Configuring General Activity Information

You can configure some of the general information for activities, including Activity Type, Duration Type, and Percent Complete Type.

Note:

If P6 is integrated with Oracle Primavera Cloud for task integration, do not change the Activity IDs of activities in integrated projects.

To configure general activity information:

  1. On the "" Navigation Menu, expand "" Projects and click Activities.
  2. On the Activities page, select an activity and click the General detail window.
    1. In the General detail window, configure the activity details to represent the information you want to display for that activity.
    2. Click Save.