CHANGE
Fact - Primavera - Spread Snapshot History Metrics Schedule Freeze Scheduled Finished Fact Activities Scheduled to Finish as of Schedule Freeze Snapshot Value Derived From : Fact_W_WORK_PROCESS_HF_WorkProcess.TF_SCHEDULED_FINISH
Fact - Primavera - Spread Snapshot History Metrics Schedule Freeze Scheduled Start Fact Activities Scheduled to Start as of Schedule Freeze Snapshot Value Derived From : Fact_W_WORK_PROCESS_HF_WorkProcess.TF_SCHEDULED_START
Fact - Primavera - Spread Snapshot History Metrics Schedule Freeze Started Fact Activities that were Scheduled to Start as of Schedule Freeze and Actually started during their Scheduled week Value Derived From : Fact_W_WORK_PROCESS_HF_WorkProcess.TF_STARTED
Fact - Primavera - Spread Snapshot History Metrics Scope Freeze Scheduled Finish Fact Activities Scheduled to Finish as of Scope Freeze Snapshot Value Derived From : Fact_W_WORK_PROCESS_HF_WorkProcess.SF_SCHEDULED_FINISH
Fact - Primavera - Spread Snapshot History Metrics Scope Freeze Finished Fact Activities that were Scheduled to Finish as of Scope Freeze and Actually finished during their Scheduled week Value Derived From : Fact_W_WORK_PROCESS_HF_WorkProcess.SF_FINISHED
Fact - Primavera - Spread Snapshot History Metrics Scope Freeze Lost Record Fact Lost Activities since the Scope Freeze Snapshot Value Derived From : Fact_W_WORK_PROCESS_HF_WorkProcess.SF_LOST_RECORD
Fact - Primavera - Spread Snapshot History Metrics Scope Freeze New Record Fact New Activities since the Scope Freeze Snapshot Value Derived From : Fact_W_WORK_PROCESS_HF_WorkProcess.SF_NEW_RECORD
Fact - Primavera - Spread Snapshot History Metrics Scope Freeze Planned Date Change Fact Planned Date Changes to Activities since the Scope Freeze Snapshot Value Derived From : Fact_W_WORK_PROCESS_HF_WorkProcess.SF_PLANNED_DATE_CHANGE
Fact - Primavera - Spread Snapshot History Metrics Scope Freeze Scheduled Start Fact Activities Scheduled to Start as of Scope Freeze Snapshot Value Derived From : Fact_W_WORK_PROCESS_HF_WorkProcess.SF_SCHEDULED_START
Fact - Primavera - Spread Snapshot History Metrics Scope Freeze Started Fact Activities that were Scheduled to Start as of Scope Freeze and Actually started during their Scheduled week Value Derived From : Fact_W_WORK_PROCESS_HF_WorkProcess.SF_STARTED
           
Activity Folder          
Activity Dates - (Activity)     Activity Dates  
Activity Dates - (Activity) Actual Finish Dimension The date on which the activity actually finished Value Derived From : Dim_W_ACTIVITY_HD_ID.ACTUAL_FINISH_DATE
Activity Dates - (Activity) Actual Start Dimension The date on which the activity actually started Value Derived From : Dim_W_ACTIVITY_HD_ID.ACTUAL_START_DATE
Activity Dates - (Activity) Baseline Project Finish Dimension The Project Baseline Planned Finish Date. Value Derived From : Dim_W_ACTIVITY_HD_ID.BASELINE_FINISH_DATE
Activity Dates - (Activity) Baseline Project Start Dimension The Project Baseline Planned Start Date. Value Derived From : Dim_W_ACTIVITY_HD_ID.BASELINE_START_DATE
Activity Dates - (Activity) Data Date Dimension The current data date for the project. The project status is up to date as of the data date. The data date is modified when project actuals are applied. Value Derived From : Dim_W_ACTIVITY_HD_ID.DATA_DATE
Activity Dates - (Activity) Early Finish Dimension The earliest possible date the activity can finish. This date is calculated by the project scheduler based on activity relationships, schedule constraints, and resource availability. Value Derived From : Dim_W_ACTIVITY_HD_ID.EARLY_FINISH_DATE
Activity Dates - (Activity) Early Start Dimension The earliest possible date the remaining work for the activity can begin. This date is calculated by the project scheduler based on activity relationships, schedule constraints, and resource availability. Value Derived From : Dim_W_ACTIVITY_HD_ID.EARLY_START_DATE
Activity Dates - (Activity) Expected Finish Dimension The date the activity is expected to finish. Typically, this date is entered in the Timesheets module by the primary resource. Value Derived From : Dim_W_ACTIVITY_HD_ID.EXPECT_FINISH_DATE
