Creating Baselines
Create baselines to measure project performance.
To create a baseline:
- On the
Navigation Menu, expand
Projects and click Activities or EPS. - On the Activities or EPS page
Tip:
- The application automatically assigns the baseline a name based on the selected project. For example, if you select Project A, the application will name the newly created baseline "A - B1".
- Specify the default Project Baseline and User's Primary Baseline by selecting from the list of available baselines for each project in the table on the Baselines dialog box.
- Click Convert a Project to Baseline and select a project to convert a project into a baseline.
- Select a baseline and click Restore a Baseline to remove the baseline and make it a project.
- When you create a new baseline, the Publish option is switched off by default.