P6 Team Member Interface Field Names

P6 field names are simplified for users in P6 Team Member interfaces. When communicating with your team members, be sure to use the correct terms when discussing dates and work units.

Note:

Users with a Team Member work distribution filter assigned see the same fields as an Activity Owner.

P6 Team Member Interfaces Field Names

P6 P6 Team Member Interfaces Available to...
Remaining Start Start By All
Actual Start Started All
Remaining Finish Finish By All
Actual Finish Finished All
Remaining Duration Remaining Duration All
Activity % Complete % Complete Activity owner and user assigned Team Member work distribution filter
Actual Units Time Spent Resource assignment
Actual Labor Units Time Spent (Labor) Activity owner and user assigned Team Member work distribution filter
Actual Nonlabor Units Time Spent (Nonlabor) Activity owner and user assigned Team Member work distribution filter
Remaining Units Time Left Resource assignment
Remaining Labor Units Time Left (Labor) Activity owner and user assigned Team Member work distribution filter
Remaining Nonlabor Units Time Left (Nonlabor) Activity owner and user assigned Team Member work distribution filter
Expected Finish Expected Finish Activity owner and user assigned Team Member work distribution filter