Creating Risk Thresholds
Create risk thresholds to use when creating a risk scoring matrix. When creating risk thresholds, you must define the probability threshold, cost impact threshold by percentage or value, schedule impact threshold by percentage or value, and tolerance threshold. You can also define as many user-defined impacts as necessary.
To create risk thresholds:
Tip:
The Cost Impact by percentage and Schedule Impact by percentage options allow you to assess risk without having to define absolute values. This enables you to use the same risk scoring matrix across multiple projects.