Budget At Completion
Budget At Completion field
The planned total cost through activity or project completion.
Calculated as Planned Labor Cost plus Planned Nonlabor Cost plus Planned Expense Cost plus Planned Material Cost.
Budget At Completion field
The planned total cost through activity or project completion.