Define milestones

  1. Choose Project, Activities.
  2. Select the activity you want to define as a start or finish milestone.
  3. Display Activity Details, then click the General tab.
  4. In the Activity Type field, select Start Milestone or Finish Milestone.

    Note:

    Milestones cannot have durations, time-based costs, or resource assignments.