Assigning Resource Curves to Resource or Role Assignments from the Activities Page
You can assign a resource distribution curve to any resource or role assignment on activities with a duration type of Fixed Duration and Units/Time or Fixed Duration & Units. Resource usage and costs are distributed evenly during an activity unless you specify nonlinear distribution using curves.
To assign a resource curve:
- On the
Navigation Menu, expand
Projects and click Activities.
Tip:
- If you assign a resource curve to an assignment with a manual curve, the manually-entered future period values will be overwritten.
- Resource curves do not support expenses. The Accrual Type will continue to spread the expenses.
- If the Curve column is not available, add it to the detail window.
- You can also assign resource curves to resource or role assignments from the Resources Assignments page.