Standard Work Week Tab of the Global Calendars Page

Overview

Use this tab to specify the length of work hours in a day or to calculate the total number of hours worked in a particular day.

Screen Elements

Work area

The typical work week that can be modified by day and hour. After choosing a calendar to be added while on the calendar tab, the Standard Work Week tab will display the similar template by days and hours.

"" Print

Opens the Print Options dialog box.

Day label

The name of each day.

Total Hours field

The total number of work hours for each day.

Calendar View area

Enables you to view a day, week, month, or year of the calendar to identify standard time, nonwork time and calendar exceptions.

Work Period display

Displays a box that represents each work period in a day. If you change the number of hours covered by the work period boxes for a day, P6 updates the Total Hours field.

Tip:

  • Modify the start day of the week in the Application Settings pane.
  • There can be multiple work period boxes displayed in one day.

Getting Here

  1. On the "" Navigation Menu, expand "" Administration and click Enterprise Data.
  2. On the Enterprise Data page, expand Global and click Global Calendars.
  3. On the Global Calendars page, click the Standard Work Week tab.