Activity types

Activity types control how an activity's duration and dates are calculated. Choose from six activity types:

  • Task dependent activity
  • Resource dependent activity
  • Level of effort activity
  • Start milestone activity
  • Finish milestone activity
  • WBS summary activity

Each activity must be assigned an activity type.