Enter activity start and finish dates
- Choose Project, Activities.
- Select the activity whose start and finish dates you want to enter.
- Display Activity Details, then click the Status tab.
To enter the activity's start date, in the Started field, click

, then select a date.To enter the activity's actual start date, mark the Started checkbox, then type the actual start date in the Started field or click
to select a date.To enter the activity's finish date, in the Finished field, click
, then select a date.To enter the activity's actual finish date, mark the Finished checkbox, then type the actual finish date in the Finished field or click
to select a date.Note:
- Entering a start or finish date for an activity can push the activity out-of-sequence. If you want to be warned if the change you make could result in out-of-sequence progress, in the User Preferences dialog box, on the Assistance tab, mark the Warn about out-of-sequence activities option.
- When you enter a start or finish date, depending on your application settings, a dialog box may prompt you to enter a constraint. To accept the constraint, click Yes in the Confirmation dialog box. If you specify start and/or finish dates without applying Must Start On or Must Finish On constraints, the dates you enter may be changed when the project is scheduled.