Applying Actuals to a Project
Apply actuals to update progress on the currently selected projects as of the specified data date.
To apply actuals:
- On the
Navigation Menu, expand
Projects and click Activities. - On the Activities page:
Tip:
- Using the Project Scheduled Services page, you can configure scheduled services that have the application apply actuals automatically.
- These services are removed from the database based on the ASAP Cleanup Rate your P6 administrator specifies on the Configurations tab in P6 Administrator application. Once the time is met all ASAP jobs that have a status other than running or delegated will be removed from the table automatically. Running and delegated jobs will be removed if they are older than the cleanup rate or if they are older than one day, whichever is greater.