Configuring Advanced Scheduling Options

Configure advanced scheduling options to define float paths.

To configure advanced scheduling options:

  1. On the "" Navigation Menu, expand "" Projects and click Activities.
  2. On the Activities page:
    1. Click Schedule....
    2. In the Schedule dialog box, click the Advanced tab.
    3. On the Advanced tab:
      • Select the Calculate Multiple Float Paths option.
      • Select Total Float or Free Float.
      • Enter or select a value for each field.
      • Click Save.

Tip:

  • You can select any activity in the Display Multiple Float Paths ending with activity dialog box; however, typically this activity is a milestone or some other major activity in the project schedule.
  • To optimize performance, type a low number (10 or less) in the Specify the number of paths to calculate field.