Early Finish
Early Finish field
The earliest possible date the activity can finish. Early finish dates can change as the project progresses and changes are made to the project management plan.
This date is calculated based on network logic, schedule constraints, and resource availability. If you schedule a project using Retained Logic this date will always be visible, even if an activity is completed.