Actual Overtime Units
Actual Overtime Units field
The actual overtime units worked by the resource on the activity.
This value is calculated from timesheets when project actuals are applied or can be entered directly by the project manager.
Actual Overtime Units field
The actual overtime units worked by the resource on the activity.
This value is calculated from timesheets when project actuals are applied or can be entered directly by the project manager.