Activity Dates - (Activity) External Early Start Dimension The External Early Start date is the earliest finish date of all lost external relationships. This field is populated only during import when a relationship is lost because it does not exist in the current database. This date may be used to calculate the start date of the current activity in place of the true relationship when scheduling. Value Derived From : Dim_W_ACTIVITY_HD_ID.EXTERNAL_EARLY_START_DATE
Activity Dates - (Activity) External Late Finish Dimension The External Late Finish date is the latest start date of all lost external relationships. This field is populated only during import when a relationship is lost because it does not exist in the current database. This date may be used to calculate the finish date of the current activity in place of the true relationship when scheduling. Value Derived From : Dim_W_ACTIVITY_HD_ID.EXTERNAL_LATE_FINISH_DATE
Activity Dates - (Activity) Finish Dimension The current finish date of the activity. Set to the activity remaining early finish date while the activity is not started or in progress, and the actual finish date once the activity is completed. Value Derived From : Dim_W_ACTIVITY_HD_ID.FINISH_DATE
Activity Dates - (Activity) Late Finish Dimension The latest possible date the activity must finish without delaying the project finish date. This date is calculated by the project scheduler based on activity relationships, schedule constraints, and resource availability. Value Derived From : Dim_W_ACTIVITY_HD_ID.LATE_FINISH_DATE
Activity Dates - (Activity) Late Start Dimension The latest possible date the remaining work for the activity must begin without delaying the project finish date. This date is calculated by the project scheduler based on activity relationships, schedule constraints, and resource availability. Value Derived From : Dim_W_ACTIVITY_HD_ID.LATE_START_DATE
Activity Dates - (Activity) Planned Finish Dimension The date the activity is scheduled to finish. This date is computed by the project scheduler but can be updated manually by the project manager. This date is not changed by the project scheduler after the activity has been started. Value Derived From : Dim_W_ACTIVITY_HD_ID.PLANNED_FINISH_DATE
Activity Dates - (Activity) Planned Start Dimension The date the activity is scheduled to begin. This date is computed by the project scheduler but can be updated manually by the project manager. This date is not changed by the project scheduler after the activity has been started. Value Derived From : Dim_W_ACTIVITY_HD_ID.PLANNED_START_DATE
Activity Dates - (Activity) Primary Constraint Date Dimension The constraint date for the activity, if the activity has a constraint. The activity's constraint type determines whether this is a start date or finish date. Activity constraints are used by the project scheduler. Value Derived From : Dim_W_ACTIVITY_HD_ID.PRIMARY_CONSTRAINT_DATE
Activity Dates - (Activity) Remaining Early Finish Dimension The date the remaining work for the activity is scheduled to finish. This date is computed by the project scheduler but can be updated manually by the project manager. Before the activity is started, the remaining finish date is the same as the planned finish date. This is the finish date that Progress Reporter users follow. Value Derived From : Dim_W_ACTIVITY_HD_ID.REMAINING_FINISH_DATE
Activity Dates - (Activity) Remaining Early Start Dimension The date the remaining work for the activity is scheduled to begin. This date is computed by the project scheduler but can be updated manually by the project manager. Before the activity is started, the remaining start date is the same as the planned start date. This is the start date that Progress Reporter users follow. Value Derived From : Dim_W_ACTIVITY_HD_ID.REMAINING_START_DATE
Activity Dates - (Activity) Remaining Late Finish Dimension Remaining late end date is calculated by the scheduler. Value Derived From : Dim_W_ACTIVITY_HD_ID.REMAINING_LATE_FINISH_DATE
Activity Dates - (Activity) Remaining Late Start Dimension Remaining late start date is calculated by the scheduler. Value Derived From : Dim_W_ACTIVITY_HD_ID.REMAINING_LATE_START_DATE
Activity Dates - (Activity) Resume Date Dimension The date progress is resumed on an activity. Value Derived From : Dim_W_ACTIVITY_HD_ID.RESUME_DATE
Activity Dates - (Activity) Schedule Freeze Date Dimension The activity schedule freeze date Value Derived From : Dim_W_ACTIVITY_HD_ID.SCHEDULE_FREEZE_DATE
