Activity % Complete
Activity % Complete field
The percent of the activity that has been completed.
The calculation is based on the formula for the selected Percent Complete Type. The Percent Complete Type can be Units, Duration, Physical, or Scope.
If the selected activity's percent complete type is Duration, the percent complete is calculated as (Planned Duration minus Remaining Duration) divided by Planned Duration.
If the activity's percent complete type is Units, the percent complete is calculated as (Actual Labor Units plus Actual Nonlabor Units) divided by (Actual Labor Units plus Actual Nonlabor Units plus Remaining Labor Units plus Remaining Nonlabor Units).
If the activity's percent complete type is Physical, either the user records the percent complete manually or the field is set to calculate using steps. To calculate using steps, the Calculate Activity % Complete from activity steps option must be set in Project Preferences.
If the activity's percent complete type is Scope, the percent complete originates from Oracle Primavera Cloud and cannot be modified in P6.