Cut and paste a work breakdown structure element

  1. Choose Project, WBS.
  2. Select the WBS element you want to cut and paste, then choose Edit, Cut.
  3. Select the WBS element to which you want to add the cut element, then choose Edit, Paste.

    Note:

    • When you cut and paste a WBS element, the element's activity assignments are also pasted.
    • When connected to a P6 EPPM database: When you cut and paste a WBS within the same project, the WBS, activities, and associated risks from P6 are moved; risks are not moved if you cut and paste the WBS to a different project.