Activity Dates - (Activity) Scope Freeze Date Dimension The activity scope freeze date Value Derived From : Dim_W_ACTIVITY_HD_ID.SCOPE_FREEZE_DATE
Activity Dates - (Activity) Secondary Constraint Date Dimension The second constraint date for the activity, if the activity has a constraint. Value Derived From : Dim_W_ACTIVITY_HD_ID.SECONDARY_CONSTRAINT_DATE
Activity Dates - (Activity) Start Dimension The current start date of the activity. Set to the activity remaining early start date while the activity is not started, and the actual start date once the activity is started. Value Derived From : Dim_W_ACTIVITY_HD_ID.START_DATE
Activity Dates - (Activity) Suspend Date Dimension The date progress is suspended on an activity. Value Derived From : Dim_W_ACTIVITY_HD_ID.SUSPEND_DATE
           
Project Folder          
Project Dates - (Project)     Project Dates  
Project Dates - (Project) Anticipated Finish Dimension Anticipated finish date of WBS, Project and EPS elements. User-entered - not dependent upon any other fields. If there are no children, the anticipated finish date will be the Finish date displayed in the columns. Value Derived From : Dim_W_PROJECT_HD_ID.ANTICIPATED_FINISH_DATE
Project Dates - (Project) Anticipated Start Dimension Anticipated start date of WBS, Project and EPS elements. User-entered - not dependent upon any other fields. If there are no children, the anticipated start date will be the Start date displayed in the columns. Value Derived From : Dim_W_PROJECT_HD_ID.ANTICIPATED_START_DATE
Project Dates - (Project) Data Date Dimension The current data date for the project. The project status is up to date as of the data date. The data date is modified when project actuals are applied. Value Derived From : Dim_W_PROJECT_HD_ID.DATA_DATE
Project Dates - (Project) Date Added Dimension The date this activity was inserted. Value Derived From : Dim_W_PROJECT_HD_ID.ADD_DATE
Project Dates - (Project) Finish Dimension The current finish date of the activity. Set to the activity remaining early finish date while the activity is not started or in progress, and the actual finish date once the activity is completed. Value Derived From : Dim_W_PROJECT_HD_ID.PROJECT_FINISH_DATE
Project Dates - (Project) Forecast Finish Date Dimension An alternate end date to be optionally used by the scheduler (see Schedule dialog), which is set by the user by dragging the project bar in the Gantt Chart around while manually leveling the resource profile (in a resource analysis layout, tracking or PA). In User Preferences dialog, the user can choose to view remaining units for a resource based on the forecast dates or the remaining dates. Value Derived From : Dim_W_PROJECT_HD_ID.FORECAST_FINISH_DATE
Project Dates - (Project) Forecast Start Date Dimension An alternate start date to be optionally used by the scheduler (see Schedule dialog), which is set by the user by dragging the project bar in the Gantt Chart around while manually leveling the resource profile (in a resource analysis layout, tracking or PA). In the User Preferences dialog, the user can choose to view remaining units for a resource based on the forecast dates or the remaining dates. Value Derived From : Dim_W_PROJECT_HD_ID.FORECAST_START_DATE
Project Dates - (Project) Must Finish By Dimension The date by which all project activities must finish. If entered, it is used as the project late finish date by the project scheduler. Value Derived From : Dim_W_PROJECT_HD_ID.PROJECT_PLANNED_FINISH_DATE
Project Dates - (Project) Planned Start Dimension The date the activity is scheduled to begin. This date is computed by the project scheduler but can be updated manually by the project manager. This date is not changed by the project scheduler after the activity has been started. Value Derived From : Dim_W_PROJECT_HD_ID.PLANNED_START_DATE
Project Dates - (Project) Scheduled Finish Dimension The early finish date of the latest activity in the project, as computed by the project scheduler. Value Derived From : Dim_W_PROJECT_HD_ID.SCHEDULED_FINISH_DATE
Project Dates - (Project) Start Dimension The current start date of the activity. Set to the activity remaining early start date while the activity is not started, and the actual start date once the activity is started. Value Derived From : Dim_W_PROJECT_HD_ID.PROJECT_START_DATE