Creating Risk Scoring Matrices
Create a risk scoring matrix to perform qualitative analysis on project risks. Project risk is assessed based on the thresholds defined in the risk scoring matrix.
Before creating a risk scoring matrix, you need to first define risk thresholds.
To create a risk scoring matrix:
- On the
Navigation Menu, expand
Administration and click Enterprise Data. - On the Enterprise Data page, expand Risks and choose Risk Scoring Matrices.
- On the Risk Scoring Matrices page:
- Click
Add. - In the Name field, click and type a unique name.
- In the Matrix Size field, double-click and click
Select.
- Click
- In the Select Matrix Size dialog box:
- On the Risk Scoring Matrices page, double-click in the Probability Threshold field and click
Select. - In the Select Probability Threshold dialog box, choose a probability and click OK.
- On the Risk Scoring Matrices page, double-click in the Schedule Impact Thresholds field and click
Select. - In the Select Schedule Impact Thresholds dialog box:
- Select a Schedule Impact and click Select.
- Select any additional impacts and click Select.
- On the Risk Scoring Matrices page, double-click in the Cost Impact Thresholds field and click
Select. - In the Select Cost Impact Thresholds dialog box:
- Select a Cost Impact and click Select.
- Select any additional impacts and click Select.
- On the Risk Scoring Matrices page, double-click in the Tolerance Threshold field and click
Select. - In the Select Tolerance Threshold dialog box, choose a tolerance and click OK.
- On the Risk Scoring Matrices page, double-click in the Risk Scoring Method field and select a risk scoring method from the list.
- In the Description detail window, type a description of the risk scoring matrix.
- On the Risk Scoring Matrices page, click Save.