Configuring General Activity Information
You can configure some of the general information for activities, including Activity Type, Duration Type, and Percent Complete Type.
Note:
If P6 is integrated with Oracle Primavera Cloud for task integration, do not change the Activity IDs of activities in integrated projects.
To configure general activity information:
- On the
Navigation Menu, expand
Projects and click Activities. - On the Activities page, select an activity and click the General detail window.
- In the General detail window, configure the activity details to represent the information you want to display for that activity.