Configuring Resource Leveling Options and Priorities
Level resources in your project schedules to ensure that resource demand does not exceed resource availability. To handle scheduling conflicts that might occur during leveling, you can add priorities that specify which project or activity is leveled first. Before leveling, configure the options and priorities specified in the steps below.
To configure resource leveling options and priorities:
- On the
Navigation Menu, expand
Projects and click EPS. - On the EPS page, click
Customize View and click Columns.- On the Columns tab, expand the General section in the Available Columns list and double-click Project Leveling Priority to add it to the Selected Columns list and click Save and Apply.
- On the EPS page:
- On the
Navigation Menu, expand
Projects and click Activities. - On the Activities page, click
Customize View and select Columns.- On the Columns tab, expand the General section in the Available Columns list and double-click Activity Leveling Priority to add it to the Selected Columns list and click Save and Apply.
- On the Activities page:
Tip:
You cannot edit the Project Leveling Priority of a project if you do not have the appropriate security privileges or if the project is checked out or opened exclusively by another user.